The National Highway Authority of India (NHAI) sought to acquire land for the widening of NH‑211 and, after the Competent Authority fixed compensation, the aggrieved landowners invoked Section 3G(5) of the National Highways Act to refer the dispute to arbitration. The arbitrator enhanced the …
The National Highway Authority of India (NHAI) appealed ten arbitration awards concerning land acquisition for the widening of National Highway No. 211, alleging that the arbitrators exceeded their statutory mandate by issuing awards after the twelve‑month period prescribed in Section 29A of the …
The National Highways Authority of India filed a batch of appeals under Section 37 of the Arbitration and Conciliation Act, 1996, challenging the Principal District Judge, Aurangabad's common judgment dated 16/10/2025 dismissing its Section 34 applications and upholding arbitral awards. Lands in …
The appellant, a construction contractor, entered into a contract with the Rajasthan Housing Board for the construction of houses and later claimed non‑payment of escalation costs. Clause 23 of the contract provided for a Standing Committee to settle disputes, but the Board failed to constitute such …
The respondent, Shapoorji Pallonji and Company Private Limited (SPCPL), filed counter-claims in an arbitration initiated by Black Canyon SEZ Pvt. Ltd. (BCSPL) against BCSPL and two non-signatory entities, ASF Buildtech Private Limited (ABPL) and ASF Insignia SEZ Pvt. Ltd. (AISPL), invoking the group …
International Seaport Dredging Pvt Ltd entered into a dredging contract with Kamarajar Port Limited, a statutory undertaking, which later gave rise to disputes and arbitration. The arbitral tribunal awarded the appellant approximately Rs 21.07 crore with interest and costs, and the respondent sought …
Rohan Builders sought an extension of time under Section 29A of the Arbitration and Conciliation Act, 1996 after the statutory twelve‑month period (or the six‑month consent‑based extension) for making an arbitral award had expired. The Calcutta High Court had held that such an application was not …
The Delhi Metro Rail Corporation (DMRC) and Delhi Airport Metro Express Private Ltd (DAMEPL) entered into a 2008 concession agreement for the Delhi Airport Metro project. DAMEPL alleged safety defects, issued a cure notice, and later terminated the agreement; an arbitral tribunal awarded substantial …
The appellant, a civil engineering contractor, entered into a contract with the Karnataka State Public Works Department and later sought arbitration for alleged delays and non‑payment, obtaining an award of Rs.14,68,239 with 18% interest. The Civil Judge, invoking Section 34 of the Arbitration and …
Lombardi Engineering, a Swiss design consultancy, entered into a contract with Uttarakhand Vidyut Nigam Ltd for a hydro‑electric project, which was later transferred from UPDCC to the respondent. After the respondent terminated the contract, Lombardi invoked the arbitration clause in the General …
The appellant, a construction firm, entered into a contract with the Engineer-in-Chief, received full payment, and issued a notice invoking the arbitration clause on 26‑12‑2013. It later filed an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 on 27‑04‑2016, after the …
Gujarat Composite Ltd. entered into a licence agreement with A Infrastructure Ltd. in 2005 that contained an arbitration clause, and later entered into a tripartite loan agreement with the same party and Bank of Baroda that lacked any arbitration provision. Disputes arose over possession, loan …
NTPC Ltd. and SPML Infra Ltd. entered into a contract for installation services. After SPML completed the work, NTPC released the final payment but retained SPML's bank guarantees, linking their release to disputes in other projects. The parties settled the matter through a Settlement Agreement that …
Ellora Paper Mills Ltd entered into a supply contract with the State of Madhya Pradesh and, after a dispute, the parties were referred to an arbitral tribunal called the Stationery Purchase Committee, which was composed entirely of state officers. The appellant sought termination of that tribunal …
The dispute arose from a settlement deed between Ratnam Sudesh Iyer (appellant) and Jackie Kakubhai Shroff (respondent) concerning the sale of shares in Atlas Equifin Private Limited. The deed required the respondent to withdraw criminal complaints and, in return, receive US$1.5 million in escrow …
DLF Home Developers Ltd (DHDL) entered into share purchase agreements (SPAs) with Rajapura Homes Pvt Ltd and Southern Homes Pvt Ltd, and subsequently executed two Construction Management Service Agreements (RCMA and SCMA) to carry out post‑closing construction obligations. DHDL claimed that the …
Arcelor Mittel Nippon Steel India Ltd. and Essar Bulk Terminal Ltd. entered into a cargo‑handling agreement containing an arbitration clause. The appellant invoked the clause, the respondent claimed the dispute was non‑arbitrable and filed Section 9 applications for interim relief in the Commercial …
The case concerned disputes arising under the Micro, Small and Medium Enterprises Development Act, 2006 (MSMED Act) where a supplier (Silpi Industries) claimed unpaid amounts from Kerala State Road Transport Corporation (KSRTC) and the corporation raised counter‑claims. The issues before the Supreme …
The dispute arose when BSNL (appellant) withheld Rs.99.70 crore from Nortel (respondent) after completing a telecom tender. Nortel claimed the amount in May 2014, which BSNL rejected on 4 August 2014. After more than five years, Nortel invoked the arbitration clause on 29 April 2020 and sought …
Pravin Electricals alleged that no consultancy agreement dated 7 July 2014 existed with Galaxy Infra, while Galaxy claimed such an agreement, containing an arbitration clause, was executed and sought appointment of a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996. …
Deccan Paper Mills entered into a development agreement with Ashray, which was later assigned to Regency Mahavir Properties containing an arbitration clause. Deccan alleged fraud by a partner of Regency and filed a suit under the Specific Relief Act, seeking cancellation of the 2006 agreement and a …
The petitioner, Mankastu Impex Private Limited, an Indian distributor of air‑quality monitors, entered into a Memorandum of Understanding with AirVisual Limited, a Hong Kong company, appointing it as exclusive distributor in India. After AirVisual was acquired by IQAir AG, which refused to honour …
The Supreme Court dismissed the appeals of Vijay Karia and others against the Bombay High Court’s order enforcing four LCIA awards arising from a joint‑venture dispute with Prysmian Cavi E Sistemi SRL. The Court held that none of the grounds pleaded under Section 48 of the Arbitration and …
The Central Organisation for Railway Electrification (CORE) terminated a Rs 165‑crore work contract with M/s ECI‑SPIC‑SMO‑MCML (JV) and the contractor invoked the arbitration clause. The parties' contract and the modified Clause 64 of the General Conditions of Contract required a three‑member …
The Supreme Court examined a batch of writ petitions filed by Hindustan Construction Company Ltd seeking to strike down Section 87 of the Arbitration and Conciliation (Amendment) Act, 2019 and the deletion of Section 26 of the 2015 Amendment, arguing that they revived an automatic‑stay of arbitral …
The Union of India (Railways) awarded civil engineering contracts to Pradeep Vinod Construction Company, which later claimed additional payments despite having signed final bills and supplementary agreements indicating full settlement. The contractor invoked the arbitration clause in Clause 64 of …
Canara Nidhi Ltd. advanced a Rs.50 lakh loan secured by mortgage and a demand promissory note, which the borrower M. Shashikala failed to repay, leading to an arbitral award of Rs.63.82 lakh. Shashikala filed an application under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside …
The appeal concerned the interpretation of Section 11(6A) of the Arbitration and Conciliation Act, 1996, introduced by the 2015 amendment and later omitted by the 2019 amendment. The appellant argued that the Supreme Court or High Court must still examine the existence of an arbitration agreement …
The National Highways Authority of India (NHAI) and Gayatri Jhansi Roadways Limited entered into a 2006 contract that contained a detailed fee schedule for arbitrators. After a dispute arose in 2017, NHAI invoked a newer NHAI circular (dated 01‑06‑2017) that amended the fee amounts, while the …
The National Highways Authority of India (NHAI) awarded a construction contract to Ssangyong Engineering & Construction Co. Ltd., which included a price‑adjustment formula based on the Wholesale Price Index (WPI) old series. When the Ministry of Industrial Development stopped publishing the old …
The Union of India (appellant) and several contractors, including Parmar Construction Company (respondent), entered into railway construction contracts containing an arbitration clause (clause 64). After completing work, the contractors submitted final bills with a "No Claim" certificate, but later …
The appellant, a coal buyer, entered into several sale orders under Coal India Ltd.'s 2007 e‑auction scheme, which contained an arbitration clause (Clause 11.12). After the appellant was deemed to have breached the scheme and his earnest money deposit was forfeited, he invoked the arbitration …
The dispute arose from a contract between Rajasthan Small Industries Corporation Ltd (RSIC) and M/s Ganesh Containers Movers Syndicate, which contained a clause appointing the Managing Director (MD) of RSIC or his nominee as the sole arbitrator. After several delays and changes of arbitrators, the …
Emaar MGF Land Ltd. (appellant) entered into a buyer's agreement with Aftab Singh (respondent) that contained an arbitration clause under the Arbitration and Conciliation Act, 1996. Singh filed a complaint before the National Consumer Disputes Redressal Commission (NCDRC) invoking the Consumer …
The appellant, a construction contractor, entered into a contract with the State of Himachal Pradesh that contained Clause 65, which stipulated that any dispute would be referred to a sole arbitrator appointed by the Engineer‑in‑Chief. When a dispute arose, the Chief Engineer appointed the …
The Board of Control for Cricket in India filed a Section 34 challenge to arbitral awards dated June 2015, and the award creditors sought execution. The award debtor argued that the pre‑amended Section 36 imposed an automatic stay on execution until the Section 34 petition was decided, while the …
Aravali Power Company Pvt. Ltd. (appellant) and M/s. Era Infra Engineering Ltd. (respondent) entered into a contract for constructing a township for a thermal power project, which contained an arbitration clause (Clause 56) stipulating that disputes be referred to the Project In‑charge or, failing …
The dispute arose from a fourth arbitration between HRD Corporation and GAIL (India) Ltd. over a long‑term wax supply contract. The appellant challenged the appointments of two arbitrators, Justice K.K. Lahoti and Justice K. Doabia, invoking Sections 12 and 14 of the Arbitration and Conciliation …
We use cookies for analytics to improve your experience. Essential cookies are always on. Privacy Policy.