M/S Ram Chandra entered into a contract on 10‑02‑2025 to renovate the Bhaisahi Approach road for the Magh Mela. The work was completed on 09‑03‑2025 but the State of U.P. and two other respondents failed to make full payment despite repeated requests. On 16‑06‑2026 the applicant invoked the …
The petitioners Prasad Pandurang Tapkir and Pandurang Narayan Tapkir filed arbitration petitions under Section 11 of the Arbitration & Conciliation Act, 1996 seeking the appointment of an arbitrator and the deletion of certain respondents. The respondents argued that the partnership firm had …
The parties entered into a franchise agreement on 28 May 2025 containing an arbitration clause in clause 17. A dispute arose and the applicant invoked the clause by notice, but the parties could not agree on an arbitrator. The applicant filed an application under Section 11(6) of the Arbitration & …
The applicants, a registered partnership firm, entered into a lease deed with the respondents for a retail outlet on 13 June 2018, but the respondents failed to pay the lease amount. The applicants invoked the arbitration clause on 1 September 2025 and filed an application under Section 11(6) of the …
Ramky Infrastructure Ltd entered into a service agreement with Paschimanchal Vidyut Vitran Nigam Ltd on 18 September 2012 and completed the work, but the respondent has delayed payment of Rs. 462.85 crores. After repeated representations, Ramky issued a notice on 26 May 2022 invoking the arbitration …
The dispute arose from a Leave and License Agreement between Motilal Oswal Financial Services Ltd. and Santosh Cordeiro, which contained an arbitration clause in Clause 33. The respondent filed a Section 11 application under the Arbitration & Conciliation Act, 1996 seeking appointment of a sole …
The petitioner, a non‑resident Indian, claimed entitlement to 400,000 and 200,010 equity shares under a 2011 Shareholders Agreement and sought appointment of an arbitrator under Section 11(6) of the Arbitration & Conciliation Act, 1996 after the respondents failed to issue share certificates. The …
NBCC (India) Ltd. issued a tender for the construction of a weir and awarded the contract to Zillion Infraprojects Ltd. The contract was governed by a Letter of Intent (L.O.I.) which incorporated the tender documents mutatis mutandis but also stipulated that disputes be resolved only in Delhi …
The dispute arose from an ex‑parte arbitral award dated 12‑03‑1998 in a matter concerning specific performance and land‑plot amalgamation. The respondents sought to set aside the award under Section 34 of the Arbitration & Conciliation Act, 1996, invoking the public‑policy ground and sought to …
The Union of India entered into a work contract with Manraj Enterprises that contained clause 16(2) of the General Conditions of Contract, which expressly barred any interest on earnest money, security deposit, or amounts payable to the contractor. An arbitrator awarded pendente lite and future …
Deccan Paper Mills entered into a development agreement with Ashray, which was later assigned to Regency Mahavir Properties containing an arbitration clause. Deccan alleged fraud by a partner of Regency and filed a suit under the Specific Relief Act, seeking cancellation of the 2006 agreement and a …
The Supreme Court examined whether Section 84(2) of the Electricity Act, 2003 obliges a High Court Judge to be appointed as Chairperson of a State Electricity Regulatory Commission and whether a member of law is required on the Commission. By interpreting the statutory language, the Court held that …
The Supreme Court examined multiple Special Leave Petitions (SLPs) arising from a protracted dispute over the acquisition and transfer of shares in Bombay Oxygen Corporation Ltd. The dispute involved Messer Holdings GmbH (MGG), Goyal Gases Ltd (GGL), the Ruia family (RUIAS) and a joint venture …
The North Eastern Railway terminated two contracts awarded to the respondent contractor in 1994, after which arbitration proceedings were initiated in 1996 under a clause that required the arbitrators to be gazetted railway officers. Despite the passage of nearly two decades, no arbitral award had …
The case involved a charter party for the carriage of crude oil from Ras Sukheir to a safe Indian port, where the charterers nominated Vadinar Single Berth Mooring (SBM) for discharge. The vessel arrived at Vadinar, tendered a Notice of Readiness (NOR) but could not moor at the SBM due to inadequate …
Trimex International FZE Ltd. sent a commercial offer by email on 15 October 2007 for the supply of bauxite, containing an arbitration clause. Vedanta Aluminium Ltd. accepted the offer on 16 October 2007, confirming five shipments. A dispute later arose and Vedanta denied the existence of a …
The Supreme Court examined whether Section 14 of the Limitation Act, 1963, which excludes time spent prosecuting a proceeding in a wrong court, applies to an application under Section 34 of the Arbitration and Conciliation Act, 1996 for setting aside an arbitral award. It held that while Section 5 …
Dr. Manju Varma filed a writ petition in the Lucknow Bench of the Allahabad High Court seeking promotion based on seniority. Respondent No.6 (Dr. Gauri Ganguli) applied to the Chief Justice for transfer of the petition to the Allahabad Bench under paragraph 14 of the United Provinces High Courts …
The West Bengal State Electricity Board (the Board) had initially consented to the establishment of a new thermal generating station at Budge Budge, but the project cost later escalated. The licensee, Calcutta Electric Supply Corporation Ltd., sought further Board consent for the revised cost, which …
GRID Corporation of Orissa Ltd. (GRIDCO) succeeded the Orissa State Electricity Board and sued Indian Charge Chrome Ltd. (ICCL) for non‑payment of electricity bills arising from ICCL's captive power plant supplying power to the board. Multiple proceedings were instituted: a reference before the …
We use cookies for analytics to improve your experience. Essential cookies are always on. Privacy Policy.