THE STATE OF MADHYA PRADESHversusM/S SEW CONSTRUCTION LIMITED & ORS.

2022 INSC 1217Dismissed

The State of Madhya Pradesh awarded a contract to M/S Sew Construction for a masonry dam, but the original sand quarry became depleted, prompting the contractor to seek an alternate quarry. The contract’s clause 3.11(A) allowed escalation of rates only if the circumstance was beyond the contractor’s …

STATE OF MADHYA PRADESH AND ANR.versusM/S. KETI CONSTRUCTION

2018 INSC 360Disposed off

The State of Madhya Pradesh and others filed a civil appeal (No. 4016 of 2018) challenging the High Court's dismissal of a revision petition filed by M/s Keti Construction. The appeal hinged on the applicability of a precedent set in Va Tech Escher Wyass Flovel Ltd. v. MPSE Board, which the High …

PURI CONSTRUCTIONS PVT. LTD.versusSTATE OF MADHYA PRADESH & ORS.

2018 INSC 360

Puri Constructions entered into a 1984 agreement to construct an assembly building in Madhya Pradesh. A dispute led the Delhi High Court to appoint an arbitrator who rendered an award in 1989, which was later made a rule of court and executed in 1991. The appellant appealed the execution, and the …

STATE OF MADHYA PRADESH & ANR.versusASHOKA INFRAWAYS LTD. & ANR.

2018 INSC 360Disposed off

The State of Madhya Pradesh appealed against an order of the Madhya Pradesh High Court that relied on an earlier judgment concerning the jurisdiction of arbitration tribunals under the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983. The Supreme Court observed that the earlier High Court …

STATE OF CHHATTISGARH AND ANR.versusM/S. KMC CONSTRUCTION LIMITED

2018 INSC 360Disposed off

The State of Chhattisgarh appealed against an order of the High Court that had directed the parties to approach the Arbitration and Conciliation Act, 1996 for resolution of a dispute with M/S KMC Construction Limited. The Supreme Court examined whether the Madhya Pradesh Madhyastham Adhikaran …

M/S MSP INFRASTRUCTURE LTD.versusM.P. ROAD DEVL. CORP. LTD.

2014 INSC 840Appeal(s) allowed

M/S MSP Infrastructure Ltd. and M.P. Road Development Corp. entered into a road development contract that was later referred to arbitration under the Arbitration and Conciliation Act, 1996. The arbitral tribunal awarded Rs. 6.90 crores to the appellant, after which the respondent filed a petition …

STATE OF M.P. & ANR.versusANSHUMAN SHUKLA

2014 INSC 525Appeal(s) allowed

The State of Madhya Pradesh filed a civil revision under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, challenging an arbitral award dated 18 June 2003, but the revision was filed 80 days after the statutory three‑month period. The State also sought condonation of the delay …

STATE OF M.P. AND ANR.versusANSHUMAN SHUKLA

2008 INSC 643Matter referred to larger bench

The State of Madhya Pradesh filed a revision application before the High Court under Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, but the application was 80 days late. The issue was whether Section 5 of the Limitation Act, 1963, which allows condonation of delay, applies …