Holding
Permission to withdraw the application was granted, and the application was dismissed as infructuous.
Summary
M/s Budha Infra Structure Pvt Ltd., through its director, filed a civil writ petition before the Patna High Court. The petitioner sought the Court's permission to withdraw the pending application, claiming it had become infructuous. The respondents, representing various officials of the Bihar Urban Development Department, were served with the petition. The learned counsel for the petitioner moved that the application be withdrawn. The Court, after hearing, granted permission to withdraw the petition. Consequently, the application was dismissed as infructuous.
Issues considered
- Whether the Court may grant permission to withdraw a pending civil writ application and dismiss it as infructuous
Subjects
- withdrawal of application
- infructuous
- civil writ jurisdiction
- Patna High Court
Judgment
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.12501 of 2025
======================================================
M/s Budha Infra Structure Pvt Ltd. having its Registered Office at Ward
No.13, Moldiyar Tola, Pathak Ghat, Mokama, through its Director Gautam
Krishna, Male aged about 39 Years, Son of Sri Suresh Prasad Singh, Resident
of 204, Ram Shyam Apartment Road No 11 Ashok Nagar, P.S. Kankarbagh,
District Patna, Bihar 800020.
... ... Petitioner
Versus
1. The State of Bihar through the Principal Secretary, Urban Development
Department, Government of Bihar, Patna.
2. The Chief General Manager, South Bihar, Bihar, Urban Infrastructure
Development Corporation, Department of Urban Development, Government
of Bihar, Patna.
3. The General Manager, South Bihar, Bihar, Urban Infrastructure
Development Corporation, Department of Urban Development, Government
of Bihar, Patna.
4. The Project Director, Bihar, Urban Infrastructure Development Corporation,
Department of Urban Development, Government of Bihar, Patna.
5. The Project Director (Parna East), Bihar, Urban Infrastructure Development
Corporation, Department of Urban Development, Government of Bihar,
Patna.
... ... Respondents
======================================================
Appearance :
For the Petitioner : Mr. Prabhat Ranjan, Advocate
For the Respondents : Mr. Lalit Kishore, Sr. Advocate with
Mr. R.K. Priyadarshi, Advocate
======================================================
CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
and
HONOURABLE MR. JUSTICE SHAILENDRA SINGH
ORAL ORDER
(Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)
6 21-04-2026 Mr. Prabhat Ranjan, learned counsel for the petitioner
seeks permission to withdraw this application as the same has
become infructuous.
2. Permission is accorded.
3. Accordingly, this application stands dismissed as
Patna High Court CWJC No.12501 of 2025(6) dt.21-04-2026
2/2
having become infructuous.
(Sudhir Singh, J.)
(Shailendra Singh, J.)