Patna High Court

Dharmbir RamversusThe State Of Bihar and Ors

Decided
Disposal
DISPOSED

Holding

The petition is dismissed as the matter is pending before the LARRA and no fresh order can be passed by the High Court.

Summary

The petitioner sought a writ directing the respondents to determine and pay compensation for his land acquired for the Patna‑Buxar National Highway Corridor. The State counsel argued that most claimants had already been compensated and the remaining claims were pending before the Land Acquisition, Rehabilitation and Resettlement Authority (LARRA) under Section 3H(4) of the National Highways Act, 1956. The court noted that the matter had been referred to the LARRA and that it could not issue a fresh order while the authority’s proceedings were ongoing. Consequently, the writ petition was disposed of without granting any relief. The decision rests on the principle that the High Court will not interfere with matters pending before a specialized land‑acquisition tribunal.

Issues considered

  • Whether the High Court can issue a writ directing compensation when the dispute is already referred to the LARRA under Section 3H(4) of the National Highways Act, 1956.

Legislation cited

Subjects

  • land acquisition
  • compensation
  • National Highway
  • writ jurisdiction
  • LARRA
  • Section 3H(4)
  • High Court

Judgment

                     IN THE HIGH COURT OF JUDICATURE AT PATNA
                              Civil Writ Jurisdiction Case No.12661 of 2016
                 ======================================================
                 Dharmbir Ram son of Late Ram Bachchan Ram resident of Mohalla-
                 Vishnupuri Chitkohra, P.S. Gardanibagh, District- Patna.

                                                                            ... ... Petitioner/s
                                                    Versus
           1.    The State Of Bihar.
           2.    The District Magistrate, Patna.
           3.    The District Land Acquisition Officer, Patna.
           4.    The National Highway Authority of India, New Delhi.
           5.    The Chief Engineer, National Highway Authority Bishweshwaraiya
                 Bhawan, Bailey Road, Patna.

                                                           ... ... Respondent/s
                 ======================================================
                 Appearance :
                 For the Petitioner/s   :      Mr. Arun Kumar Jha, Advocate
                 For the Respondent/s   :      Mr. Ravi Kumar, AC to GP-13
                                               Mr. Akshay Lal Prasad, AC to GP-13
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE RAJIV ROY
                                       ORAL ORDER

2   31-01-2026                 Heard the parties.

                               2. The present petition has been preferred for the

                   following relief(s):

                                             “for issuance of an appropriate writ,

                                  order or direction to respondents to determine the

                                  compensation amount of the petitioner's land

                                  acquired for the construction of Patna-Buxar

                                  National Highway Corridor and payment thereof

                                  be made to the petitioner in accordance with law

                                  and/or pass such order/orders for which the

                                  petitioner is entitled to.”
          Patna High Court CWJC No.12661 of 2016(2) dt.31-01-2026
                                                     2/2




                                3. Learned State counsel has taken this Court to

                    paragraph-9 of the counter-affidavit of respondent nos. 2 and 3

                    to submit that most of the persons occupying the land have

                    already been compensated (0.15063 acres).

                                4. So far as the rest over land is concerned, since

                    number of claimants have approached the authorities, the

                    answering respondent referred the matter under Section 3H(4)

                    of the NH Act, 1956 before the Court of Land Acquisition,

                    Rehabilitation and Resettlement Authority, Patna (for brevity

                    ‘the LARRA’) vide letter no. 327 dated 21.02.2017 and will

                    abide by the order passed by the said authority where parties

                    shall appear and put forward their respective claims.

                                5. Considering the aforesaid submissions, since the

                    matter has already been referred to ‘the LARRA’ and in view of

                    the aforesaid development, no fresh order/direction can be

                    passed, the writ petition stands disposed of.



                                                  (Rajiv Roy, J)
Adnan/-

U


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.