Patna High Court

M/s. EMS Ltd.versusThe State of Bihar

Decided
Disposal
DISPOSED

Holding

The Court held that the petitioner must be afforded a hearing and a reasoned order before any rejection of its technical bid can stand.

Summary

M/s EMS Ltd. filed a writ petition challenging the Tender Committee's decision dated 06.01.2026 to reject its technical bid for the Sasaram Sewerage Network and STP project under AMRUT 2.0, on the ground that an Enforcement Directorate investigation and a debarment order were pending. The petitioner sought quashing of the decision, a direction to reconsider its bid, and an award of the contract. The Court examined whether the rejection without a hearing violated the principles of natural justice and whether the debarment order could be invoked without due process. It held that the petitioner was entitled to a reasoned order after being given an opportunity of hearing. Consequently, the Court directed the Managing Director of BUIDCo to consider the petitioner’s representation and pass a reasoned order within three weeks, and disposed of the writ application.

Issues considered

  • Whether the Tender Committee's rejection of the technical bid without a hearing violates the principles of natural justice.
  • Whether the pending Enforcement Directorate investigation and debarment order can be validly used to disqualify the bidder.
  • Whether the decision of the Tender Committee is liable to be quashed and the bid reconsidered.

Subjects

  • tender
  • technical bid
  • natural justice
  • debarment
  • writ petition
  • public procurement
  • AMRUT 2.0
  • Enforcement Directorate
  • representation
  • stay order

Judgment

                      IN THE HIGH COURT OF JUDICATURE AT PATNA
                               Civil Writ Jurisdiction Case No.1708 of 2026
                 ======================================================
                 M/s. EMS Ltd. having its registered office at C-88, RDC, Raj Nagar,
                 Ghaziabad, Uttar Pradesh through its authorized signatory, namely, Satish
                 Kumar Styarthy, male, aged about 34 years, S/o Ram Kumar, R/o Mohanpur,
                 P.O. Mohanpur, P.S. Bidupur, District- Vaishali, Bihar.

                                                                                  ... ... Petitioner
                                                   Versus
           1.    The State of Bihar through the Chief Secretary, Main Secretariat, Patna.
           2.    Bihar Urban Infrastructure Development Corporation Ltd., through its Man-
                 aging Director, Bihar Urban Infrastructure, Development Corporation Ltd.,
                 Patna.
           3.    The Managing Director, Bihar Urban Infrastructure Development Corpora-
                 tion Ltd., Patna.
           4.    General Manager (Finance), Bihar Urban Infrastructure Development Cor-
                 poration Ltd., Patna.
           5.    Chief General Manager, South Bihar Sub-Division, Bihar Urban Infrastruc-
                 ture Development Corporation Ltd., Patna.
           6.    General Manager, South Bihar Sub-Division, Bihar Urban Infrastructure De-
                 velopment Corporation Ltd., Patna.
           7.    Engineer-In-Chief, Urban Development and Housing Department, Patna.

                                                           ... ... Respondents
                 ======================================================
                 Appearance :
                 For the Petitioner     :       Mr. Ratnesh Kumar, Advocate
                                                Mrs. Parul Prasad, Advocate
                                                Mr. Aditya Anand, Advocate
                 For the Respondents    :       Mr. Lalit Kishore, Sr. Advocate with
                                                Mr. Standing Counsel-9
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
                                           and
                         HONOURABLE MR. JUSTICE RAJESH KUMAR VERMA
                                       ORAL ORDER

                          (Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)

2   03-02-2026                  The following reliefs have been sought in the present

                   writ application:-

                                            “(i) Quashing of the decision of the Tender
                                            Committee vide proceeding dated 06.01.2026 in
                                            Sasaram Sewerage Network and STP under
Patna High Court CWJC No.1708 of 2026(2) dt.03-02-2026
                                             2/4




                                  AMRUT 2.0 (corresponding to Notice Inviting
                                  Tender No. BUIDCO/YO-3256/2025- 28 dated
                                  09.06.2025) by which without affording any
                                  opportunity of personal hearing, the technical
                                  bid of the Petitioner has been rejected on the
                                  ground of pendency of investigation being
                                  carried out by the Enforcement Directorate
                                  (ED) and operation of the debarment order
                                  passed by the Project Director, Munger, Bihar
                                  Urban Infrastructure Development Corporation
                                  Limited (hereinafter referred to as BUIDCo)
                                  vide Letter No.07 dated 02.01.2026.
                                  (ii) Direction upon the Respondent BUIDCo to
                                  reconsider the technical bid of the Petitioner in
                                  Sasaram Sewerage Network and STP under
                                  AMRUT 2.0 which has been rejected by the
                                  decision     of   the   Tender     Committee    vide
                                  proceedings dated 06.01.2026 (corresponding to
                                  Notice Inviting Tender No. BUIDCO/YO-
                                  3256/2025-28 dated 09.06.2025).
                                  (iii) Direction upon the respondents to declare
                                  M/s EMS Ltd., as technically qualified in
                                  connection with the bid submitted for the work
                                  of Sasaram Sewerage Network and STP under
                                  AMRUT 2.0 (corresponding to Notice Inviting
                                  Tender No. BUIDCO/YO-3256/ 2025- 28 dated
                                  09.06.2025)       and   subsequently,   open     the
                                  financial bid and award the work to the
                                  Petitioner, if found successful.
                                  (iv) Stay the operation of the decision of the
                                  Tender      Committee    vide    proceeding    dated
                                  06.01.2026 (corresponding to Notice Inviting
Patna High Court CWJC No.1708 of 2026(2) dt.03-02-2026
                                              3/4




                                  Tender No. BUIDCO/YO-3256/ 2025- 28 dated
                                  09.06.2025) during the pendency and or without
                                  the leave of this Hon'ble Court.
                                  (v)      Alternatively,     direction     upon   the
                                  Respondents to declare the Petitioner to be
                                  provisionally successful in the technical bid in
                                  connection with the bid submitted for the work
                                  of Sasaram Sewerage Network and STP under
                                  AMRUT 2.0 (corresponding to Notice Inviting
                                  Tender No. BUIDCO/YO-3256/2025- 28 dated
                                  09.06.2025)       and     subsequently,   open   the
                                  financial bid of the Petitioner and award the
                                  work subject to the decision in present writ
                                  petition.
                                  (vi) And pass any other appropriate order(s)
                                  that this Hon'ble Court may deem fit and proper
                                  in the facts and circumstances of the present
                                  case.”



                      2. For redressal of his grievance, the petitioner had

          submitted a representation vide Annexure ‘P/4’, before

          respondent No. 3, which is pending till date.

                      3. Considering the facts and circumstances of the

          case, respondent No.3 is directed to consider the representation

          of the petitioner and pass a reasoned and speaking order, in

          accordance with law after giving an opportunity of hearing to all

          the stakeholders preferably within a period of three weeks from

          the date of receipt/production of a copy of this order.
            Patna High Court CWJC No.1708 of 2026(2) dt.03-02-2026
                                                        4/4




                                  4. With the aforesaid observation, the writ application

                      stands disposed of.

                                  5. Pending application(s), if any, shall stand disposed

                      of.



                                                  (Sudhir Singh, J)


                                            ( Rajesh Kumar Verma, J)
Gaurav Kumar,
Ibrar/-