Patna High Court

Dhanveer SinghversusThe State of Bihar

Decided
Disposal
ALLOWED

Holding

The court held that the forfeiture order was ultra vires as it was issued before the 15‑day period expired, and therefore set aside the order and directed refund of the EMD.

Summary

The petitioner, Dhanveer Singh, was awarded a public work contract for anti‑erosion work on the Kamla River after submitting the lowest bid in NIT No. 01/2022‑23. The tender required the successful bidder to furnish a security of performance (EMD) and execute contract documents within 15 days of award. The authorities forfeited the EMD of Rs 1,92,200 and ordered the petitioner’s black‑listing on 31 May 2022, before the 15‑day period had elapsed. The petitioner challenged the forfeiture as arbitrary and sought a mandamus directing refund of the EMD with interest and quashing of the forfeiture order. The court examined Clause 1.7 of the NIT, which stipulates forfeiture only if the bidder fails to comply after the 15‑day period, and held that the authority acted beyond its powers by terminating the contract prematurely. Consequently, the court set aside the forfeiture order, directed the refund of the EMD within four weeks, and barred any coercive action against the petitioner.

Issues considered

  • Whether the forfeiture of the earnest money deposit before the expiry of the 15‑day period prescribed in Clause 1.7 of the NIT is legally valid.
  • Whether the authority’s termination of the contract and black‑listing of the petitioner constitute an arbitrary exercise of power.
  • Whether the petitioner is entitled to a refund of the EMD with interest under the writ petition.

Subjects

  • Earnest Money Deposit
  • Tender
  • Contract forfeiture
  • Administrative law
  • Writ of mandamus
  • Public procurement
  • Arbitrariness
  • Refund
  • Interest

Judgment

                       IN THE HIGH COURT OF JUDICATURE AT PATNA
                                 Civil Writ Jurisdiction Case No.17087 of 2023
                  ======================================================
                  Dhanveer Singh, Son of Musafir Singh, Resident of Village- Bhim Nagar,
                  P.S.- Birpur, District- Supaul.

                                                                      ... ... Petitioner/s
                                                  Versus
            1.    The State of Bihar through the Principal Secretary, Water Resources
                  Development Department, Bihar. Patna.
            2.    The Engineer-in-Chief, Headquarter, Water Resources Department, Bihar.
                  Patna.
            3.    The Chief Engineer, Flood Control and Water Discharge, Water Resources
                  Department, Samastipur.
            4.    The Additional Secretary, Water Resources Department, Bihar, Patna.
            5.    The Executive Engineer, Water Discharge Division, Darbhanga.
            6.    The Executive Engineer, Water Discharge Division, Darbhanga.

                                                            ... ... Respondent/s
                  ======================================================
                  Appearance :
                  For the Petitioner/s    :       Mr. Raju Kumar, Adv.
                                                  Mr. Pradhan Murli Manohar Pd., Adv.
                                                  Mr. Sanjay Pd., Adv.
                                                  Mr. Subham Samrat, Adv.
                  For the Respondent/s    :       Mr. Anjani Kumar (Aag4)
                  ======================================================
                  CORAM: HONOURABLE MR. JUSTICE A. ABHISHEK REDDY
                                        ORAL ORDER

11   04-02-2026                   Heard the parties.

                                  2. The present writ petition has been filed for the

                    following relief(s) :

                                                “(i) To issue an appropriate order/s,
                                                direction/s including a writ preferably in
                                                nature of Mandamus commanding the
                                                respondents to make the payment of earnest
                                                money amounting to Rs. 2,00,000/-against
                                                short term invitation information No.
                                                01/2022-23 for the works allotted under anti
                                                erosion work on the right bank of Kamla
                                                river in village-Sajjanpura and Kanhauli
                                                under Benipur Block of District- Darbhanga
                                                vide Agenda No. 186/19/2022.
Patna High Court CWJC No.17087 of 2023(11) dt.04-02-2026
                                           2/7




                                       (ii) To direct the respondents to make the
                                       payment of Rs. 3.50,000/-for soil dumping
                                       sand/ on the work site against the work in
                                       question.
                                       (iii) To direct the respondent to make the
                                       payment of 18% interest on the
                                       abovementioned dues to the petitioner on
                                       account of delay and latches on the part of
                                       respondent.”


                      3. The following paragraph has been added vide order

          dated 22.10.2024 by way of I.A. No. 01 of 2024.

                                       “(iv) To quash the order dated 31.05.2022
                                       vide leter No. 630 issued by the Executive
                                       Engineer, Drainage Division, Darbhanga
                                       whereby and whereby he ordered for
                                       forfeiting    the     earnest   money      of
                                       Rs.1,92,200/- against short term Invitation
                                       Information No. 01/2022-23 for the works
                                       allotted under anti erosion work on the right
                                       bank of Kamla River in Village- Sajjanpura
                                       and Kanhauli under Benipur Bloci of
                                       District Darbhanga vide Agenda No.
                                       186/19/2022.”

                      4.     Learned counsel appearing on behalf of the

          Respondent Nos. 1 to 3 and 5 submits that he has filed the soft

          copy of the supplementary counter affidavit before the Registry

          but could not file the hard copy. Learned counsel seeks

          permission to place the same on record before this Court.

                      5. Permission is granted.

                      6. Hard copy of the supplementary counter affidavit

          filed by the Respondent Nos. 1 to 3 and 5 is handed over across
Patna High Court CWJC No.17087 of 2023(11) dt.04-02-2026
                                           3/7




          the Bench and the same is taken on record.

                      7. It is the case of the petitioner that pursuant to the

          tender notice bearing NIT No. 01/2022-23 dated 27.04.2022, the

          petitioner has participated in the same and being lowest bidder,

          the contract was awarded to him vide order dated 19.05.2022.

          Learned counsel submits that as per the terms and conditions of

          the tender the petitioner was obligated to furnish the security

          performance within a period of 15 days and also execute certain

          documents. However the authority without waiting for the 15

          days to be over has passed the impugned order on 31.05.2022

          forfeiting the       EMD paid by the petitioner           but also

          recommending the name of the petitioner for black listing.

          Learned counsel submits that the act of the respondents in

          terminating the contract and forfeiting the EMD is an arbitrary

          exercise of power is contrary to the terms and conditions of the

          NIT. Learned counsel has therefore prayed this Hon’ble Court to

          allow the present writ petition and consequentially direct the

          respondent-authority to refund the EMD amount and also not to

          take any coercive steps against the petitioner in respect of the

          present NIT.

                      8. Per contra, the learned counsel appearing on behalf

          of the respondent-State has vehemently opposed the very
Patna High Court CWJC No.17087 of 2023(11) dt.04-02-2026
                                            4/7




          maintainability of the present writ petition and stated that the

          petitioner in spite of being given several opportunities has failed

          to deposit the security performance and also turn up before the

          authority concerned for executing the necessary documents.

          Learned counsel has stated that the authority was well within its

          rights to cancel the allotment and forfeit the EMD amount as the

          petitioner has not turned up before the authority in spite of being

          put on notice. Further it is stated that the petitioner has violated

          the terms and conditions of the NIT more specifically Clause 1.7

          of the NIT and therefore the authority left with no other option

          had to cancel the allotment and forfeit the EMD amount.

          Learned counsel has therefore prayed this Hon’ble Court to

          dismiss the present writ petition.

                       9. This Court vide order dated 05.02.2025 duly taking

          note of the contents of the pleadings, directed the respondent

          authorities to clarify the query raised by this Court which reads

          as under:-

                                  “3. In the meanwhile, the respondents shall
                                  also specify by way of supplementary
                                  counter-affidavit as to whether there is any
                                  clause or any other document between the
                                  parties     stipulating   that   in   case   the
                                  successful bidder does not deposit the
                                  security and also additional performance
Patna High Court CWJC No.17087 of 2023(11) dt.04-02-2026
                                           5/7




                                  guarantee then his EMD likely to be
                                  forfeited.”


                      10.         Thereafter the 2nd supplementary counter

          affidavit is filed by the Respondent Nos. 1 to 3 and 5 wherein it

          is reiterated that after the allotment of the work, the petitioner

          has failed to turn up before the authority in spite of granting

          several opportunities. That the authority left with no other

          option has cancelled the allotment made in favour of the

          petitioner and forfeited the EMD amount.

                      11. In order to appreciate the issue involved in the

          present writ petition, it is necessary to extract Clause 1.7 of the

          NIT which reads as under:-

                                            "Within 15 days from the date of
                                issue of the letter accepting his tender the
                                successful tenderer shall furnish the required
                                security of performance and attend the office
                                of the Executive Engineer named in the letter
                                of acceptance for execution of contract
                                documents. If he fails to furnish the security of
                                performance or to execute the contract his
                                earnest money deposit shall be forfeited to
                                Government of Bihar and tenderer may be
                                disqualified for tendering in future for works
                                in the State of Bihar."
                       12. Admittedly in this particular case, the contract
Patna High Court CWJC No.17087 of 2023(11) dt.04-02-2026
                                           6/7




          was allotted to the petitioner on 19.05.2022 and thereafter the

          termination order was passed on 31.05.2022, i.e., well before

          the 15 days has expired.

                       13. In the 2nd supplementary counter affidavit filed by

          the Respondent Nos. 1 to 3 and 5, the authority has taken a

          stand, which reads as under:-

                                          “13.That in the light of Clause 1.7 of
                                the Instruction to bidder the Petitioner was
                                duty bound to furnish the security of
                                performance and to execute the agreement as
                                the Petitioner was selected as LI and work
                                order had been issued in his favour. But the
                                Petitioner did not turn up for execution of
                                agreement as well as to furnish the security
                                performance before the concerned Executive
                                Engineer despite repeated requests. Thus the
                                Petitioner violated the provision of Clause 1.7
                                of the Instruction to bidder which is the part of
                                NIT.”


                       14. It is not understandable as to how the authority

          has taken the stand that the petitioner has violated Clause 1.7 of

          the NIT, when it is manifestly clear that the termination order is

          passed even before the expiry of 15 days from the date of

          allotment. Once the authorities have issued a public tender the

          terms and conditions for the said tender are binding on both the
             Patna High Court CWJC No.17087 of 2023(11) dt.04-02-2026
                                                        7/7




                       parties and any correspondence between the parties contrary to

                       the said terms and conditions of the tender are not lawful. The

                       contention of the respondents authority that number of

                       reminders were sent to the petitioner to furnish the security

                       performance he has failed to do so is contrary to the provisions

                       of Clause 1.7 of the NIT.

                                    15. Having regard to the above, the impugned order

                       dated 31.05.2022 passed by the Executive Engineer, Drainage

                       Division, Darbhanga is set aside. The authorities are directed to

                       refund the EMD amount which has been forfeited back to the

                       petitioner within a period of four weeks from the date of receipt

                       of a copy of this order. The authorities are directed not to take

                       any coercive steps against the petitioner in respect of the NIT

                       which is subject matter of the present writ petition.

                                    16. The present writ petition stands allowed to the

                       extent indicated above.



                                                                 (A. Abhishek Reddy , J)
Bhardwaj/-