Patna High Court

JSP Projects Pvt. Ltd.versusThe State of Bihar

Decided
Disposal
DISPOSED

Holding

The writ petition is disposed of as the matter has been finally decided by the order dated 08.03.2026, which merges the earlier communications.

Summary

JSP Projects Pvt. Ltd. was declared the lowest bidder for the Ara‑Ekauna‑Khaira‑Sahar Road contract and was asked to furnish an additional unconditional bank guarantee on the ground of an alleged abnormally low bid (ALB). The petitioner objected to this demand, submitting a representation which it claimed was not considered. The High Court earlier directed the respondents to ascertain the status of the representation, and the respondents subsequently issued a reasoned order on 08.03.2026 addressing the representation. The Court held that the final order of 08.03.2026 subsumes the earlier communications and that the writ petition seeking relief against those communications could not be entertained. Consequently, the petition was disposed of, with the petitioner advised that it may challenge the 08.03.2026 order through the appropriate legal remedy.

Issues considered

  • Whether the demand for an additional bank guarantee on the basis of an alleged abnormally low bid was made in accordance with Clause 38.2(b) and Clause 38.3 of the Instructions to Bidders.
  • Whether the petitioner’s representation dated 17.12.2025 was required to be considered before imposing the additional guarantee.
  • Whether the writ petition seeking to set aside the letters dated 16.12.2025 and 26.12.2025 remains maintainable after the issuance of a final order on 08.03.2026.

Subjects

  • tender
  • abnormally low bid
  • bank guarantee
  • doctrine of merger
  • writ petition
  • administrative law
  • contract award
  • performance security

Judgment

                      IN THE HIGH COURT OF JUDICATURE AT PATNA
                               Civil Writ Jurisdiction Case No.1782 of 2026
                 ======================================================
                 JSP Projects Pvt. Ltd., having its registered office at E-27, Ground Floor,
                 Geetanjali Enclave, Malviya Nagar, New Delhi 110017, through its
                 Authorised Representative, Mr. Saurabh Tyagi (male), aged about 43 years,
                 Son of D.K. Tyagi, resident of village Dhanarua, P.O. and P.S. Hapur, Dist-
                 Hapur, U.P., Pin- 245101, at present residing at Flat no- G-1, Block C,
                 Indraprast Apartment, Ramesh Colony, Daryapur Road, Kurthoul, Patna-
                 804453.


                                                                              ... ... Petitioner
                                                 Versus
           1.    The State of Bihar through the Secretary, Road Construction Department,
                 Bihar, Patna.
           2.    The Secretary, Road Construction Department, Bihar, Patna.
           3.    The Bihar State Road Development Corporation Ltd., Patna, in the matter of
                 Tender for Constructions of Ara-Ekauna-Khaira-Sahar Road in the State of
                 Bihar under Civil Works Contract Package No. BSHP-IV (Phase-I)/pkg-2,
                 through its Managing Director, BSRDCL, Patna.
           4.    The Managing Director, BSRDCL, Patna.
           5.    The Chief General Manager, BSRDCL, Patna.


                                                           ... ... Respondents
                 ======================================================
                 Appearance :
                 For the Petitioner    :      Mr. Manish Gupta, Advocate, Mr. Ray Saurabh
                                              Nath, Advocate, Mrs. Manjari Nath, Advocate,
                                              Mrs. Shalini Sinha, Advocate and Mr. Akshat
                                              Kumar, Advocate
                 For the State         :      Mr. Vikash Kumar, SC-11
                 For the BSRDCL        :      Mr. P.K. Shahi, Sr. Advocate and Mr. Manish Dhari
                                              Singh, Advocate
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
                         and
                         HONOURABLE MR. JUSTICE SHAILENDRA SINGH
                                       ORAL ORDER

                 (Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)


5   18-03-2026                    Heard learned counsel for the petitioner through

                   video conferencing, learned counsel for the State and learned
Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                            2/9




          senior counsel for the B.S.R.D.C.L.

                      2. The following reliefs have been sought for in the

          present writ application:

                                  “1. For seeking the indulgence of the
                                  Hon’ble High Court to set aside the letter
                                  dated      16.12.2025               and     letter   dated
                                  26.12.2025 issued by the Respondent No. 3
                                  i.e.,   Bihar      State            Road     Development
                                  Corporation            Ltd.,        Patna     (hereinafter
                                  referred as “BSRDCL”) wherein it has been
                                  demanded an additional unconditional Bank
                                  Guarantee of Rs. 22,28,50,456/- (Rupees
                                  Twenty Two Crores Twenty Eight Lakhs Fifty
                                  Thousand Four Hundred and Fifty Six Only)
                                  on account of “Abnormally Low Bid”
                                  (hereinafter referred as “ALB”) and above
                                  the performance unconditional Performance
                                  Bank      Guarantee            of    Rs.     9,45,88,479/-
                                  (Rupees Nine Crores Forty Five Lacs
                                  Eighty Eight Thousand Four Hundred and
                                  Seventy Nine Only) being 5% of the
                                  Contract value. The said decision of the
                                  Respondent No. 3 is directly in contravention
                                  of Clause 38.2(b) of the Instruction of
                                  Bidders (hereinafter referred as “ITB”)
                                  being part of the Tender.”


                         3. The brief facts of the present case is that a tender
Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                            3/9




          was floated by the respondent authorities for construction of

          Ara-Ekauna-Khaira-Sahar Road. The petitioner participated in

          the said tender process and was declared the lowest bidder (L-

          1). Pursuant thereto, a Letter of Acceptance dated 16.12.2025

          was issued in favour of the petitioner, wherein the petitioner was

          also required to furnish an additional unconditional Bank

          Guarantee of Rs. 22,28,50,456/- on the ground that its bid was

          an Abnormally Low Bid (ALB). The petitioner, being aggrieved

          by the said condition, submitted a objection/ representation

          dated 17.12.2025 objecting to the demand of the additional

          Bank Guarantee. It is the case of the petitioner that the said

          representation was not considered and, in the meantime, the

          respondents reiterated the demand vide communication dated

          26.12.2025.

                         4. By order dated 16.12.2025, the following order

          was passed by the Chief General Manager, B.S.R.D.C.L.:

                                  “ Sub: Construction of Ara-Ekauna-Khaira-
                                  Sahar Road in the State of Bihar under Civil
                                  Works Contract Package No. BSHP-IV
                                  (Phase-1) Pkg-2.
                                  Sir,
                                           This is to notify you that your bid
                                  dated      22.07.2025   for   execution   of
                                  ‘Construction of Ara-Ekauna-Khaira-Sahar
                                  Road in the State of Bihar under Civil Works
                                  Contract Package No. BSHP-IV (Phase-
Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                            4/9




                                  1)/Pkg-2’ for the Contract Price in the
                                  equivalent of INR 189,17,69,571.00 (Indian
                                  Rupees One Hundred Eighty-Nine Crore
                                  Seventeen Lakh Sixty-Nine Thousand Five
                                  Hundred Seventy-One) only exclusive of
                                  GST is hereby accepted by Bihar State Road
                                  Development Corporation Ltd.
                                                  You are requested to furnish an
                                  unconditional Bank Guarantee amounting to
                                  5%      of      Contract        Price,     i.e.,,   INR
                                  9,45,88,479/- (Indian Rupees Nine Crore
                                  Forty-Five Lakh Eighty-Eight Thousand
                                  Four Hundred Seventy-Nine) only towards
                                  Performance Security as per Section-8 of
                                  ADB’s SBD.
                                                  As your bid is found to be on the
                                  lower side, you are further requested to
                                  furnish an unconditional Bank Guarantee
                                  amounting to INR 22,28,50,456/-(Indian
                                  Rupees Twenty-Two Crore Twenty-Eight
                                  Lakh Fifty Thousand Four Hundred Fifty-
                                  Six)      only         towards      an      Additional
                                  Performance Security in accordance with the
                                  Clause 38.4 (b) of ITB.
                                                  The       above          said       Bank
                                  Guarantee(s) towards Performance Security
                                  and Additional Performance Security shall
                                  be submitted within 28 days of the receipt of
                                  Notification of Award and shall be in the
                                  form     acceptable        to    the     Employer     in
Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                            5/9




                                  accordance with Clause 45 of ITB.”
                         5. When the matter was taken up on 16.02.2026, a

          query was put by this Court as to whether the representation

          submitted by the petitioner was still pending consideration

          before the competent authority. Upon the same being taken note

          of, the respondents were required to ascertain the position of the

          said representation.

                         6. Learned counsel for the petitioner submits that

          the impugned action of the respondents in demanding additional

          Bank Guarantee is wholly arbitrary, illegal and contrary to the

          terms and conditions of the tender. It is submitted that the action

          of the respondents is in clear contravention of Clause 38.2(b)

          read with Clause 38.3 of the Instructions to Bidders (ITB),

          which mandates that in cases of an alleged Abnormally Low

          Bid, the Employer is required to first seek a written explanation

          from the bidder and undertake an objective evaluation of the

          justification furnished before taking any adverse decision. It is

          submitted that in the present case, without adhering to the

          aforesaid      mandatory        procedure,     the   respondents   have

          straightaway imposed the condition of furnishing additional

          Bank Guarantee, rendering the impugned communications

          unsustainable in law.

                         7. Learned counsel for the respondents, referring to
Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                            6/9




          the supplementary counter affidavit, has brought to the notice of

          this Court that in compliance of the order dated 16.02.2026, the

          representation of the petitioner has been duly considered and a

          reasoned order bearing Order No. 854/2026 dated 08.03.2026

          has already been passed, which has been brought on record vide

          Annexure- 5/A to the supplementary counter affidavit.

                             8. Upon perusal of the materials available on record

          and having heard learned counsel for the parties, it transpires

          that the primary grievance of the petitioner in the present writ

          petition      is     directed   against    the    communications      dated

          16.12.2025 and 26.12.2025, whereby the petitioner was called

          upon     to        furnish   additional    Bank    Guarantee,   and     the

          consequential grievance is that its representation dated

          17.12.2025 was not considered by the respondents.

                             9. It further transpires that during the pendency of

          the present writ petition, this Court, vide order dated

          16.02.2026, had specifically directed the respondents to

          ascertain the position of the representation of petitioner. In

          pursuance thereof, the respondents have now passed a detailed

          and reasoned order dated 08.03.2026.

                             10. Since the order dated 08.03.2026 has been

          passed on the representation of the petitioner and the same is not
Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                            7/9




          under challenge in the present proceedings, this Court finds no

          occasion to examine the merits thereof. However, if the

          petitioner remains aggrieved by the said order dated 08.03.2026,

          he has always liberty to take a legal recourse against the said

          order.

                         11. In such circumstances, the cause of action, as

          originally pleaded in the writ application, stands surpassed by

          the subsequent development, namely, the passing of the final

          order dated 08.03.2026. Once a final, reasoned order has been

          passed by the competent authority on the subject matter of

          dispute, the earlier communications merge into the said final

          decision and it is the said order which governs the field.

                         12. At this juncture, it is pertinent to take note of the

          judgment rendered by the Hon’ble Supreme Court while

          deciding the case of Kunhayammed and Ors. vs. State of

          Kerala reported in (2000) 6 SCC 359, wherein it has been

          observed that the doctrine of merger is not of universal

          application but postulates that once a superior forum or

          competent authority has passed a final order, it is that order

          which subsists and governs the rights of the parties. The relevant

          part of the said order reads as follows:

                                   “44. To sum up, our conclusions are:
                                   (i) Where an appeal or revision is provided
Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                            8/9




                                   against an order passed by a court, tribunal
                                   or any other authority before superior
                                   forum and such superior forum modifies,
                                   reverses or affirms the decision put in issue
                                   before it, the decision by the subordinate
                                   forum merges in the decision by the
                                   superior forum and it is the latter which
                                   subsists, remains operative and is capable
                                   of enforcement in the eye of law….”



                         13. This Court also finds that the reliefs sought in

          the present writ petition are confined to the earlier

          communications dated 16.12.2025 and 26.12.2025, which now

          stand subsumed in the final order dated 08.03.2026. In such

          circumstances, adjudication of the said communications in

          isolation would not be appropriate. Moreover, this Court refrains

          from entering into the merits of the case at this stage, as the

          same would necessarily involve examination of the correctness

          of the reasoned order dated 08.03.2026, which is not under

          challenge in the present proceedings.

                         14. Considering the fact that a final order has

          already been passed during the pendency of the writ application,

          this Court is of the considered view that no further order is

          required to be passed in the present writ application in relation

          to the reliefs originally sought.
         Patna High Court CWJC No.1782 of 2026(5) dt.18-03-2026
                                                     9/9




                                  15. Accordingly, the writ petition stands disposed

                   of.

                                  16. However, the petitioner, if so advised, shall be at

                   liberty to challenge the order dated 08.03.2026 in accordance

                   with law.

                                  17. Pending application(s), if any, shall also stand

                   disposed of.




                                               (Sudhir Singh, J)


                                            ( Shailendra Singh, J)
U.K./-
U
