Amar Engicon and Construction Private LimitedversusThe State of Bihar

Decided
Disposal
DISMISSED

Holding

The writ petition is dismissed as there is no merit to interfere with the tender process, which was lawfully re‑tendered.

Summary

Amar Engicon and Construction Private Limited filed a writ petition challenging a letter dated 24‑09‑2025 that cancelled a tender without prior notice or a show‑cause opportunity. The petitioner sought quashing of the cancellation, direction to award the work to it, and any other relief. Respondents, including the State of Bihar and officials of the Road Construction Department, contended that the original tender was cancelled on technical grounds due to lapse of bid validity and that the subsequent re‑tender was lawfully conducted under the Bihar Financial Rules. The Departmental Tender Committee (DTC) treated the re‑tender as a first‑time tender and invited fresh bids, a decision upheld by a prior High Court judgment (CWJC No. 13968 of 2025). The Court observed that the petitioner had already participated in the fresh tender and found no merit to interfere with the departmental process, ordering the writ petition dismissed and directing the return of any bank guarantees.

Issues considered

  • Whether the cancellation of the original tender without notice or a show‑cause notice is violative of procedural fairness.
  • Whether the Departmental Tender Committee's decision to treat the re‑tender as a first‑time tender is legally valid.
  • Whether a writ petition is maintainable to challenge the tender cancellation and subsequent re‑tender.

Subjects

  • tender cancellation
  • public procurement
  • writ jurisdiction
  • departmental tender committee
  • procedural fairness
  • re‑tender

Judgment

                     IN THE HIGH COURT OF JUDICATURE AT PATNA
                              Civil Writ Jurisdiction Case No.18030 of 2025
                 ======================================================
                 Amar Engicon and Construction Private Limited, through its Director Gopal
                 Kumar Verma, (Male), aged about 39 years, son of Late Kishun Saw, resident
                 of Flat No. 201, Sirmangala Tower, Saheb Pokhra Road, VIP Chowk,
                 Deoghar 814112 (mobile No. 7004393616)

                                                                              ... ... Petitioner
                                                  Versus
           1.    The State of Bihar.
           2.    The      Engineer-in-Chief-cum-Additional    Commissioner-cum-Special
                 Secretary, Works Manager, Road Construction Department, Bihar, Patna.
           3.    The Secretary, Road Construction Department, Bihar, Patna.
           4.    The Financial Advisor, The Secretary, Road Construction Department, Bihar,
                 Patna.
           5.    The Chief Engineer (South), Road Construction Department, Bihar, Patna.
           6.    The Executive Engineer, Road Construction Department, Lakhisarai.

                                                           ... ... Respondents
                 ======================================================
                 Appearance :
                 For the Petitioner    :      Mr. Ajay Prasad, Advocate.
                 For the Respondents   :      Mr. Government Pleader (4)
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
                         and
                         HONOURABLE MR. JUSTICE SHAILENDRA SINGH
                                       ORAL ORDER

                 (Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)

5   20-04-2026                  Heard learned counsel for the petitioner and learned

                   counsel for the respondents.

                               2. Following is the relief sought for in the present writ

                   petition.

                                  “1 (i) For quashing the letter dated
                                  24.09.2025 issued by the respondent no. 2 to 4
                                  under the name of the petitioner whereas
                                  cancelled the tender without prior notice to
                                  the petitioner, without asking any show cause
                                  to the petitioner with regard to deem to be the
Patna High Court CWJC No.18030 of 2025(5) dt.20-04-2026
                                           2/4




                         first tender as well as also issued a direction
                         by the Direction to the Chief Engineer with
                         regard to advertise the fresh tender.
                         (ii) For issuance of a direction to the
                         respondent authority to allow the work
                         through the writ petitioner who is qualified in
                         tender for grant as per Notice Inviting Tender.
                         (iii) For any other order or orders to which
                         the petitioner may be entitled to.”


                      3. A supplementary counter affidavit has been filed on

          behalf of respondent no. 6 wherein in paragraph nos. 7, 8, 9, 10,

          11, 12 and 13 following statements have been made which is

          reproduced hereinbelow:-

                         “7. That in the first tender two bidder namely
                         Santosh Kumar and Nishant Kumar had
                         participated. The Bid validity of the both the
                         bidder lapsed during the pendency of the
                         Tender process. Neither the departmental
                         official, nor the bidder took steps to extend the
                         bid validity. Since the Bid validity of the both
                         the bidder had lapsed, the tender was
                         cancelled which is evident from Letter No. 920
                         dated 12.03.2025 of Chief Engineer. Since the
                         Tender was cancelled on technical ground it
                         was a sham transaction and it was decided to
                         Invited fresh tender.
                         8. That in the present tender, petitioner and
                         another bidder namely Santosh Kumar
                         participated. The second bidder Santosh
                         Kumar was disqualified in the Technical bid
                         as he did not possess Technical experience
                         required in the bid. Only petitioner was
                         declared responsive in the Technical Bid.
                         9. That since this was a case of single tender,
Patna High Court CWJC No.18030 of 2025(5) dt.20-04-2026
                                           3/4




                         the Chief Engineer referred the matter to the
                         higher authority i.e. Departmental Tender
                         Committee (DTC) in the light of provision
                         made in Departmental letter no 3162(S) dated
                         09.05.2016 which has been issued in the light
                         of Rule 131J(c) of the Bihar Financial Rules.
                         The DTC in its meeting held on 23.09.2025
                         (impugned decision in the present application)
                         decided that since the first time tender was
                         cancelled on ground of expiry of the Bid
                         validity, it was not a valid transaction and
                         therefore the Retender will be treated as First
                         Time Tender and direction was issued to invite
                         fresh Bid. All these facts are clearly mentioned
                         in the DTC proceeding, dated 23.09.2025
                         which is impugned letter in this writ
                         application.
                         10. The decision of DTC dated 23.09.2025 is
                         fully covered by the Judgment of this Hon'ble
                         Court passed in CWJC no. 13968 of 2025, on
                         19.09.2025, as referred above.
                         11. That evidently, the decision of DTC dated
                         23.09.2025 does not suffer from any legal
                         infirmity and is sustainable in eye of law.
                         12. That moreover, pursuance to the decision
                         of DTC held on 23.09.2025 to invite fresh
                         tender, it has been invited under NIT no
                         RCD/Lakhisarai/E Retendering /20/2025-26.
                         It is relevant to mention here that the
                         petitioner has also participated in this Re-
                         tender along with two other bidders. The
                         Evaluation of bid is under process.
                         13. That in view of participation of the
                         petitioner in the fresh bid invited on
                         17.01.2026, the present writ petition has lost
                         its significance and the instant writ petition
                         has become infructuous.”
            Patna High Court CWJC No.18030 of 2025(5) dt.20-04-2026
                                                       4/4




                                    4. Upon perusal of the materials available on record, it

                      appears that the petitioner has already participated in the

                      subsequent re-tender bearing NIT No. RCD/Lakhisarai/E

                      Retendering/20/2025-26 dated 17.01.2026 issued by the Road

                      Construction Department.

                                    5. In view of the aforesaid, this Court is of the view

                      that there is no reason for interfering with the tender process in

                      question at this stage.

                                    6. Accordingly, we find no merit in the present writ

                      application and the same stands dismissed.

                                    7. Pending application(s), if any, shall also stand

                      disposed of.

                                    8. Since the tender in question has already been

                      cancelled, any bank guarantee or other documents submitted in

                      respect of the said tender notice shall be returned to the

                      petitioner.




                                                         (Sudhir Singh, J)



                                                      (Shailendra Singh, J)
U.K./-BKS
U


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.