Created by Fuzzy Cloud

Patna High Court

Pawan Kumar SinghversusThe State of Bihar

Decided
Disposal
ALLOWED

Holding

The petitioner had completed the work as certified and is entitled to the balance payment, warranting the issuance of a writ of mandamus directing payment.

Summary

The petitioner, Pawan Kumar Singh, completed the construction of a driving testing track at Dhanupara, Ara under a 2022 tender and received Rs.38 lakh of the contracted Rs.48.22 million. He claimed the remaining Rs.10.32 lakh was unpaid despite certification of completion by the Executive Engineer and multiple letters requesting fund allocation. The respondents, including the State of Bihar and various departmental officials, contended that only 25-30% of the work was done and in a dilapidated condition, thereby refusing payment. The court examined the certifications, correspondence, and the lack of any prior objection by the respondents, finding the claim of incomplete work untenable. Consequently, the court directed the respondents to release the balance amount within four weeks, effectively granting the writ of mandamus.

Issues considered

  • Whether the petitioner is entitled to the balance payment of Rs.10,32,000 under the contract.
  • Whether the respondents' allegation that the work was incomplete is substantiated.
  • Whether a writ of mandamus can be issued to compel the government to pay the dues.
  • Whether the delay in payment violates principles of natural justice and contractual obligations.

Subjects

  • contractual payment
  • public works
  • writ of mandamus
  • government liability
  • balance dues
  • completion certification

Judgment

         IN THE HIGH COURT OF JUDICATURE AT PATNA
                 Civil Writ Jurisdiction Case No.18288 of 2023
     ======================================================
     Pawan Kumar Singh Son of Late Chandra Dev Singh Resident of Mohalla
     Mansa Pandey Baga PS Ara Nagar, District- Bhojpur.


                                                              ... ... Petitioner/s
                                     Versus
1.   The State of Bihar through the Principal Secretary, Building Constraction
     Department Bihar Patna.
2.   The Bihar Public Works Department, Patna.
3.   The Executive Engineer Building Division, Ara.
4.   The Executive Engineer Bhawan, Parmandall Bhojpur at Ara.
5.   The District Transport Office Bhojpur at Ara.


                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :      Mr. Ajay Kumar Singh, Adv.
     For the Respondent/s   :      Mr. Advocate General
     ======================================================
     CORAM: HONOURABLE MR. JUSTICE A. ABHISHEK REDDY
     ORAL JUDGMENT
      Date : 21-01-2026
               Heard the learned counsel for the parties.

                   2. This writ petition has been filed for the following

     relief(s):-

                                       “That, this application is directed for
                            issuance or appropriate writ in the nature of
                            mandamus       any    other   writ   order    direction
                            Commanding the respondents to pay the Admitted
                            dues of the petitioner for the work done vide
                            tender Publish in 2022 in Vide work name
                            Construction     at    driving   testing     track   at
                            Dhanupara in Agreement No. 01F2/2022-2023.
                                       At the very outset it is stated that them
                            petitioner has completed the Construction of
Patna High Court CWJC No.18288 of 2023 dt.21-01-2026
                                           2/7




                                driving testing tack, work at Dhanupara, Ara,
                                District-Bhojpur       and   has   completed   the
                                Construction and entire premises It is further
                                stated that the petitioner has also completed the
                                assigned the constructed work there for in the
                                premises at Bihar Publish Work Department.”



                    3. It is the case of the petitioner that pursuant to the

       notification of the tender, the petitioner has participated in the

       tender process and the petitioner being the successful bidder the

       work was allotted to him. Thereafter the petitioner has constructed

       the driving testing track at Dhanupara, Ara, District- Bhojpur

       within the stipulated time. That after completion of the work, the

       petitioner has been paid an amount of Rs. 38 lakhs out of the total

       contracted amount of Rs. 48,22,736/- and the balance amount of

       10,32,000/- is yet to be paid. That the Executive Engineer vide

       letter no. 1473 dated 21.08.2023 and vide letter no. 1738 dated

       05.10.2023 has certified that the work assigned to the petitioner

       has been completed and the said letters were addressed to the

       Respondent Nos. 4 and 5. Though the work was completed in the

       year 2022, the balance amount due to the petitioner is yet to be

       paid. Learned counsel has, therefore, prayed this Hon’ble Court to

       allow the present writ petition and direct the respondents to pay

       the amount due to the petitioner.
Patna High Court CWJC No.18288 of 2023 dt.21-01-2026
                                           3/7




                    4. In the counter affidavit filed by the Respondent No. 3

       i.e. Executive Engineer Building Division, Ara at Bhojpur, the

       factum of the tender being published, the work being entrusted to

       the petitioner and the completion of the construction as per the

       timeline fixed in the agreement bearing no. 01F2/2022-2023 has

       not been denied. The counter affidavit specifically states that the

       agreement value is of Rs. 48,22,736/- was done by the petitioner

       and an amount of Rs. 38,00,000/- has already been paid to the

       petitioner. Further, the factum of the Respondent No. 3 writing

       letters to the Respondent Nos. 4 and 5 about the completion of the

       work assigned to the petitioner and for releasing the funds has also

       not been denied. Further, in the counter affidavit, it is stated that

       thereafter Chief Engineer (South) vide his letter no. 588 dated

       28.02.2024 letter no. 744 dated 13.03.2024, letter no. 867 dated

       24.04.2024 and letter no. 1647 dated 21.08.2024 has repeatedly

       requested the District Transport Officer, Bhojpur, Ara for allotment

       of funds for making the payment of the balance amount due to the

       petitioner. That Executive Engineer Ara has once again vide his

       letter no. 915 dated 03.07.2024 and Letter No. 1115 dated

       02.09.2024 requested the allotment of funds from District

       Transport officer, Bhojpur, Ara (Respondent No. 5). That in this

       regard, Secretary, Transport Department has also been requested
Patna High Court CWJC No.18288 of 2023 dt.21-01-2026
                                           4/7




       by Letter No. 8156 dated 08.10.2024 to provide the allotment of

       necessary funds. Thereafter, it is stated that the respondents are

       awaiting the allotment of funds for making the necessary payments

       to the petitioner.

                    5. In the counter affidavit filed by the Respondent No. 5,

       the authority has not denied about the allotment of the work to the

       petitioner and also the amounts paid to the petitioner. However,

       with regard to the balance amount due to the petitioner, it is stated

       that the Respondent No. 1 i.e. Principal Secretary, Building

       Construction Department had communicated letter bearing no.

       744(S) dated 13.03.2024 and the Respondent No. 3 vide letter no

       47/Pari. dated 15.04.2025 had written to the Motor Vehicle

       Inspector, Bhojpur for furnishing the present status of construction

       of the Driving Testing Track at Dhanupura, Ara and the Motor

       Vehicle Inspector has submitted his status report of the driving

       testing track vide letter no. 256/Pari dated 24.04.2025. In the

       report, it is stated that only 25% to 30% of the total work has been

       done and the same is also in a dilapidated condition covered by

       herbs/shrubs and grass. Further, it is stated in the counter affidavit

       that in view of the above, the balance amounts due to the petitioner

       cannot be made. The petitioner has filed a rejoinder to the counter

       affidavit filed by the Respondent Nos. 3 and 5 duly enclosing the
Patna High Court CWJC No.18288 of 2023 dt.21-01-2026
                                           5/7




       copies of the communication between various departments which

       evidence that the work assigned to the petitioner has been

       completed. Further, it is stated that the work agreement was signed

       on 15.04.2022 and the work has been completed on 14.07.2022

       and the same was endorsed by the concerned authorities. The

       authority at this stage cannot take a ground that the work has not

       been completed and state that only 25% to 30% has been done.

       More particularly, in view of the fact that the Executive Engineer

       has certified the work done by the petitioner.

                    7. Thereafter, supplementary counter affidavit on behalf

       of the Respondent No. 3 has been filed wherein at para 8, 9 and 10

       it is stated as under:

                                            “8. That it is most humbly submitted
                                that the answering respondent does not dispute the
                                remaining amount as claimed by petitioner. That
                                under para-8 of his writ petition. Petitioner has
                                submitted that only Rs. 10,32,000/- remains
                                unpaid which is true.
                                            9. That in the previously filed counter
                                affidavit respondents has already brought on
                                record the fact that for payment of remaining dues
                                of Rs 10,32,000/-, Executive Engineer, Building
                                Division, Ara vide his Letter No.1473 dated
                                21.08.2023, Letter No.1738 dtd.05.10.2023, Letter
                                No.915       dtd.03.07.2024,    Letter    No.1115
                                dtd.02.09.2024 and Letter No.1758 dtd.09.12.2025
                                and Chief Engineer(South) vide his Letter No.588
Patna High Court CWJC No.18288 of 2023 dt.21-01-2026
                                           6/7




                                dtd. 28.02.2024, Letter No.744 dtd. 13.03.2024,
                                Letter No.867 dtd. 24.04.2024 and Letter No.1647
                                dtd. 21.08.2024 has repeatedly requested District
                                Transport Officer, Bhojpur, Ara to provide the
                                remaining allotment of Rs 10,32,000/-, so that
                                petitioner remaining dues could be cleared off.
                                            10. That it is further submitted that vide
                                Letter No.8156 dated 08.10.2024 Secretary,
                                Transport Department has also been requested to
                                provide     the    remaining    allotment    of    Rs
                                10,32,000/-.”


                    8. It is pertinent to note that the Measurement Book has

       been enclosed along with the supplementary counter affidavit

       which evidences the work done and also the completion.

                    9. Having regard to the above mentioned facts and

       circumstances and also the correspondence made by the

       Respondent No. 3, it is manifestly clear that the petitioner has

       completed the work assigned to him within the stipulated period. It

       is pertinent to note that the work was completed in July, 2022 and

       there is no protest by the Respondent No. 5 at any point of time

       prior to filing of the present C.W.J.C. that the petitioner has not

       done the work. It is only after the C.W.J.C. has being filed, the

       Respondent No. 5 has taken a stand that the work has not being

       completed. There is no explanation forthcoming from the said

       authority as to why they have kept quite for a period of almost
             Patna High Court CWJC No.18288 of 2023 dt.21-01-2026
                                                        7/7




                    three years if the work was not completed by the petitioner within

                    the stipulated time. Further the said stand taken by the Respondent

                    No. 5 is contrary to the letter written by the Executive Engineer

                    where it was certified that the work entrusted to the petitioner has

                    being completed. There is nothing but a lame excuse to avoid the

                    payment of the legitimate dues to the petitioner.

                                 Having regard to the above, the present writ petition has

                    to be necessarily allowed and the same is accordingly allowed. The

                    Respondent Nos. 4 and 5 are directed to see that the balance

                    amounts due to the petitioner are deposited with the Respondent

                    No. 3 at the earliest preferably within a period of four weeks from

                    the date of receipt of the copy of this order and on receipt of the

                    said funds, the authority is directed to make the payments to the

                    petitioner forthwith.

                                 10. With the above directions, the present writ petition

                    stands allowed to the extent indicated.



                                              (A. Abhishek Reddy , J)
Gauravkr/-

AFR/NAFR                    NAFR
CAV DATE                     N/A
Uploading Date           30.01.2026
Transmission Date            N/A


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.