Patna High Court

Kaushal RayversusThe State of Bihar

Decided
Disposal
DISPOSED

Holding

The Court held that, due to the limited scope of writ jurisdiction and the presence of factual disputes, it would not entertain the petition and disposed of it without granting relief.

Summary

The petitioner, Kaushal Ray, filed a public interest writ petition seeking a direction to the State and other respondents to provide permanent road connectivity from Tamtam Padaau to Anisabad Jagdeopath Road, alleging that the temporary diversion constructed for a railway under‑pass was inadequate. Respondent No.3, a senior project engineer of the Bihar State Bridge Construction Nigam Ltd., submitted a counter‑affidavit stating that a proper diversion had already been provided and that technical constraints prevented construction of an additional diversion on the eastern side of the under‑pass. The petitioner’s counsel filed a rejoinder, but the Court noted that the writ jurisdiction is not suited for adjudicating factual disputes. Consequently, the Court declined to entertain the contested facts and refrained from issuing any further order. The petition was therefore disposed of without relief.

Issues considered

  • Whether the State and related agencies are legally obligated to provide permanent road connectivity in place of the temporary diversion pending completion of the railway under‑pass.
  • Whether the writ petition is maintainable given the factual dispute over the adequacy of the existing diversion.

Subjects

  • public interest litigation
  • writ jurisdiction
  • road connectivity
  • railway under‑pass
  • temporary diversion
  • administrative law

Judgment

                      IN THE HIGH COURT OF JUDICATURE AT PATNA
                                Civil Writ Jurisdiction Case No.19403 of 2025
                 ======================================================
                 Kaushal Ray S/o Late Subalal Ray, resident of Gram Ufarpura, P.S.- Dhanaut,
                 District- Patna.

                                                                             ... ... Petitioner/s
                                                   Versus
           1.    The State of Bihar through the Chief Secretary, Bihar, Patna.
           2.    The Additional Chief Secretary, Road Construction Department, Bihar,
                 Patna.
           3.    The Managing Director, Bihar State Bridge Construction Nigam Limited,
                 Patna.
           4.    The Chief Engineer Cum Additional Commissioner Cum Special Secretary,
                 Road Construction Department, Bihar, Patna.
           5.    The Commissioner, Patna Division, Patna.
           6.    The Collector, Patna.
           7.    The Circle Officer, Phulwarisharif, Patna.
           8.    The Circle Officer, Danapur, Patna.
           9.    The Union of India through the Divisional Railway Manager, Danapur,
                 Patna.

                                                           ... ... Respondent/s
                 ======================================================
                 Appearance :
                 For the Petitioner/s    :       Mr. Sunil Kumar, Adv
                 For the State           :       Mr. Additional Solicitor General
                 For the U.O.I.          :       Mr. Dr. Chandra Shekhar Azad, CGC
                 For BSBCN Ltd.          :       Mr. P.K. Shahi, Sr. Adv
                                                 Mr. Vikas Kumar, Adv
                 ======================================================
                 CORAM: HONOURABLE THE CHIEF JUSTICE
                         and
                         HONOURABLE MR. JUSTICE ALOK KUMAR SINHA
                                       ORAL ORDER

                 (Per: HONOURABLE THE CHIEF JUSTICE)

6   09-02-2026                      This writ petition has been filed by the petitioner

                   Kaushal Ray in the nature of Public Interest Litigation seeking

                   for the following reliefs:

                                                       “For     a     direction      to     the
                                             Respondents to give connectivity to Main
Patna High Court CWJC No.19403 of 2025(6) dt.09-02-2026
                                           2/4




                                  Road from (Tamtam Padaau) Anisabad
                                  Jagdeopath         Road     after    constructing
                                  diversion on the North-East of Railway
                                  Under-Pass, which has been temporarily
                                  developed for connectivity of the people for
                                  the    period      the    main   Under-Pass    is
                                  constructed over Railway Crossing No.33
                                  between Phulwarisharif Railway Station to
                                  Danapur Junction for smooth and easy
                                  connectivity of people at large of the said
                                  locality.”


                      2. A counter affidavit has been filed by respondent no.

          3, Sanjiv Kumar, Senior Project Engineer, Bihar Rajay Pool

          Nirman Nigam Limited, Patna-1 wherein in paragraph nos. 5,6,

          8 and 10, it is stated as follows:

                                               “5. That at the outset, it is
                                  submitted that the present writ petition is
                                  totally misconceived as the answering
                                  respondent have already given connectivity
                                  to Main road from (Tamtam Padaau)
                                  Anisabad         Jagdeopath         Road    after
                                  constructing diversion on the North East of
                                  Railway Under Pass which has been
                                  temporarily developed for connectivity of the
                                  people for the period main under Pass.
                                               6. That due to ongoing under pass
                                  work across railway line, proper diversion
Patna High Court CWJC No.19403 of 2025(6) dt.09-02-2026
                                           3/4




                                  has been provided for giving connectivity
                                  one side of Railway Line to other side of
                                  railway People crossing across the Railway
                                  Line through this diversion. Once the under
                                  pass work is completed this under pass will
                                  be used for crossing across the Railway
                                  Line.
                                              8. That the statement made in
                                  Para 2 is misconceived, misleading and
                                  contrary to the facts of the case. Proper
                                  diversion has been provided for giving
                                  connectivity one side of Railway Line to
                                  other side of railway. People crossing across
                                  the Railway Line through this diversion.
                                  Once the under pass work is completed this
                                  under pass will be used for crossing across
                                  the Railway Line and at present there is
                                  inconvenience in crossing the Railway line
                                  through the Diversion constructed for this
                                  purpose. A site sketch is being enclosed for
                                  proper appreciation of the matter.
                                              10. That in reply to the statement
                                  made in Para 5 to 7 of the writ petition, it is
                                  submitted that one diversion has been
                                  provided on the western side of the under
                                  construction Under Pass and movement of
                                  traffic is smooth though this diversion. It is
                                  technically not possible to construct any
                                  diversion on the eastern side of under pass
                                  due to railway line thoughout. Diversion on
          Patna High Court CWJC No.19403 of 2025(6) dt.09-02-2026
                                                     4/4




                                            western side was possible at the location of
                                            an old bridge/damaged bridge.”


                                3. Though the learned counsel for the petitioner has

                    filed the rejoinder affidavit to the counter affidavit disputing the

                    stand taken by the respondent no. 3, Sanjiv Kumar but since

                    limited scope is available in writ jurisdiction, we are not

                    inclined to enter into this disputed question of fact and after

                    going through the stand taken by the respondent no. 3, Sanjiv

                    Kumar, we are not inclined to pass any further order in this writ

                    petition.

                                4. Accordingly, the present writ petition is disposed

                    of.



                                        (Sangam Kumar Sahoo, CJ)


                                            ( Alok Kumar Sinha, J)
kiran/-