Patna High Court

Rohit RanjanversusThe State of Bihar

Decided
Disposal
ALLOWED

Holding

The cancellation order was inappropriate, arbitrary and not in public interest, and is set aside.

Summary

The petitioner, Rohit Ranjan, was awarded a work order for the MMGSY road construction package and was issued a Letter of Acceptance on 23‑12‑2025, which he received on 04‑01‑2026. He failed to furnish the required performance bank guarantee within the stipulated 15‑day period due to a typhoid illness, but subsequently submitted the guarantees on 18‑02‑2026 and 26‑02‑2026, which the respondents accepted. The Department cancelled the work order on 14‑02‑2026 on the ground of non‑submission of the guarantee and issued orders directing re‑tendering. The petitioner challenged the cancellation, seeking certiorari and mandamus to enforce the original award. The Court examined whether the cancellation was justified given the later submission and acceptance of the guarantee and found the order to be arbitrary, not in public interest, and therefore set it aside. Consequently, the writ petition was allowed and the cancellation orders were vacated.

Issues considered

  • Whether the cancellation of the work order on the ground of delay in furnishing the performance bank guarantee is justified when the guarantee was later submitted and accepted.
  • Whether the Department's order to cancel and re‑tender the work is arbitrary and contrary to public interest.

Subjects

  • performance bank guarantee
  • work order cancellation
  • public interest
  • arbitrariness
  • certiorari
  • mandamus
  • tender re‑evaluation
  • Rural Works Department
  • Bihar

Judgment

                      IN THE HIGH COURT OF JUDICATURE AT PATNA
                               Civil Writ Jurisdiction Case No.4359 of 2026
                 ======================================================
                 Rohit Ranjan son of Jainendra Kumar, Moriya Vihar Colony Transport Nagar,
                 B.H Colony, P.O and P.S-Agamkuan, District-Patna Bihar. (Bid I.D-142525).

                                                                          ... ... Petitioner/s
                                                  Versus
           1.    The State of Bihar through Additional Chief Secretary (ACS), Rural Works
                 Department, Government of Bihar, Patna.
           2.    The Additional Chief Secretary (ACS), Rural Works Department,
                 Government of Bihar, Patna.
           3.    The Secretary, Rural Works Department, Government of Bihar. Patna.
           4.    The Engineer-in-Chief, Rural Works Department, Government of Bihar.
                 Patna.
           5.    The Chief Engineer-1, Rural Works Department, Bihar, Patna.
           6.    The Superintending Engineer, Work Division Nalanda, Rural Works
                 Department, Government of Bihar, Patna.
           7.    The Executive Engineer, Work Division Hilsa, Rural Works Department,
                 Bihar, Patna.
           8.    The Nodal Officer, MMGSY, Rural Works Department, Bihar, Patna.
           9.    The Technical Bid Evaluation Committee, in relation to Package No.
                 MMGSY (Awesh - GEN) HILSA-342 (Tender ID-144895) in connection
                 with NIT No. RWD/MMGSY (AWSESH- GEN)/HQ/ET/2025-26/12 dt.
                 09.09.2025 represented through Engineer-in-Chief, Rural Works
                 Department, Government of Bihar, Patna.

                                                           ... ... Respondent/s
                 ======================================================
                 Appearance :
                 For the Petitioner/s   :      Mr. Ashish Giri, Sr. Adv.
                                               Mr. Sumit Kumar Jha, Adv.
                                               Mrs. Riya Giri, Adv.
                 For the State          :      Mr. Raghwanand, GA-11
                                               Mr. Pratik Kumar, AC to GA-11
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
                         and
                         HONOURABLE MR. JUSTICE SHAILENDRA SINGH
                                       ORAL ORDER

                 (Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)

3   31-03-2026                    Heard learned counsel for the parties.

                                 2. Following are the reliefs sought in the present writ

                   application :
Patna High Court CWJC No.4359 of 2026(3) dt.31-03-2026
                                            2/4


                                     "i) To issue a writ/order/ direction in
                         the nature of certiorari to set aside the office order
                         contained in Memo No.94 dt. 13.02.2026 issued
                         under the signature of superintending Engineer,
                         Rural Works Department, work division, Nalanda
                         by     which      the    Superintending      engineer
                         recommended for cancelling the work order issued
                         in the favour of the petitioner and for seizure of
                         performance guarantee submitted by the petitioner
                         in relation to package no. MMGSY (Awesh- GEN)
                         HILSA-342 (Tender ID- 144895).
                                     ii) To issue a writ/order/direction in the
                         nature of certiorari to set aside the office order
                         contained in order No.19 dt. 14.02.2026 issued
                         under the signature of Chief Engineer-1, Rural
                         Works Department, Patna by which the Chief
                         engineer -1 cancelled the work order issued in the
                         favour of the petitioner vide memo no. 2285 dt.
                         18.12.2025 in light of recommendation of the
                         Superintending engineer dt. 13.02.2026. package
                         no. MMGSY (Awesh - GEN) HILSA-342 (Tender
                         ID-144895)
                                     iii) To issue a writ/order/ direction in
                         the nature of certiorari to set aside the office order
                         contained in Memo No.387 dt. 16.02.2026 issued
                         under the signature of executive engineer, Rural
                         Works Department, work division, Hilsa by which
                         the Respondent executive engineer has
                         recommended the Nodal officer, MMGSY Rural
                         work department Patna to re-tender the package
                         bearing package no. MMGSY (Awesh GEN)
                         HILSA-342
                                     iv) To issue a writ/order/ direction in
                         the nature of mandamus directing the respondent
                         authorities to allow the petitioner to enter into the
                         agreement in relation to MMGSY (Awesh GEN)
                         HILSA-342 (Tender ID-144895) which has been
                         awarded in favour of the petitioner through LOA
                         as contained in memo no.2702 dt. 23.12.2025.
                                     v) To issue a writ/order/ direction in the
                         nature of mandamus directing the respondent
                         authorities to allow the petitioner to start the work
                         of construction of road which have been awarded
                         to the petitioner through LOA as contained in
                         memo no. 2702 dt. 23.12.2025.
Patna High Court CWJC No.4359 of 2026(3) dt.31-03-2026
                                            3/4


                                    vi) To pass interim /exparte interim
                         direction to restrain the respondents from
                         retendering the work/ package bearing package
                         no. MMGSY (Awesh - GEN) HILSA-342 (Tender
                         ID-144895) and / or staying the operation of
                         impugned order of cancellation of work order
                         dated 14.02.2026 during pendency of this writ
                         petition.
                                    vii) To any other relief or reliefs for
                         which the petitioner is found to be entitled in the
                         facts and circumstances of the case."

                       3. A limited issue arises for consideration before this

          Court, namely, whether the cancellation of the work order on

          account of delay in furnishing the performance bank guarantee is

          justified, particularly in the facts of the present case, where the

          performance bank guarantee has subsequently been furnished and

          still retained by the respondents.

                       4. It is not in dispute that the work order came to be

          cancelled vide order dated 14.02.2026 (Annexure-P/9) on the

          ground that the performance bank guarantee was not submitted

          within the stipulated period.

                       5. Mr. Ashish Giri, learned senior counsel appearing on

          behalf of the petitioner, submits that although the Letter of

          Acceptance (LoA) was issued on 23.12.2025, but it came to be

          received on 04.01.2026. The petitioner, on account of being

          diagnosed with typhoid and being under medical advice for

          complete bed rest, could not furnish the performance bank

          guarantee within the stipulated period of 15 days. It is further

          submitted that the petitioner has since furnished the bank
          Patna High Court CWJC No.4359 of 2026(3) dt.31-03-2026
                                                      4/4


                    guarantees on 18.02.2026 and 26.02.2026 (Annexure-P/7), which

                    have been accepted by the respondents. The petitioner also

                    undertakes to complete the work within the prescribed time

                    without seeking any extension.

                                 6. Mr. Raghwanand, learned counsel for the State, upon

                    query of this Court, submits that no fresh tender has been floated

                    till date in respect of the work in question.

                                 7. Considering the explanation offered for the delay by

                    the petitioner, and the acceptance of the performance bank

                    guarantee by the respondent-department, as also the information

                    made by the respondent that no fresh tender has been floated, and

                    the undertaking of the petitioner that the work would be

                    completed within stipulated time frame, this Court is of the view

                    that the impugned order dated 14.02.2026 (Annexure-P/9) seems

                    inappropriate, arbitrary and not to be in public interest, and is

                    accordingly set aside.

                                 8. The writ application, accordingly, stands allowed.

                                 9. Pending application(s), if any, shall also stand

                    disposed of.


                                                (Sudhir Singh, J)


                                             ( Shailendra Singh, J)
annu/Rajesh