Patna High Court
Rajendra UpadhyayversusThe State of Bihar through Principal Secretary,
- Decided
- Disposal
- DISPOSED
Holding
The Court did not decide the merits but ordered the Collector to expedite disposal of the Section 18 application within two months.
Summary
The appellants, Rajendra and Shiv Nandan Upadhyay, filed a Letters Patent Appeal against the State of Bihar and several officials concerning land taken for flood protection projects. They had received Rs. 35,178 as compensation, which was undisputed, but claimed entitlement to the portion of land not formally acquired. They also filed an application under Section 18 of the Land Acquisition Act, 1984 for appropriate compensation, which has been pending before the Collector for three years. The Court noted the delay and directed the Collector to dispose of the application within two months of the order, without expressing any view on its merits. The Court further held that the appellants may pursue any other remedy against the State’s use of land without acquisition, and the appeal was disposed.
Issues considered
- The appellants' entitlement to land not covered by the acquisition process
- Whether the pending application under Section 18 of the Land Acquisition Act, 1984 should be expedited
- The legality of the State utilizing land without formal acquisition
Legislation cited
- Land Acquisition Act, 1984 — s. 18
Subjects
- land acquisition
- compensation
- Section 18
- collector
- Bihar
- flood protection project
- Letters Patent Appeal
Judgment
IN THE HIGH COURT OF JUDICATURE AT PATNA
Letters Patent Appeal No.177 of 2025
In
Civil Writ Jurisdiction Case No.7334 of 2024
======================================================
1. Rajendra Upadhyay S/o Late Vrajanandan Upadhyay @ Brij Nandan
Upadhyay, R/o Village - Jitan Chapra, Dulinbazar, P.O. Rajipur, P.S. - Rani
Talab, District- Patna.
2. Shiv Nandan Upadhyay S/o Late Vrajanandan Upadhyay @ Brij Nandan
Upadhyay, R/o Village - Jitan Chapra, Dulhinbazar, P.O. Rajipur, P.S. - Rani
Talab, District- Patna.
... ... Appellant/s
Versus
1. The State of Bihar through Principal Secretary, Water Resources
Department, Government of Bihar, Patna.
2. The Principal Secretary, Department of Revenue and Land Reforms, Land
Acquisition Directorate Bihar Patna.
3. The Director, Land Acquisition and Rehabilitation, Water Resources
Department, Bihar, Patna.
4. The Commissioner for Rehabilitation and Resettlement, Bihar, Patna.
5. The Chief Engineer, Water Resources Department, Bihar Patna.
6. The Collector, Patna, District- Patna.
7. The Special Land Acquisition Officer, Patna Flood Protection Project, Patna.
8. The Superintending Engineer, Ganga Sone Flood Protection Circle, Patna.
9. The Executive Engineer, Sone Flood Protection Division, Bihta, Patna.
10. The Executive Engineer, Sone Canal Division, Khagaul Patna.
11. The Land Acquisition Officer, Water Resources Department, Anisabad,
Patna.
12. The Sub Divisional Officer, Sone Flood Protection Sub- Division, Bihta,
Khagaul, Danapur, Patna.
... ... Respondent/s
======================================================
Appearance :
For the Appellant/s : Mr. Abhishek Kumar, Adv.
For the Respondent/s : Mr. Anjani Kumar, AAG-4
======================================================
CORAM: HONOURABLE THE CHIEF JUSTICE
and
HONOURABLE MR. JUSTICE HARISH KUMAR
ORAL JUDGMENT
Patna High Court L.P.A No.177 of 2025 dt.17-02-2026
2/3
(Per: HONOURABLE THE CHIEF JUSTICE)
Date : 17-02-2026
As per the order dated 08.01.2026 passed in the
present LPA, it is submitted by the learned AAG-4 that an
amount of Rs. 35,178/- (Rupees Thirty-five thousand one
hundred seventy eight only) has already been handed over to the
appellants, which is not disputed.
2. Learned counsel for the appellants, however,
submits that they are also entitled to get back the portion of the
lands, which were not under the land acquisition process.
Further, the appellants have already filed an application under
Section 18 of the Land Acquisition Act, 1984 for payment of
appropriate compensation, which is pending before the
Collector, Patna.
3. Since the application is made in February, 2023 and
three years have already been passed, this Court expects that the
Collector, Patna shall do the needful in expediting the disposal
of the application at an earliest, preferably within a period of
two months, from the date of production of the certified copy of
this order, if there is no other impediment.
4. It is made clear that we have not expressed any
opinion on the merits of such application. Accordingly, the
Patna High Court L.P.A No.177 of 2025 dt.17-02-2026
3/3
present LPA stands disposed off.
5. The appellants are also at liberty to avail any other
remedy, if they feel aggrieved with the action of the State in
utilizing the land without acquisition, in accordance with law.
(Sangam Kumar Sahoo, CJ)