Holding

The court held that there was no violation of the earlier order and therefore dismissed the petition for contempt.

Summary

Petitioner Rakesh Ranjan filed a writ petition seeking contempt proceedings against the Circle Officer and other officials for allegedly violating a court order dated 23‑04‑2024 in CWJC No.639 of 2019. The respondents submitted a show‑cause memorandum stating that only limited earthwork was carried out, that the land in question lies beyond the sanctioned project limit of 7.32 km chainage (the land is at 7.57 km), and that no construction activity is ongoing. They argued that the land therefore cannot be subject to acquisition under the approved scheme. The court examined the measurement report, the fresh verification report, and the project agreement, and found the respondents' explanations satisfactory. Consequently, the court disposed of the petition, granting the petitioner liberty to agitate the matter if desired, but not ordering contempt proceedings.

Issues considered

  • Whether the Circle Officer violated the order dated 23‑04‑2024 in CWJC No.639 of 2019 by proceeding with work on the petitioner's land.
  • Whether contempt proceedings can be initiated against the respondents for alleged non‑compliance with the earlier court order.

Subjects

  • contempt
  • land acquisition
  • irrigation project
  • court order compliance
  • show cause memorandum
  • jurisdiction

Judgment

                      IN THE HIGH COURT OF JUDICATURE AT PATNA
                               Miscellaneous Jurisdiction Case No.128 of 2026
                                                      In
                                 Civil Writ Jurisdiction Case No.639 of 2019
                 ======================================================
                 Rakesh Ranjan Son of Late Ramshidh Sharma @ Ramsidh Sharma, Resident
                 of Village Hardashpur, P.O.- Saho Bigha, P.S.- Ghosi, District- Jehanabad.

                                                                               ... ... Petitioner/s
                                                Versus
           1.    The State of Bihar, through its Chief Secretary, Shri Prataya Amrit
                 Government of Bihar, Patna.
           2.    Shri Santosh Kumar Mall, The Principal Secretary, Irrigation Department,
                 Government of Bihar, Patna.
           3.    Shri C.K. Anil, The Principal Secretary, Revenue and Land Reforms
                 Department, Government of Bihar, Patna.
           4.    Shri Allangkita Pandey, District Magistrate, Jehanabad.
           5.    Shri Arun Kumar Paswan, The Executive Officer, Irrigation Department,
                 Jehanabad.
           6.    Shri Sudhir Tiwary, The Circle Officer, Ghosi, District- Jehanabad.

                                                        ... ... Opposite Party/s
                 ======================================================
                 Appearance :
                 For the Petitioner/s     :        Mr.Arbind Kumar Singh, Advocate
                 For the Opposite Party/s :        Mr.Government Advocate 2
                 ======================================================
                 CORAM: HONOURABLE MR. JUSTICE RAJIV ROY
                                       ORAL ORDER

4   01-05-2026                    Heard the parties.

                                2. The present petition has been preferred for the

                   following relief/s:

                                              (i) "for initiation of contempt proceeding

                                              against the opposite parties specially the

                                              Circle Officer, Ghosi, Jehanabad for the

                                              violation of the order dated 23.04.2024

                                              passed by the Hon'ble Court in CWJC No.

                                              639 of 2019."
Patna High Court MJC No.128 of 2026(4) dt.01-05-2026
                                            2/4




                       3. A show cause has come on behalf of the opposite

          party nos. 04 and 06 and the learned State counsel has taken this

          Court to paragraph nos. 07 to 12 which read as under:

                                        7. That from the measurement report

                                        annexed by the petitioner himself as

                                        Annexure-P/4, it is evident that only

                                        limited earthwork was found on certain

                                        portions of the land, which was carried

                                        out by the Irrigation Department.

                                        8. That without prejudice to the above,

                                        and       taking    serious    note    of     the

                                        petitioner's claim, fresh verification was

                                        directed by the Circle Officer, Chosi

                                        vide Letter No. 504 dated 10.04.2026.

                                        9. That pursuant thereto, the Anchal

                                        Amin           submitted      report        dated

                                        11.04.2026, which          clearly establishes

                                        that no further work has been carried

                                        out and the earlier position remains

                                        unchanged.

                                        10. That it is further submitted that as

                                        per official records, the work under
Patna High Court MJC No.128 of 2026(4) dt.01-05-2026
                                            3/4




                                        Agreement No. 02/SBD/2018-19 dated

                                        19.04.2018 was sanctioned only up to

                                        7.32 KM chainage, whereas the land

                                        claimed by the petitioner situated at

                                        7.57 KM chainage, i.e.. beyond the

                                        sanctioned project limit.

                                        11. That the report clearly demonstrates

                                        that any earthwork found on the

                                        petitioner's land is beyond the approved

                                        project alignment and therefore cannot

                                        be treated as part of any sanctioned

                                        governmental        activity.   Consequently,

                                        such land is not liable to acquisition

                                        under the approved scheme.

                                        12. That it in further submitted that the

                                        land in question is presently lying

                                        unused         and there is     no ongoing

                                        construction activity over the same.

                       4. Learned State counsel with the help of paragraph-

          12 submits that the land in question is lying unused and there is

          no construction activity over it.

                       5. This Court is satisfied with the show cause filed by
         Patna High Court MJC No.128 of 2026(4) dt.01-05-2026
                                                     4/4




                   the opposite parties, the MJC No. 128 of 2026 is disposed of

                   with liberty to the petitioner to agitate the matter, if he so wants.



                                                  (Rajiv Roy, J)
Ravi/-