Created byFuzzy Cloud

High Court of Gujarat

YOGI CONSTRUCTION CO. A REGISTERED PARTNERSHIP FIRMversusTHE MUNICIPAL COMMISSIONER

Disposal
26-DISMISSED @ ADM.STAGE

Holding

The court held that the Municipal Corporation’s arbitrary and mala‑fide rejection of the bids, including improper reliance on stamp‑paper value, irrelevant litigation‑history disclosure, and the partner’s experience, invalidated the tender process, necessitating the setting aside of the award to SNL & Co. and directing consideration of other eligible bids.

Summary

The Gujarat High Court examined two writ petitions challenging the award of a Rs 122.97‑crore sewage‑treatment‑plant contract. R & B Infra Project Ltd. argued that its bid was unfairly rejected first for incomplete online upload, then on a technical ground that its MoU was on a Rs 100 stamp paper instead of Rs 300, and finally for alleged non‑disclosure of litigation history. Yogi Construction Co. contended its bid was rejected for not submitting a site‑visit certificate and an MoU in the prescribed format. The Court found the Municipal Corporation’s successive rejections to be arbitrary, noting the stamp‑paper issue was irrelevant, the litigation‑history clause applied only to black‑listing for delay, and the corporation’s reliance on a partner’s experience violated the tender’s explicit experience requirements. Consequently, the award to SNL & Co. was set aside and the corporation was directed to consider other eligible bids, while Yogi’s petition was dismissed for non‑compliance with mandatory site‑visit requirements.

Issues considered

  • Whether the Municipal Corporation’s rejection of R & B’s bid on the basis of stamp‑paper value and alleged non‑disclosure of litigation history was arbitrary and violative of tender conditions.
  • Whether the corporation’s reliance on the experience of a partner’s black‑listed firm to satisfy the work‑experience criterion for SNL & Co. was permissible.
  • Whether the absence of a geo‑tagged site‑visit photo and a specific MoU format justified the rejection of Yogi Construction’s bid.
  • Whether the court should intervene under Article 226 to set aside the award of the contract to SNL & Co.

Subjects

Tender lawPublic procurementTechnical non‑responsivenessArbitrarinessMala fideBlacklistingMoU stamp paperWork experience requirementSite‑visit certificateArticle 226

Judgment

 C/SCA/5436/2026                                  CAV JUDGMENT DATED: 08/05/2026




                                               Reserved On   : 01/05/2026
                                               Pronounced On : 08/05/2026

         IN THE HIGH COURT OF GUJARAT AT AHMEDABAD


          R/SPECIAL CIVIL APPLICATION NO. 5436 of 2026
                              With
          R/SPECIAL CIVIL APPLICATION NO. 4647 of 2026
==================================================
                    M/S R AND B INFRA PROJECT LIMITED
                                  Versus
                   THE MUNICIPAL COMMISSIONER & ORS.
==================================================
Appearance in SCA/5436/2026:
MR. MIHIR JOSHI, SENIOR ADVOCATE WITH MS. SIMRAN PAHWA,
ADVOCATE FOR THAKKAR AND PAHWA ADVOCATES(1357) for the
Petitioner(s) No. 1
MR. SAURABH SOPARKAR, SENIOR ADVOCATE WITH MR. D.M.
DEVNANI(5880), ADVOCATE for the Respondent(s) No. 1
MR. JAIMIN R. DAVE(7022), ADVOCATE WITH MS. MANVI A.
DAMLE(10805), ADVOCATE WITH MR. YASH SIKKA, ADVOCATE for the
Respondent(s) No. 4

Appearance in SCA/4647/2026:
MR. R. S. SANJANWALA, SENIOR ADVOCATE WITH MR.BHASH H.
MANKAD(6258), ADVOCATE for the Petitioner(s) No. 1
MR. SAURABH SOPARKAR, SENIOR ADVOCATE WITH MR. D.M.
DEVNANI(5880), ADVOCATE for the Respondent(s) No. 1

MR. JAIMIN R. DAVE(7022), ADVOCATE WITH MS. MANVI A
DAMLE(10805), ADVOCATE WITH MR. YASH SIKKA, ADVOCATE for the
Respondent(s) No. 2
==================================================

 CORAM:HONOURABLE MR.JUSTICE N.S.SANJAY GOWDA
       and
       HONOURABLE MR.JUSTICE J. L. ODEDRA


                            CAV JUDGMENT

 (PER : HONOURABLE MR.JUSTICE N.S.SANJAY GOWDA)




                                Page 1 of 44
 C/SCA/5436/2026                             CAV JUDGMENT DATED: 08/05/2026




[1]   In these two writ petitions, the award of tender for
designing and construction of Sewage Treatment Plant of 11.00
and 3.00 MLD, and also the designing and construction of
various pumping stations along with allied works, awarded in
favor of SNL & Company, is under challenge by two rival
bidders whose bid has been rejected. The estimated contract
value of this tender is about Rs.122.97 crores.

[2]   Special Civil Application No.5436 of 2026 is filed by M/s R
& B Infra Projects Limited (hereinafter referred to as “the R &
B”), who are aggrieved by the rejection of their tender on the
ground that the Memorandum of Understanding (MoU) that
they had entered into with the owner of an asphalt plant was on
a stamp paper of Rs.100/-, whereas the requirement of the
tender was that it ought to have been on an MoU of Rs.300/-.

[3]   After the bid was rejected on the aforementioned ground,
a subsequent order has been passed by the Municipal
Corporation to the effect that R & B had suppressed material
facts in relation to its litigation history, despite a specific clause
in the tender requiring that all litigations in the past five years
be disclosed and this would also result in them being
disqualified.


[4]   Special Civil Application No.4647 of 2026 is filed by Yogi
Construction Co., which is aggrieved by rejection of their tender
by the Corporation on the ground that they had not complied
with the six conditions of the tender, including the requirements


                              Page 2 of 44
 C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




of submission of a site visit certificate duly signed by the
engineer, and that the MoU submitted by it was not in
accordance with the format and requirement of the tender
conditions.

[5]   The following facts are not in dispute:-

[5.1] On 15.01.2026, the Corporation issued an invitation for
bids in respect of the aforementioned work, i.e., designing and
construction of a Sewage Treatment Plant, having an estimated
contract value of about Rs.122.97 crores. The last date for
submission of the bids was 23.02.2026 at 5:30 PM. One of the
requirements for submission of the bids was that the bid was to
be submitted online. However, one of the conditions of the
tender was also that physical copies of the bid that had been
submitted online was also required to be submitted to the
Corporation.

[5.2] After the online submission, it was noticed by the R & B
that out of the 139 pages, only 106 pages had been uploaded, as
per the portal, and as a consequence R & B contacted the entity,
and it was informed that the discrepancy was due to the manner
in which the documents had been uploaded. It appears that the
bidder was required to upload four to five documents at a time,
wait for the message ‘files signed and saved successfully', and
only thereafter could the next set of files be uploaded.
Apparently, since R & B had not followed this procedure, the
entire set of documents had not been uploaded.



                             Page 3 of 44
 C/SCA/5436/2026                           CAV JUDGMENT DATED: 08/05/2026




[5.3] Clause 24 of the tender conditions required that all tender
documents should also be submitted through speed post so as to
reach the Municipal Corporation within seven working days
from the last date. R & B had, in fact, submitted all the tender
documents physically within the required time frame of seven
days. However, R & B was informed that their tender submitted
online would not be considered since all the documents had not
been uploaded.


[5.4] The petitioner, as a consequence, approached this Court in
Special Civil Application No.4641 of 2026, and this Court, by an
order dated 01.04.2026, disposed of the writ petition directing
the Corporation to consider the documents which R & B had
physically submitted and thereafter take a decision on the bids
submitted by R & B and also by the others, on their merits.



[5.5] The Corporation had, in fact, informed the Court that the
tender had been opened, negotiations had been undertaken, and
a work order had also been issued. It was, however, submitted
before the Court that the said decision would be kept in
abeyance till the case of R & B was considered.


[5.6] Pursuant to the said order, the case of R & B was
considered and the bid was rejected on 07.04.2026 on the
ground that the MoU executed between R & B and its DI Pipe
Supplier and DWC Pipe Supplier had been executed on a non-


                            Page 4 of 44
 C/SCA/5436/2026                                       CAV JUDGMENT DATED: 08/05/2026




judicial stamp paper of Rs.100/- instead of a non-judicial stamp
paper of Rs.300/-. It appears that this defect had been pointed
out by the consultants engaged by the Corporation and this
defect had made the bid being technically non-responsive and
was therefore required to be rejected.


[5.7] R & B thereafter preferred a writ petition, i.e., Special
Civil Application No.11994 of 2026 on 13.04.2026, challenging
the said rejection.

[5.8] A week after the bid of R & B had been rejected, by way of
communication dated 20.04.2026, the Corporation informed R &
B that it was disqualified, as it had suppressed material
information regarding its blacklisting and the consequential
litigation in respect of the Black listing of a few of its other
tenders. As a consequence,                   this communication dated
20.04.2026, has also been challenged by R & B, by way of an
amendment.


[5.9] The facts, in so far as Yogi Construction Co. are
concerned, is that the Corporation refused to open its
commercial         bid   on   24.03.2026         and     they     are     therefore
constrained to file a writ petition seeking a direction to be
issued to the Corporation to pen their bids and to evaluate their
Technical bid and also for opening of their financial bid. They
also seek rejection of the award of the tender in favor of SNL &
Company.



                                  Page 5 of 44
    C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




[5.10]            The tender submitted by the Yogi Construction Co.
was not rejected due to six defects in their bid. The grounds, on
which it was held that Yogi Construction Co. did not technically
qualify, were that they did not meet the minimum experience,
and they had failed to provide details regarding litigation
history and staff requirements; and more importantly, they had
not visited the site and submit a geotagged photo of the site
visit duly certified by the concerned engineer and upload the
same. Their tender was also considered technically non-
responsive since the MoU that they had produced was not in
accordance with the terms and conditions of the tender,
inasmuch as they did not abide by the prescribed format that
had been adhered to by all the other bidders, and they had
produced only an MoU regarding the drum mix plant.


[6]      Shri Mihir Joshi, learned Senior Counsel, assisted by Ms.
Simran Pahwa, appearing on behalf of R & B, contended that:-


        The entire process adopted by the Corporation was
         manifestly arbitrary and was actuated by mala fides.

        The Corporation had initially rejected the tender on a
         hyper technical ground that all the documents had not
         been         uploaded,   and    thereafter,    pursuant        to    the
         intervention of this Court, which directed the bid to be
         considered on the basis of the physical documents that
         had been submitted. The Corporation, being annoyed by


                                    Page 6 of 44
    C/SCA/5436/2026                             CAV JUDGMENT DATED: 08/05/2026




         this, proceeded to reject the bid on the specious ground
         that the MoU which R & B had entered into with their pipe
         supplier was on a non-judicial stamp paper of Rs.100/-,
         whereas it ought to have been for a sum of Rs.300/-. This
         reason, which was not only trivial but totally unconnected
         to the merits of the claim of R & B, itself indicated that the
         Corporation was bent upon keeping R & B out of the entire
         tender process.

        The fact that after the bid of R & B was rejected, the
         Corporation proceeded to issue a communication holding
         that R & B was disqualified because they did not disclose
         their litigation history also fortifies the contention that the
         Corporation was discovering reasons to non-suit R & B.

        The fact that there was a second order disqualifying R &
         B, by itself, established that it had been pre-decided by the
         Corporation that the bid of R & B would never be
         considered.


        The reason why the bid of R & B was rejected was
         fundamentally because its financial bid was only 8% over
         the contractual value, whereas the bid of SNL & company
         was 33% over and it was therefore obvious that the
         Corporation wanted to favor SNL & company to facilitate
         them to earn a huge profit to the detriment of the public
         exchequer.




                                 Page 7 of 44
    C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




        The requirement of disclosing a blacklisting in other
         Tenders would not be relevant since the tender clause
         clearly stated that only if the bidder had been blacklisted
         for the delay in execution of the projects was the said fact
         required to be disclosed. If the blacklisting was for any
         reason other than delay, the bidder was not required to
         disclose the said fact. The Corporation basically intended
         to keep out only those bidders who were blacklisted
         because they had delayed the execution of the works, and
         it did not consider blacklisting for other reasons to be
         relevant.


        It is submitted that the litigation history, which R & B is
         alleged to have not disclosed, essentially pertained to
         litigation in respect of blacklisting of R & B for reasons
         other than delay in execution of the projects. A reading of
         the relevant clause relating to litigation history would
         indicate that only litigation history in respect of executed
         contracts or contracts being executed and awards
         obtained thereof was relevant, and this by itself clearly
         indicated that other kinds of litigation history was
         unnecessary.


        The litigation history sought was for the specific history
         relating to a specific set of facts, and therefore,
         demanding disclosure of litigation history with reference
         to facts which are not considered germane by the



                                Page 8 of 44
    C/SCA/5436/2026                             CAV JUDGMENT DATED: 08/05/2026




         Corporation is proof that the Corporation was seeking
         reasons to keep R & B out of the bidding process.


        The entire conduct of the Corporation in rejecting the bid
         of the tender of R & B by citing three different reasons at
         three different points in time, including a rejection after
         the initial disqualification, indicates that the entire tender
         process had a predetermined outcome, namely, to favour
         SNL & Company.

        SNL & Company was not even qualified to bid, inasmuch
         as it, being a proprietary concern, had absolutely no work
         experience in similar works.


        SNL & company, a proprietary concern owned by Mr.
         Siddharth Lunagariya and this Lunagriya was the main
         partner in N. P. Patel and Company. The proprietor of SNL
         & company, namely Mr. Siddharth Lunagariya was, in fact,
         holding a stake of 90% in N. P. Patel and Company, a
         partnership firm, indicating that the firm N. P. Patel and
         Company was nothing, but an entity wholly owned and
         controlled by him. The registration of N. P. Patel and
         Company as AA+ contractor was itself fraudulent,
         inasmuch as the work experience of N. P. Patel and
         Company had been relied upon to secure such registration
         and SNL & Co had absolutely no work experience as
         required under the Tender notification.



                                 Page 9 of 44
    C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




        N. P. Patel and Company, in which SNL & Co, the fourth
         respondent owned 90% of the firm, was admittedly a
         blacklisted company, and this order of blacklisting was
         confirmed by the High Court and also by the Hon’ble
         Supreme Court.


        In essence, since N. P. Patel and Company could not
         participate in the present tender, the person who owned
         90% in that firm created a proprietary concern, namely
         the 4th respondent and had proceeded to utilize the
         experience of N. P. Patel and Company, and submitted the
         bid basically to overcome the fact that N. P. Patel and
         Company could not have directly participated by virtue of
         its blacklisting.


        The tender notification did not permit the work experience
         of any person other than the bidder to be relied on, and
         since admittedly SNL & company had absolutely no work
         experience, it was wholly ineligible to participate in the
         tender.


[7]      Shri Saurabh Soparkar, learned senior counsel assisted by
Shri D. M. Devnani, appearing on behalf of the Corporation put
forth the following submissions:-


        The rejection of the petitioner's tender cannot be assailed,
         since the bid contained defects which were incurable.



                               Page 10 of 44
    C/SCA/5436/2026                              CAV JUDGMENT DATED: 08/05/2026




        Though the bid of the petitioner had been found to be
         defective and liable for rejection, it was later discovered
         that there was a glaring contravention of the tender
         condition, inasmuch as the petitioner had suppressed the
         history of litigation in which it had been engaged in
         respect of other tenders.


        The question of the petitioner's blacklisting was not of
         relevance, but the fact that he had litigated in various
         courts over a period of time would constitute a vital factor
         in determining the legitimacy of the petitioner’s bid. If a
         bidder had deliberately suppressed not just one but a
         large number of litigations, it was apparent that he was
         trying to mislead the Corporation, and therefore, on
         discovery of these suppressed facts, the Corporation was
         entitled to reject the bid.


        The petitioner had submitted its bid on 23.02.2026, and as
         on that day, he had in fact been blacklisted by two entities
         and despite a query raised by the Corporation regarding
         the blacklisting, the petitioner had not disclosed the
         litigation arising from such blacklisting.

        It is settled law that the satisfaction of the tender inviting
         authority was paramount, when it comes to the question of
         determining the practicality of awarding tender to a
         bidder. If the antecedents of the bidder were doubtful or


                                 Page 11 of 44
    C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




         suspicious, the tender inviting authority had the legal right
         to reject the bid, since the authority cannot be expected to
         take the risk of trusting a bidder who had not been fair in
         the submission of the bid.


        Insofar as the work experience of SNL & Company is
         concerned, the Corporation had followed the PWD Manual
         and had accepted the work experience of N.P. Patel &
         Company, in which the fourth respondent was a 90%
         partner.     The   PWD     Manual        permitted      taking       into
         consideration the work experience of a partner for the
         purpose of meeting the eligibility criteria, and thus, the
         decision of the Corporation cannot be found fault with.


        It was submitted that the Courts cannot minutely examine
         the assessment of a bid, as this is the prerogative of the
         tender inviting authority. The Courts are restrained from
         sitting in judgment over the decision of the tender
         accepting authority insofar as it relates to its satisfaction
         regarding the desirability of selecting a particular bidder
         to satisfy the terms of the contract.


        He submitted that a disqualified or an in eligible bidder
         cannot possess the legal right to challenge the award of a
         tender to any other bidder and hence the petition itself
         was not maintainable.




                                  Page 12 of 44
    C/SCA/5436/2026                              CAV JUDGMENT DATED: 08/05/2026




        He placed reliance on the following cases in support of his
         arguments:-


         i.       In the case of State of Madhya Pradesh and
                  another versus Uttar Pradesh State Bridge
                  Corporation Limited and Another reported in
                  (2022) 16 SCC 633.


         ii.      In the case of Silppi Construction Contractors
                  versus Union of India and another reported in
                  (2020) 16 SCC 489.


         iii.     In the case of Municipal Corporation, Ujjain and
                  another versus BVG India Limited & others
                  reported in (2018) 5 SCC 462.


         iv.      In the case of Afcons Infrastructure Limited
                  versus Nagpur Metro Rail Corporation Limited
                  & another reported in (2016) 16 SCC 818.


         v.       In the case of A.G.Construction through its
                  Authorised    Signatory        versus         State         of
                  Maharashtra and others reported in 2023 SCC
                  OnLine Bom.


         vi.      In the case of Mohammad Arif Shaikh versus
                  Madhya Pradesh Paschim Kshetra Vidyut Vitran



                                 Page 13 of 44
    C/SCA/5436/2026                                 CAV JUDGMENT DATED: 08/05/2026




                  Co. Ltd. through Managing Director reported in
                  2017 (3) M.P.L.J.


         vii.     In the case of Akash Infra Projects Limited
                  versus   Ahmedabad             Municipal       Corporation
                  reported in 2020 (O) AIJEL-HC247918.


[8]      Shri Jaimin R. Dave, learned counsel appearing on behalf
of SNL & Company supported the argument of Shri Soparkar,
learned senior counsel and stated that the acceptance of the bid
of SNL & Company could not be called in question. He placed
reliance on the following case in support of his arguments:-


         i.       In the case of N.G.Projects Limited versus Vinod
                  Kumar Jain and others reported in (2022) 6 SCC
                  127.


[9]      Shri R. S. Sanjanwala, Learned Senior Counsel assisted by
Shri Bhash H. Mankad, appearing for the Yogi Construction and
Co. submitted that:-


        The rejection of Yogi's bid was on frivolous reasons. He
         submitted that the reason put forth, namely the absence of
         a site visit certificate along with a geo-tagged photograph
         was an insignificant requirement. Even assuming, for the
         sake of argument, that the site visit had not been
         conducted by the petitioner, the same would not render
         the bid defective.

                                 Page 14 of 44
    C/SCA/5436/2026                              CAV JUDGMENT DATED: 08/05/2026




        He further submitted that the requirement of a site visit
         certificate along with a geo-tagged photograph was
         insignificant, and even if such a visit had not been
         undertaken, that would not render with bid defective.
         Even if it is assumed that the site visit had not been
         carried out, at best, the petitioner would be taking a risk
         in the execution of the contract and could not obviously
         thereafter contend that he was unaware of the site
         conditions. If a bidder does not comply with a condition
         that was designed for his benefit, the same cannot be used
         as a ground to reject a tender.


        Yogi Construction Co. had produced an MoU in relation to
         hiring a drum-mix plant, and this satisfied the condition of
         the tender. He emphasized that the tender document
         required     an   MoU   evidencing      an   understanding           or
         agreement in relation to an asphalt plant. However, the
         corrigendum to the tender permitted a bidder to use a
         drum-mix plant, which is the same as an asphalt plant, and
         thus the requirement of the tender notification stood
         satisfied.


        He submitted that a drum-mix plant is the same as an
         asphalt plant, and possessing of either of the two was
         sufficient; therefore, the tender condition stood satisfied
         the moment there was a lease agreement in respect of a
         drum-mix plant.


                                 Page 15 of 44
    C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




[10] Insofar as the writ petition filed by Yogi Construction Co.
is concerned, Shri Saurabh Soparkar, learned senior counsel
contended that:-


        Though the bid was rejected on six grounds, the writ
         petition was liable to be dismissed only on the ground that
         the     required   documents      along    with     the     necessary
         certification had not been produced by Yogi Construction
         Co., and also because the MoU, which was a mandatory
         requirement, had not been submitted.


        It was contended that the tender document categorically
         stated that if the required documents were not submitted
         along with the tender, the same would be rejected.


        It is, in fact, admitted by the petitioner that the geo-tagged
         photograph, along with the certification of the concerned
         engineer regarding the site visit, was not furnished, and
         the MoU in the required format was also not produced;
         therefore, the rejection of Yogi Construction's bid cannot
         be found fault with.

        When the tender specified the requirement of an MoU in
         relation to an asphalt plant and a drum-mix plant, it was
         not open for the bidder to decide which of the two would
         satisfy the tender condition. Having participated in the
         tender, knowing fully well that certain conditions were


                                 Page 16 of 44
    C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




         required to be complied with, it was not open to the bidder
         to     thereafter   contend    that     those    conditions        were
         unnecessary or superfluous. He submitted that so long as
         the tender conditions had been accepted, adherence to
         them was mandatory.


[11] In the light of the above submissions, the following
questions would arise for consideration:-

        Whether R & B has established that the processing of the
         tender is manifestly arbitrary so as to warrant interference
         by this Court in exercise of its powers under Article 226 of
         the Constitution of India?

        Whether R & B has established that the Corporation was
         not justified in rejecting its bid on the ground that
         litigation history of the petitioner had not been disclosed?


        Whether R & B has established that it had satisfied the
         conditions of the tender and its bid was required to be
         considered on its merits?


        Whether R & B had established that SNL & Co was not
         entitled to be awarded the contract since it had no work
         experience at all?


        Whether the R & B has established that SNL & Co could
         not have relied on the work experience of NP Patel & Co,
         which was Blacklisted Concern and the properties of SNL

                                 Page 17 of 44
 C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




      & Co owned 90% of the firm and for all purposes was the
      true owner of the firm?

[12] At the outset, it is to be stated that the legal position in
relation to the interference of the Courts in matters related to
tenders is rather well settled. The Courts can only examine the
manner in which the tender is processed and consider whether
the terms of the tender have been adhered to by both the tender
inviting authority as well as the bidders. Though the scope of
interference by Courts is limited and lies within a narrow
compass, nevertheless, the law is also well settled that the
Courts are obliged to interfere when the procedure adopted in
the tendering process is manifestly arbitrary and is plainly
evident from the pleadings and also if the conduct of the parties
on the basis of admitted materials establish that the entire
tendering process was vitiated by wanton acts of mala fides.

[13] Since, this is the settled position of law, it would be
unnecessary to reiterate all the judgments cited by both the
parties, as they essentially convey the same principle. Thus, the
overarching concern of this Court is to examine whether the
procedure adopted by the Corporation for processing the tender
is fair, just and proper, and does not smack of arbitrariness or
mala fides.


[14] As noticed above, the tender is for the purpose of
establishing a Sewage Treatment Plant with an estimated
contract value of 122.97 crores. Thus, it is clear that the tender


                            Page 18 of 44
  C/SCA/5436/2026                           CAV JUDGMENT DATED: 08/05/2026




is not in relation to a work which can considered of a minor or a
trivial nature. The establishment of a Sewage Water Treatment
Plant would affect the entire city of Porbandar which houses
lakhs of people and hence, it would all the more be necessary to
examine whether the processing of the tender by the
Corporation has been just and proper and is in accordance with
established norms of law.


[15] In the present case, it is not in dispute that the bid
submitted by R & B was initially rejected on the ground that the
complete set of bid documents had not been uploaded. The
Corporation, though had received the hard copy of the tender
document as stipulated in the tender notification, refused to
consider the physical copy to consider the bid of R & B.
Admittedly, in the physical copy submitted by the petitioner, all
the documents, including those which had not been properly
uploaded, were available. Significantly, the hard copy had also
been furnished within the stipulated time. Nevertheless, the
Corporation chose to reject the tender. It was only upon the
intervention of this Court that the Corporation had to consider
the bid of R & B. It may be pertinent to note that the
Corporation has not found any deficiency in the bid which
affects it validity.


[16] On consideration of the petitioner's bid, the Corporation
has proceeded to reject the bid on a ground which is rather
strange. It appears that the Corporation had engaged the


                            Page 19 of 44
 C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




services of a consultant, who advised that the MoU submitted by
R & B could not be acted upon since it was executed on a non-
judicial stamp paper of Rs.100/-, as against the requirement of
Rs.300/-. In respect of a tender relating to the establishment of
a Sewage Treatment Plant, wherein one of the conditions
required an MoU to establish that the bidder had an agreement
with the supplier of pipes, the essential requirement for the
Corporation was to satisfy itself there existed a valid
arrangement between the bidder and the supplier for the supply
of those items which were essential for the execution of the
contract. The Corporation does not dispute the fact that there
was, in fact, an MoU between R & B and the supplier. The
Corporation has also not taken the stand that it had received
any complaint from the contracting party, i.e., the supplier, that
no such MoU had been executed.


[17] If the MoU was not executed on a stamp paper of the
requisite value, the authorities could, at best, have taken action
to ensure recovery of the stamp duty. By no stretch of the
imagination could the Corporation have rejected the bid on that
ground. The fact that the Corporation, through its consultant,
went into such microscopic details indicates that it was
essentially searching for some reason to reject the bid.

[18] This suspicion of the Court regarding the conduct of the
Corporation stands fortified by a further analysis of the manner
in which the Corporation has conducted itself thereafter.



                            Page 20 of 44
 C/SCA/5436/2026                                  CAV JUDGMENT DATED: 08/05/2026




[19] This rejection of the bid submitted by R & B for the second
time on the ground of insufficient stamp paper was made on
07.04.2026, and this writ petition challenging the same was
filed on 13.04.2026.


[20] On 18.04.2026, i.e., nearly 11 days after the bid was
rejected, the Corporation has addressed an email to R & B
(which is produced by the Corporation at Annexure R1), seeking
to raise a query as to whether it had been blacklisted by any
Municipal          Corporation   or   Central     Government        or     State
Government, and sought for the details of any such blacklisting.
A second notice was issued on the 20.04.2026, alleging that the
petitioner had not furnished details of its litigation history, and
related matters. This act of the Corporation, in issuing notices
after it had already rejected the tender bid of R & B on
07.04.2026 and after the filing of the writ petition, itself
indicates that the Corporation was aware that the reasons for its
earlier rejection were on weak grounds and it basically wanted
to discover new grounds to non-suit R & B.

[21] R & B, in fact, furnished a reply on 23.04.2026, wherein it
provided details of the litigation history in which it had been
engaged with other entities. At first blush, this admission by R &
B that it had engaged in litigation in respect of other tenders
would ordinarily have led this Court to conclude that there had
been suppression of material facts, necessitated dismissal of the
writ petition on that ground alone.


                                  Page 21 of 44
 C/SCA/5436/2026                               CAV JUDGMENT DATED: 08/05/2026




[22] The Corporation, on receipt of the reply of R & B,
thereafter, proceeded to pass an order to the effect that there
had been suppression of facts, and consequently, R & B was
declared disqualified from the tender. In essence, this was the
third time that bid of R & B was being rejected. The first
rejection was on 25.03.2026, when the bid was rejected on the
ground that all the documents had not been uploaded. The
second rejection was on 07.04.2026, on the ground that the
MoU produced by R & B was not on the requisite value of stamp
papers. The third rejection on 24.04.2026 was an order whereby
the Corporation declared R & B to be disqualified from
participating in the tender.


[23] This relentless conduct of the Corporation in finding
different grounds to reject the bid of R & B, not once but thrice,
raises serious doubts about its bona fides and the manner in
which it has evaluated the tenders submitted by the petitioner.



[24] Be that as it may, it would be desirable to examine
whether there has been a flouting of the tender condition by R
& B on the ground that it had not disclosed the litigation history
as required under the tender notification.


[25] The clause relating to litigation history reads as follows:-




                               Page 22 of 44
 C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




      “4.5.8.      Litigation History
      The Applicant should provide accurate information on any
      litigation or arbitration resulting from contracts completed or
      under execution by him over the last five years. A consistent
      history of awards against the Applicant or any partner of a joint
      venture may result in failure of the applicant.”


[26] The clause relating to blacklisting would first have to be
considered to understand the import of the above clause. That
the relevant clause relating to blacklisting is Clause 4.7.8, which
reads as follows:-

      “VI) The Bidder/JV MEMBER/MOU partners contract should not
      have been terminated/blacklisted/debarred in any State Govt/
      Municipal Corporations/ Central Govt./ Any state Govt
      Organization, Urban Local body and/or its undertaking company
      or its SPV, Asian Development Bank/ World Bank or similar
      international funding agencies organizations due to delay in
      projects during last five years.”


[27] A plain reading of this particular clause would indicate
that the a contract of the bidders with other entities, which they
had executed should not have been terminated, the bidder
should not have been blacklisted or debarred on the ground that
there had been a delay in the execution of the projects in the
preceding five years. Thus, through the said clause in the tender
notification, the Corporation was only interested in knowing for
a fact whether the contract of bidder had been terminated or
whether the bidder had been blacklisted or debarred because
they had delayed the execution of the projects. In other words,
the capability of the bidders to execute the work within the
prescribed time frame was all that the Corporation was interested
in, which is understandable given the nature of the project.


                                Page 23 of 44
 C/SCA/5436/2026                             CAV JUDGMENT DATED: 08/05/2026




[28] The unmistakable consequence of a plain reading of this
clause is that if the contract of the bidder had been terminated,
or if the bidder had been blacklisted or debarred on any other
ground was not considered to be a disqualification for the
bidder to apply. To put up differently, it is only if a bidder had
suffered the termination of the contract, or blacklisting or
debarment in other contracts in the past five years, for the
reason that there was a delay in the execution of the projects, it
is only then that the bidder would be ineligible to succeed in his
bid.


[29] The further consequence of this clause is that if a bidder
had been blacklisted for any reason other than delay in
execution of the projects, then, the Corporation did not consider
it as a disqualification and that it was basically not interested in
knowing            whether     there         had           been               a
termination/blacklisting/debarring for any other reason.

[30] If it was the intention of the Corporation that all kinds of
blacklisting, debarment or termination of other contracts,
irrespective of the reason, were material facts to be disclosed by
the bidder, the tender clause would not have indicated that the
blacklisting, debarment or termination of the contract should
only be for the specific reason of delay in execution of the
project.

[31] It is the admitted case of R & B that in respect of three



                             Page 24 of 44
 C/SCA/5436/2026                               CAV JUDGMENT DATED: 08/05/2026




contracts it had been blacklisted. However, it is specifically
contended that the blacklisting was not because there was any
delay in the execution of the contract and the blacklisting was
for other technical reasons. This assertion of R & B that the
blacklisting was not for reasons relating to the execution of its
other contracts, is not disputed by the Corporation.

[32] It may also be pertinent to state here that R & B had, in
fact, given a reply in response to the query raised by the
Corporation after its contract was terminated, and in this reply
also they have stated the blacklisting suffered by them and also
narrated the reasons. R & B also produced the copies of the
order passed by the High Courts of Rajasthan, which clearly
established that the blacklisting was not because of any delay
on their part in the execution of the contract. In fact, the
blacklisting was on account of submission of false experience
certificate. It is thus clear that as the contracts of R & B with
other entities had not been terminated or they had been
blacklisted or debarred for causing a delay in the execution of
the contracts and they were as a consequence not disqualified
to participate in the tender as contemplated in the tender
condition referred to above.

[33] Shri Soparkar, learned Senior Counsel, however, argued
that even assuming that the blacklisting was not for delay in the
execution of the projects, nevertheless, R & B was guilty of
flouting a vital tender clause, namely the clause relating to
litigation history.


                               Page 25 of 44
 C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




[34] The clause in relation to litigation history, as cited above,
would clearly indicate that the bidder is required to provide
accurate information on any litigation or arbitration in respect
of completed contracts or contracts which are under execution
in the last preceding five years. This clause indicates that if
there is a consistent history of awards against the bidder or any
partner of a joint venture, that could result in failure of the
applicant. It is rather obvious that this clause could not be
pressed into service by the Corporation to non-suit the
petitioner.


[35] As noticed above, the Corporation was interested in
knowing only kind of blacklisting i.e., blacklisting for the delay
in execution of the project. The Corporation, by necessary
implication, was not holding the blacklisting of a bidder for any
other reason as a disqualification of the bidder. To put it
differently, the Corporation only wanted to know whether the
blacklisting was for the reason of causing a delay in the
execution of the project. If this is the admitted position, the
litigation arising out of a blacklisting which was a reason other
than delay in the execution of the projects, would really be of no
consequence and would not be a material fact which had to be
disclosed to the Corporation.

[36] It is also important to note that the clause relating to
litigation history is also specifically worded to state that the
litigation should be in relation to the contracts which are


                            Page 26 of 44
 C/SCA/5436/2026                             CAV JUDGMENT DATED: 08/05/2026




completed or which are under execution. The further use of the
term "the consistent history of awards against the bidder" would
indicate that the litigation was obviously only in relation to the
execution of the contract.

[37] In other words, only if there was litigation in relation to
the manner in which a contract had been executed was the
bidder required to really disclose the same. The reason for such
disclosure is also found in the very same clause, which states
that the bid of the applicant could be rejected if there was a
consistent history of awards against him. This would therefore
remove all ambiguity regarding the litigation history that was to
be disclosed by a bidder. It is clear that the litigation history in
relation to the actual execution of a work or the contracts that
were still under execution by him was a fact which was to be
disclosed to the Corporation.

[38] As far as R & B is concerned, the blacklisting in respect of
other tenders was due to their lapse in such as submission of
false experience certificate, and all the litigation that R & B had
engaged into was in relation to this aspect of blacklisting only.


[39] As already noticed above, if blacklisting was for reasons
other than delay in execution of the project, the same was
irrelevant as regards the corporation's term of disclosure, and
as a logical consequence, the subsequent litigation in relation to
such an irrelevant factor need not be disclosed or the non-
disclosure of this irrelevant factor would not affect the integrity


                             Page 27 of 44
 C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




of the bidder. It is therefore clear that the Corporation has
searched for reasons to disqualify the petitioner. It is therefore
clear that the manner in which the Corporation has undertaken
the   tender       process   smacks     of arbitrariness       and, as           a
consequence, this Court will be obliged to intervene and annul
the arbitrariness.


[40] There is yet another reason to interfere in this tender
process which is much more weighty and is a crucial factor in
relation to the execution of the project.


[41] Shri Mihir Joshi, learned Senior counsel pointed out that
the tender condition required the bidder to possess certain
qualification criteria which was spelt out in Clause 4.5.3 of the
tender condition, which related to general experience, and the
same is reproduced here for the sake of clarity:-

      “4.5.3. General Experience.

      The Applicant shall meet with the following minimum criteria:

      (e) Achieved a minimum annual financial turnover (defined as
      billing for works in progress and completed in all classes of civil
      engineering construction works only) in any one year, over the
      last five years of the annual value of contract / contracts applied
      for as per below criteria.

      (b) Experience in successfully completing or substantially
      completing at least one contract of Sewerage at least percent
      mentioned in below criteria of the value of proposed contract
      within the last five years.

      The works may have been executed by the applicant as prime
      contractor or as a member of a joint venture or as a nominated
      sub-contractor. As subcontractor, he should have acquired the



                                Page 28 of 44
 C/SCA/5436/2026                                 CAV JUDGMENT DATED: 08/05/2026




      experience of execution of all major items of works under the
      proposed contract. In case a project has been executed by a joint
      venture, weight towards experience of the project would be given
      to each joint venture in proportion to their financial participation
      in the joint venture.

      Substantially completed works means those works which are at
      least 90% completed as on the date of submission (i.e. gross
      value of work done up to the last date of submission is 90% or
      more of the original contract price) and continuing satisfactorily.
      For these, a certificate from the employers shall be submitted
      along with the application incorporating clearly the name of the
      work, contract value, billing amount, date of commencement of
      works, satisfactory performance of the contractor and any other
      relevant information.


[42] Clause 4.5.3 sub-clause (b) categorically states that the
applicant should have experience in successfully completing or
substantially completing at least one contract of Sewage
Treatment Plant with the percentage prescribed therein of the
value of the proposed contract in the preceding five years. This
would therefore mean that SNL & Company which should have
substantially completed at least one contract of Sewage
Treatment Plant of the prescribed value in the preceding five
years.


[43] The second para of Clause (b) also states that the works
could have been executed by the bidder, either as a prime
contractor or as a member of a joint venture or as a nominated
subcontractor.


[44] It is not in dispute that SNL & Company has not executed
any work either as a prime contractor or as a member of a joint
venture or as a nominated subcontractor. Thus, on a plain

                                 Page 29 of 44
 C/SCA/5436/2026                                      CAV JUDGMENT DATED: 08/05/2026




reading of this particular clause, it is obvious that SNL &
Company did not possess any experience at all in the
construction of a Sewage Treatment Plant in the preceding five
years.


[45] However,       the   Corporation           has    embarked         upon       an
ingenious defense to get over this lacuna and defend their
acceptance of bid of SNL & Company. The Corporation, in its
affidavit in reply (in para 8), has stated that SNL & Company
was holding a valid “AA class” certificate and it was therefore
entitled to participate. It has also gone on to state that if R & B
had any grievance regarding AA class certificate, they would
have to challenge it, and so far as the Corporation was
concerned, it is bound by the certification.

[46] Insofar as the work experience, in para 33 it is stated as
follows:-


      “33. Furthermore, it is submitted that according to PWD
      manual Page No. 679 Point B Subpoint (i), experience gained by
      individual partners in the execution of works in the past can be
      taken into consideration while deciding the category of the
      contractors, if the partner concerned has to his credit the
      execution of such works by virtue of monetary share and other
      Interests. Therefore, experience gained by Mr. Siddharth
      Narendrakumar Lunagariya i.e. proprietor of M/s S. N. L. & Co.
      in execution of works of M/s N. P. Patel and Co. can be
      considered for the purpose of technical and financial criterion. In
      other words, considering the monetary share of Mr. Siddharth
      Narendrakumar Lunagariya i.e. proprietor of M/s S. N. L. & Co.
      in M/s N. P. Patel and Co., Mr. Siddharth Narendrakumar
      Lunagariya i.e. proprietor of M/s S. N. L. & Co. can rely upon
      technical and financial criterion of M/s N. P. Patel and Co.
      Furthermore, there are no terms and conditions in the tender



                                Page 30 of 44
 C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




      document, whereby bidder is prohibited from relying upon the
      experience of M/s N. P. Patel and Co. for technical and financial
      criterion. On the contrary, the PWD manual permits M/s S. N. L.
      & Co. to rely upon the experience of M/s N. P. Patel and Co. for
      technical and financial criterion considering the financial share
      of Mr. Siddharth Narendrakumar Lunagariya. It is submitted that
      out of abundant caution the answering Respondent No. 1 has
      also obtained opinion of consultant for the said project, namely
      Savjani Architecture & Engineering Consultants. It is submitted
      that vide opinion dated 09.04.2026, one Savjani Architecture &
      Engineering Consultants has confirmed the above-mentioned
      position and confirmed the eligibility of the Respondent No. 4. (A
      copy of opinion obtained from Savjani Architecture &
      Engineering Consultants is marked and annexed hereto as
      Annexure - "R4"). Hence, the present petition is required to be
      rejected even on the count that as on date Respondent No. 4 is
      holding valid "AA Class" certificate and Respondent No. 4 was
      evaluated in accordance with terms and conditions of the
      tender.”


[47] The Corporation is seeking to contend that SNL &
Company satisfies the criteria of experience as prescribed under
the PWD Manual and not in terms of the tender notification. The
Corporation is essentially shifting its goalposts and is finding
ways and means to accommodate the bid of SNL & Company,
and this is further proof of the mala fides and the arbitrary
manner in which it has undertaken this tender process.


[48] The argument that the Corporation can rely upon the PWD
Manual and, as a consequence, allow SNL & Company to glean
the experience of N. P. Patel and Company is basically perverse.
As noticed above, the work experience of the bidder is essential.
If the bidder was a part of a joint venture, the experience of the
joint venture was acceptable. Similarly, if the bidder was a
nominated subcontractor, that experience was also acceptable.


                                Page 31 of 44
 C/SCA/5436/2026                                 CAV JUDGMENT DATED: 08/05/2026




[49] The tender notification does not, by any stretch of
imagination, contemplate the experience of a partner of the
bidder would be adequate. The tender notification, in fact,
specifically states that the bidder is required to have the
requisite prescribed work experience and there is not mention
either directly or indirectly that experience of any entity related
to the bidder is acceptable. This attempt by the Corporation is a
deliberate attempt not only to mislead but also to skew the
entire qualification criteria.


[50] It is not in dispute that SNL & Company is a proprietary
concern. It is the admitted position of SNL & Company, that the
proprietor Mr. Siddharth Narendrakumar Lunagariya, is a
partner in the partnership firm, N. P. Patel and Company, and in
that partnership firm he owned 90% of the shares.



[51] In other words, the individual proprietor, is a partner in a
firm. A partnership firm, in law, is a distinct entity. The
experience of a firm would be material if the firm had been the
bidder. A partner of such a firm, when bidding for a contract as
an individual proprietor, cannot claim that the experience of the
firm to which he is a partner as his own experience, even if he
owns substantially the entire share of the firm.


[52] The PWD Manual, on which reliance is placed, contains a
clause which reads as follows:-


                                 Page 32 of 44
 C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




      “(B) PROFESSIONAL CAPACITY AND RELIABITY:

      Supported by certificates or recommendations of officers who
      have had personal knowledge of applicant and his work and a list
      of works executed showing their nature, year of construction and
      actual cost of construction. Technical quali fications and
      experience of all the partners and leading tech-nical employces
      in the Firm should also be on record.

      (i) The experience gained by individual partners in the exe-cution
      of works in the past may be taken into consideration while
      deciding the category of the contractors , if the partner
      concerned has to his credit the execution of such works by virtue
      of monetary share and other intcrests. Experience gained merely
      as a servant may not count as a proof of the capabi-lity of the
      Firm as a whole,

      (ii) While considering the application for registration/up
      radation/renewal, the certificates regarding satisfactory com-
      pletion of works as well as works in progress or works for which
      teader have been quoted by the contractor shall be examined by
      the Department. Information of such works has to be given in a
      statement, as per Fortn No. 3. In addition to this, information in
      Form No. 3-A shall be furnished for cach and every work done or
      in progress in last 3 years alonge with the application Form and
      other documents.”


[53] As could be seen from this extract, which is produced by
the Corporation, this would indicate that, it is in respect of
registration of category of Contractors and in that regard it is
stated that in respect of professional capacity and reliability,
certificates or recommendations of officers who had personal
knowledge of the bidder and his work are acceptable. It is also
indicated that the technical qualifications and experience of all
the partners and lead technical employees in the firm should be
on record.



                                Page 33 of 44
 C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




[54] In the context of a firm, sub-clause (i) states that the
experience gained by individual partners in the execution of
works in the past may be taken into consideration while
deciding the category of contractors, if the partner has to his
credit the execution of such works by virtue of his monetary
share and other interest.


[55] In other words, if the applicant was a firm seeking for
registration as a particular class of contractor, which was
dependent on the value of the works already executed, then, the
experience of an individual partner of the firm had secured
could be considered for the purpose of registering the firm as a
particular class of contractor. This would thereby mean that the
clause upon which Corporation has relied upon was essentially
in relation to the registration of partnership firm as particular
class of Contractor.


[56] To illustrate, if the firm was seeking for registration as
AA+ contractor and for this it was required to show that it had
executed say, Rs. 10 crores of work, then, in such a case, the
work executed by the firm and also by the individual partners
would be collectively considered for registration as AA+
contractor.


[57] However, this clause is sought to be twisted to mean that
a bid by a proprietary concern, which, by itself, has no
experience can still participate in the tender by taking

                            Page 34 of 44
 C/SCA/5436/2026                             CAV JUDGMENT DATED: 08/05/2026




advantage of the experience of the firm to which the proprietor
was a partner. This kind of an interpretation of a clause
providing for registration of a contractor as a particular class of
contractor and importing the clause into a tender notification to
determine the eligibility of a bidder is perverse, to say the least.
This would virtually amount to completely disregarding,
probably the most vital aspect of the tender, i.e., the ability of
the tenderer to execute specialized work.


[58] The reason that we are constrained to make these
observations regarding the conduct of the Corporation is
because, it is an admitted fact in the present case that N. P.
Patel and Company, the partnership firm to which Mr.
Siddharth Narendrakumar Lunagariya, the proprietor of SNL &
Company is a partner, has been blacklisted in respect of other
tenders, and this blacklisting has also been upheld by the
Courts. As a result of this blacklisting, N. P. Patel and Company
would have been disqualified from participating in the present
tender. In order to get over this disqualification, on NP Patel &
Co, its major partner i.e., the proprietor of SNL & Company has
submitted its bid as a proprietary concern.


[59] It may also be pertinent to state here that SNL & Company
obtained its classification as a AA class contractor by once again
placing reliance on the work of the blacklisted firm, i.e., N. P.
Patel and Company. To put it in simple terms, since N. P. Patel
and Company was disqualified from participating in the tender,


                             Page 35 of 44
 C/SCA/5436/2026                                 CAV JUDGMENT DATED: 08/05/2026




it has submitted the bid through Mr. Siddharth Narendrakumar
Lunagariya,        who   incidentally    holds   90%      shares       of   the
partnership firm N. P. Patel and Company. In our view, this
clearly establishes that the entire tender process is sought to be
skewed in order to ensure SNL & Company is awarded the
contract.


[60] as already noticed above, that as per clause 2 of the PWD
Manual, reliance upon which reliance is placed, relates to the
registration, upgradation and renewal of a contractor. This
would mean that the PWD Manual is basically in relation to the
registration of a contractor and assigning the contractor to a
particular category. This would therefore not mean to state that
the PWD Manual would accept the work experience of an entity
to which the bidder, i.e., a proprietary concern, was a partner.



[61] Another argument is sought to be advanced by the
Corporation to the effect that it is bound to abide by the terms
of the PWD Manual, and this is also made clear in the Technical
Approval, that has been granted by the Corporation (vide
Annexure R2 to its additional affidavit). Reliance is sought to be
placed on Clause 11, which states that the approval is granted
subject to the condition that the work is to be executed in
compliance of the terms of the PWD Manual. It is to be stated
here that Annexure R2 is admittedly a technical approval
granted by the Corporation for the project. This would obviously
mean that the technical requirements of the project should

                                Page 36 of 44
 C/SCA/5436/2026                             CAV JUDGMENT DATED: 08/05/2026




satisfy the terms of the PWD Manual. This clause cannot be
stretched to contend that a clause relating to registration of a
contractor of a firm, can be utilized to hold that the bidder
satisfies the work experience criteria specified in the tender
notification.


[62] Reliance is also sought to be placed on Section 493 and
Appendix IV the Gujarat Provincial Municipal Corporation Act to
contend that any notification, rule, by-law established, issued
under the provision of the Gujarat Panchayats Act or the Gujarat
Municipalities Act would continue to apply. It is contended that
since the technical approval contains a clause regarding
adherence to the terms PWD Manual, the PWD Manual would
also be ipso facto applicable in all aspects. This is, once again, a
deliberate attempt to misread a provision.



[63] The provision under the Gujarat Provincial Municipal
Corporation Act is a transitory provision which comes into
operation when a either a Panchayath or a Municipality is being
upgraded to a municipal corporation,. This transitory provision
would basically indicate that any act done in exercise of
statutory powers, either under the Gujarat Panchayats Act or
the Municipalities Act, would continue to operate. Admittedly,
the PWD Manual is not a manual enacted in exercise of
statutory powers conferred either under the Gujarat Panchayats
Act or the Gujarat Municipalities Act or the Gujarat Municipal



                             Page 37 of 44
 C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




Corporations Act. The purpose of the transitory provision is to
ensure that there is continuity whenever a panchayat or
municipality becomes a part of the Corporation and there is no
conflict which emerges when this event occurs. In our view, the
argument that the PWD Manual enables the Corporation to rely
upon the work experience of N. P. Patel and Company, a
blacklisted company, for the purpose of satisfying the work
experience of the bidder, i.e., SNL & Company, a proprietary
concern, cannot be accepted.


[64] In the result, we have no other option but to quash the
award of contract in favor of SNL & Company, i.e., the fourth
respondent, and, as a consequence, the Corporation is directed
to consider the other eligible bids, including the bid of R & B,
the petitioner, in accordance with law.


[65] To clarify, if there are any other eligible bidders apart
from R & B still in the fray, the Corporation can consider those
bids and, on comparative analysis on the merits of the bids, take
an appropriate decision. Special Civil Application No.5436 of
2026 filed by M/S R and B Infra Project Limited is allowed.


[66] As far as the petition filed by Yogi Construction Co. is
concerned, the argument of the learned senior counsel Mr. R. S.
Sanjanwala is that the non-production of a certificate required
under the terms of the tender is not a material aspect and could
be disregarded. In our view, this argument is unacceptable.



                            Page 38 of 44
 C/SCA/5436/2026                                CAV JUDGMENT DATED: 08/05/2026




[67] Clause 4.6.3 of the tender condition reads as follows:-

      “Joint venture is not allowed

      4.6.3. The bidder has to attach MOU with Road work agencies as
      a part of technical bid. A contractor should have a Asphalt plant
      owned by him within an aerial radius of 10 km from the limits of
      Porbandar Municipal Corporation and a contractor having a
      Asphalt plant owned by him inside an aerial radius of 10 km from
      the limits of Porbandar Municipal Corporation and an existing
      batch owned by another within an aerial radius of 10 km from
      the limits of Porbandar Municipal Corporation. If the contractor
      wants to use a plant which is a Asphalt, then the contractor has
      to submit an on a stamp paper of Rs.300 and an MOU with the
      owner for the usual time frame. Along with this, proofs showing
      the latest ownership of the plant must also be given and
      mentioned and this MOU with the owner will be valid for the
      duration of the work and the performance guarantee of the work
      will be in force. Which also has to be mentioned. Performa of
      MOU with the owner will be given by Authority.ez If more than
      one contractor signs an MOU with a Asphalt plant, the MOU
      signed with the first contractor will be consider valid and the
      MoU signed with the second contractor thereafter will be
      disqualified.


      The Agency may establish their own asphalt plant incase they are
      not willing to execute MOU with locally available asphalt plant.”


[68] As could be seen from the said clause, Yogi Construction
Co. was required to attach an MoU with road work agencies as
a part of the technical bid, and it ought to have either owned an
asphalt plant within a radial distance of 10 kilometers from the
limits of the Corporation and, in the event Yogi Construction Co.
wanted to use an asphalt plant of some other entity, it had to
submit an MoU on stamp paper with the owner of the plant. In
such an event, proof of ownership of the plant was also required
to be given. The proforma of the MoU was also prescribed as a


                                Page 39 of 44
  C/SCA/5436/2026                                     CAV JUDGMENT DATED: 08/05/2026




part of the tender (at page 124 of the writ petition). It is the
case of the Corporation that all the other bidders had submitted
the MoU in the prescribed format, but Yogi Construction Co.
had not produced the MoU and therefore its bid was rejected.


[69] The case of Yogi Construction Co. is that a corrigendum
had been issued by the Corporation (at page 301 of the papers)
which permitted the bidder to produce only an MoU in respect
of a drum mix plant, along with proof of ownership, and since
this condition was satisfied by Yogi Construction, the bid was
compliant. Moreover, it is their case that as the drum mix plant
was sufficient to adhere to the terms of the tender as a drum
mix plant would meet the requirement of possessing access am
Asphalt plant. This argument cannot be accepted.



[70] It is an admitted fact that the corrigendum issued a
Corrigendum to the tender, which reads as follows:-

“CORRIGENDUM 2 FOR PORBANDAR DRAINAGE TENDER ID NO.-264909

The present provision in tender as per column no.4 of below given table shall be
replaced/ added as per column no.5 of blow given table:

 Tender Page Tender Present Provision                          To be replaced
 Volume No. Clause
             No.
 1         2        3     4                                    5
 ---       ---      ---   ---                                  ---
 ---       ---      ---   The bidder has to attach MOU with Please add following:
                          Road work agencies as a part of MOU within an Arial
                          technical bid. A contractor should radius of 10 km from
                          have a Asphalt plant owned by him the         limit    of
                          within an aerial radius of 10 km from Porbandar Municipal



                                     Page 40 of 44
 C/SCA/5436/2026                                     CAV JUDGMENT DATED: 08/05/2026




                         the limits of Porbandar Municipal Corporation         or
                         Corporation and a contractor having owner ship proof
                         a Asphalt plant owned by him inside (drum mix plant bill)
                         an aerial radius of 10 km from the must be produced.
                         limits   of   Porbandar   Municipal
                         Corporation and an existing batch
                         owned by another within an aerial
                         radius of 10 km from the limits of
                         Porbandar Municipal Corporation. If
                         the contractor wants to use a plant
                         which is a Asphalt, then the
                         contractor has to submit an on a
                         stamp paper of Rs.300 and an MOU
                         with the owner for the usual time
                         frame. Along with this, proofs
                         showing the latest
---       ---      ---   ---                                  ---



[71] As could be seen from this corrigendum, it is not like as if
Clause 4.6.3 was to be substituted and the requirement of an
MOU in respect of an asphalt plant was done away with. The
corrigendum only added one more clause, i.e., the requirement
of having an MoU in respect of a drum mix plant also. Thus, the
Corporation required an MoU in respect of an asphalt plant as
well as a drum mix plant.


[72] It is settled law that the requirements of the tender
inviting authority for executing the work lie within the exclusive
domain of the tender inviting authority. It is not for the bidder
to determine which of the conditions are necessary or which of
the terms are unnecessary. Since admittedly, an MoU in relation
to an asphalt plant has not been produced, the bid of Yogi
Construction Co. was defective and was correctly rejected by
the Corporation.




                                    Page 41 of 44
 C/SCA/5436/2026                                 CAV JUDGMENT DATED: 08/05/2026




[73] It is also to be noticed here that there was a specific
clause regarding site visit, which reads as follows:-


      “7. Site Visit


      7.1. The Bidder, at the Bidder's own responsibility and risk is
      encouraged to visit and examine the Site of work and its
      surrounding and obtain all information that may be necessary for
      preparing the Bid and entering into a contract for construction of
      the Works.


      The costs of visiting the site shall be at the Bidder's own expense.


      7.2 The bidder should visit the site, mentioned in the tender
      document along with Deputy Municipal Commissioner or his
      representative before submitting the tender and get the site visit
      certificate duly signed by City/Municipal Engineer, Porbandar
      Municipal Corporation. It is mandatory for bidder to submit
      the Geo-tagged photo of site visit and also upload the site
      visit certificate duly signed City/Municipal Engineer,
      Porbandar      Municipal    Corporation      in   Annexure-01
      (attached separately), without this bid will be considered
      invalid. The same should be upload with technical bid.”



[74] Though Clause 7.1 indicates that the bidder was being
encouraged to visit the site and obtain information, Clause 7.2
categorically states that it would be mandatory for the bidder to
submit the geo-tagged photo of the site visit and also upload the
site visit certificate, which was to be duly signed by the
concerned engineer of the Porbandar Municipal Corporation. It
was also clearly stated that if this requirement was not satisfied,
the bid would be considered invalid.




                                 Page 42 of 44
  C/SCA/5436/2026                            CAV JUDGMENT DATED: 08/05/2026




[75] It is the argument of the Learned Senior counsel Shri
Sanjanwala that the engineers of the Corporation were not
present when a site visit was actually undertaken by Yogi
Construction Co. It is averred in the affidavit-in-rejoinder that
representatives of Yogi Construction Co. had visited the office of
the Corporation on 23.02.2026 and had intimated the officials
that they had visited the spot on 18.02.2026, which was
accepted by them and also ratified. It is stated that the absence
of a geo-tagged photo was only due to the fact that the officials
of the Corporation were not present at the site. It is also sought
to be argued that the non-production of a site visit certificate,
did not have any bearing on the tender, and thus would be of no
consequence and reliance of the Corporation on this aspect of
the matter to reject the tender was not justified. This affidavit-in-
rejoinder clearly indicates that the requirement of a geo-tagged
photo was not complied with along with the tender document.
What was sought to be produced was only a site visit certificate,
which was signed by two officials, but admittedly was not done by
the officials at the site.

[76] In light of the fact that the terms of the tender relating to
site visit mandated the production of a geo-tagged photo, and
also made it clear that the absence of producing a geo-tagged
photo would render the bid invalid, this argument of the learned
senior counsel cannot be accepted, and it has to be held that the
rejection of the bidder, Yogi Construction Co., was justified.
Consequently, there is no merit in the writ petition filed by Yogi
Construction Co., and the same is dismissed.

                             Page 43 of 44
  C/SCA/5436/2026                                               CAV JUDGMENT DATED: 08/05/2026




[77] Special Civil Application No.5436 of 2026 filed by M/S R
and B Infra Project Limited is allowed and Special Civil
Application No.4647 of 2026 filed by Yogi Construction Co. is
dismissed.



                                                               (N.S.SANJAY GOWDA, J.)




                                                                         (J. L. ODEDRA, J.)
DHARMENDRA KUMAR


Original copy of this order has been signed by the Hon'ble Judges.
Digitally signed by: KUMAR DHARMENDRA(HC01071), GOV, at High Court of Gujarat on 08/05/2026 18:05:19




                                           Page 44 of 44


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Tender law"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.