Bombay High Court
SURESH DATTU MORE THR CA ZAHEER USMAN WADIAversusTHE. MUNICIPAL CORPORATION OF GREATER MUMBAI AND ANOTHER
- Decided
- Disposal
- Disposed Off
Holding
The appeal is allowed; the trial court’s order dismissing the injunction application is set aside and the BMC is restrained from acting on the Section 354A notice pending final disposal of the suit.
Summary
The appellant, owner of a building in Mumbai, was served with notices under the Mumbai Municipal Corporation Act, 1888 demanding cessation of alleged unauthorized structural repairs and threatening demolition. The appellant submitted a structural audit classifying the work as minor, tenantable repairs (C‑3) and argued that the repairs were completed before the notice dated 31 July 2025, making the notice under Section 354A invalid. The trial court dismissed the appellant's motion for a temporary injunction without addressing the appellant's documents or the vagueness of the notice. On appeal, the High Court held that the trial court failed to form a prima facie view, ignored the fact that no work was in progress at the time of the notice, and misapplied the provisions of Section 354A, citing Goverdhan Ramnaresh Singh v. Municipal Corporation of Greater Mumbai. Consequently, the appeal was allowed, the trial court’s order was set aside, and the BMC was restrained from acting on the July 2025 notice pending final disposal of the suit.
Issues considered
- Whether a notice issued under Section 354A of the Mumbai Municipal Corporation Act is valid when the alleged structural repairs were completed before the notice and no work was in progress.
- Whether minor or tenantable repairs classified as C‑3 under a structural audit require prior permission under Section 342 of the Act.
- Whether the trial court should have granted an interim injunction considering the balance of convenience and irreparable loss.
- Whether the trial court erred by not forming a prima facie view on the documents and the vagueness of the notice.
Legislation cited
- Code of Civil Procedure, 1908 — s. Order XLIII Rule 1, Section 104
- Mumbai Municipal Corporation Act, 1888 — s. 342, 351, 352, 352A, 353B, 354A
Subjects
- municipal corporation
- unauthorized construction
- Section 354A
- interim injunction
- structural audit
- C‑3 category
- balance of convenience
- prima facie view
- demolition
Judgment
15 - AO-720-2026.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
APPEAL FROM ORDER NO. 720 OF 2026
Suresh Dattu More Thr CA
Zaheer Usman Wadia Appellant
Versus
The. Municipal Corporation Of
Greater Mumbai and Another Respondents
WITH
INTERIM APPLICATION NO. 5554 OF 2026
Suresh Dattu More Applicant
Versus
The. Municipal Corporation Of
Greater Mumbai and Another Respondents
_______
Mr. A. Y. Sakhare, Senior Advocate a/w Mr. Shobhit Shukla, Advocate for the
Appellant.
Ms. Smita Tondwalkar, Advocate for the Respondent/BMC.
_______
CORAM: AARTI SATHE, J.
DATE: 17th AUGUST 2026.
P.C.
1. Heard learned counsel for Appellant (Original Plaintiff) and learned
Counsel for Respondents (Original Defendant). This Appeal from Order under Order
XLIII Rule 1 read with Section 104 of the Code of Civil Procedure, 1908 (“CPC”) takes
exception to the order dated 15 th July 2026 passed by the Learned Judge, City Civil
Court, Bombay (“Trial Court”) in Notice of Motion No. 3046 of 2026 in L.C. Suit No.
Page 1 of 10
Bharati
15 - AO-720-2026.DOC
1247 of 2026, whereby the Trial Court has dismissed the Notice of Motion No. 3046
of 2026 filed by the Appellant (Original Plaintiff).
2. Mr. A. Y. Sakhare, Senior Advocate along with Mr. Shobhit Shukla appears
on behalf of the Appellant (Original Plaintiff) and Ms. Smita Tondwalkar appears on
behalf of the Respondents (Original Defendant).
3. Briefly the facts are as follows:
i. The Appellant (Original Plaintiff) is the owner in respect of building no.
38-40, V. V. Chandan Street, CTS No. 739 of Mandvi Division, Mumbai - 400003
(hereinafter referred to as “the structure”). It is the Appellant’s (Original Plaintiff’s)
contention that the said V. V. Chandan street was earlier known as D'Souza street and
the said street was renamed as Vitthaldas Chandan street commonly known as V. V.
Chandan street and the said renaming was done sometime around the year 1960. On
24th May 2024, the Respondents (Original Defendant) issued notice under Section
353B of the Mumbai Municipal Corporation Act, 1888 (hereinafter referred to as “the
Act”) and directed the owner to submit the structural audit report.
ii. The Appellant (Original Plaintiff) being the owner of the aforesaid
structure through the License Surveyor carried out the structural audit of the building
and in the said audit report it was concluded that minor repairs were required for the
structure and the said structure was categorized as C-3 i.e. “No Eviction - needs minor
repairs”. On 24th March 2025 the Administrative Officer of the Building and Proposal
Department, in response to the Appellant’s (Original Plaintiff’s) representative who had
filed an RTI application on 11 th February 2024 to seek certain documents, informed the
Appellant (Original Plaintiff) that the documents containing to file No. EB/1419/B of
Page 2 of 10
Bharati
15 - AO-720-2026.DOC
1968 were available in the aforesaid office and could be obtained upon payment of the
requisite charges.
iii. On 31st July 2025, Respondents (Original Defendant) issued notice under
Section 354A of the Act stating that “unauthorized structural repair to back side
portion of building without permission from the competent authority of the BMC” had
been undertaken by the Appellant (Original Plaintiff), and sought to demolish the
aforesaid alleged unauthorized structural repair. Thereafter on 4 th August 2025, the
Respondents (Original Defendant) once again issued a notice exercising powers under
Sections 351, 352, 352A and 354A of the Act directing that the Appellant (Original
Plaintiff) stop the erection of the said building / execution of the said work and
forthwith submit the permission granted by a competent authority in favour of the
Appellant (Original Plaintiff) for the erection of the said building and for execution of
the work within 24 hours to the office of the Respondents (Original Defendant). By
way of aforesaid notice, it was also informed to the Appellant (Original Plaintiff) that if
the erection of the building or the execution of the work of the building is not stopped
forthwith or permission/approval of the competent authority in favour of the erection
of the said building or execution of the work is not produced within 24 hours from the
service of the said notice, the said building/work would be removed or pulled down and
all the material, machinery, equipment, devices or articles used for the process of
erection of the said building or execution of the said work would be removed from the
sight at the risk and cost of the Appellant (Original Plaintiff).
iv. Thereafter on 14th August 2025, the Respondents (Original Defendant)
issued a notice directing the Appellant (Original Plaintiff) to remove the existing work
Page 3 of 10
Bharati
15 - AO-720-2026.DOC
within 15 days of receipt of the said notice failing which the alleged unauthorized work
would be demolished by the Respondents (Original Defendant) at the risk, cost and
consequence of the Appellant (Original Plaintiff).
v. On 2nd December 2025, the Appellant (Original Plaintiff) through their
Advocate submitted a detailed reply along with the documents available with the
Appellant (Original Plaintiff) denying the allegations in the said notice and stated that
the work of repair to the building was completed even before the notice dated 31 st July
2025. The Appellant (Original Plaintiff) submitted documents received under RTI and
entire file of CS No. 793 for addition/alteration filed by the earlier owner for
Intimation of Disapproval (“IOD”) dated 16th May 1969 and commencement
certificate dated 16th May 1969 and plans attached with the file in addition/alteration.
vi. Thereafter on 16th April 2026, the Respondents (Original Defendant)
passed a speaking order and held that the documents submitted by the Appellant
(Original Plaintiff) did not go to prove that any permission from any competent
authority for ongoing work had been submitted by the Appellant (Original Plaintiff)
and therefore directed the Appellant (Original Plaintiff) to discontinue the use of notice
structure and remove or restore the unauthorized work mentioned in the referred
notice immediately from the receipt of the said notice failing which the same would be
demolished by the Respondents (Original Defendant) entirely at risk and cost of the
Appellant (Original Plaintiff).
vii. Thereafter the Appellant (Original Plaintiff) moved the learned City Civil
Court by filing L.C. Suit No. 1247 of 2026 and also filed Notice of Motion No. 3046
of 26 seeking a temporary injunction restraining the Respondents (Original
Page 4 of 10
Bharati
15 - AO-720-2026.DOC
Defendant), their officers, servants, agents and all persons claiming through them from
taking any coercive action in respect of the said structure.
viii. On 15th June 2026, the Respondents (Original Defendant) filed a detailed
reply and relied upon documents i.e. Preliminary Inspection Report dated 22 nd July
2025, photographs and sanctioned issued notices. On 15 th July 2026, by way of the
impugned order, the learned Trial Judge was pleased to dismiss the Notice of Motion
filed by the Appellant (Original Plaintiff) against which the present Appeal from Order
has been preferred.
viii. The case of the Appellant (Original Plaintiff) before the Trial Court was
primarily to the effect that the action on the part of Respondents (Original Defendant)
was incorrect and the structural audit of the building was conducted on 13 th January
2025 which clearly showed that the building was categorized in C-3 category i.e. “No
Eviction, need minor repairs”. The Appellant (Original Plaintiff) therefore contended
that the said minor repairs and tenantable repairs as mentioned in the structural audit
report requires no separate permission from the Building and Proposal Department and
hence, the repair works were carried out by the Appellant (Original Plaintiff). It was
also submitted that on 2nd September 1968 the earlier trust who was owner of the said
building appointed architect and submitted proposal under Section 342 of the Act for
repairs of the building and submitted plans which clearly showed the existence of the
building comprising the Ground Floor, Mezzanine Floor, and First to Eighth floor. It
was further contended that on 16 th May 1969, the Executive Engineer, Building and
Proposal Department issued IOD and also issued a commencement certificate for the
said building. It was further contended on behalf of the Appellant (Original Plaintiff)
Page 5 of 10
Bharati
15 - AO-720-2026.DOC
that notice under Section 354A of the Act could be issued only when work is in
progress, and considering that the building was in existence and tenantable repairs had
been carried out much prior to the issuance of notice, the said notice dated 31 st July
2025 itself could not be issued. The Appellant (Original Plaintiff) submitted that the
said notice also was a vague notice which did not clarify what is structural repair and
what are the exact measurements which the Respondents (Original Defendant) seeks to
classify as unauthorized structures and repairs to that unauthorized structure, which
vitiates the entire notice itself. Further, learned counsel on behalf of the Appellant
(Original Plaintiff) submitted that the impugned order dated 15 th July 2026 had
nowhere dealt with the aforesaid contention of the Appellant (Original Plaintiff) that
the notice dated 31st July 2025 was a vague notice not specifying any details. Learned
counsel for the Appellant (Original Plaintiff) also submitted that the speaking order
dated 16th April 2026 had discarded the documents submitted by the Appellant
(Original Plaintiff) and therefore, could not be relied upon. He therefore submitted that
no prima facie view was formed by the Trial Court on appreciation of facts and record
before dismissing the Notice of Motion. He further sought to place reliance on the
decision of this Court in the case of Goverdhan Ramnaresh Singh Vs. The Municipal
Corporation of Greater Mumbai1, to submit that if by the time the notice under Section
354A of the Act has been issued, the work/repairs have been completed, then the said
notice could not be issued.
ix. Ms. Smita Tondwalkar, learned Advocate for the Respondents (Original
Defendant) opposes the present Appeal primarily on the ground that no permission
1 Order dated 15th April 1999 in Appeal from Order no. 257 of 1999
Page 6 of 10
Bharati
15 - AO-720-2026.DOC
had been granted to the Appellant (Original Plaintiff) prior to carrying out the repairs
to the said building/structure. She therefore submitted that the notice dated 31 st July
2025 under Section 354A of the Act was correctly issued and further sought to place
reliance on the Inspection Report dated 22 nd June 2025 and the photographs which
according to her proved, that unauthorized structural repair to the back side portion of
the building/structure without permission from competent authority of the Respondent
Corporation was sought to be made by the Appellant (Original Plaintiff).
4. I have considered rival submissions and perused the record. On perusal of
the documents and the impugned order, it is quite clear that the impugned order does
not record any finding with respect to the documents submitted by the Appellant
(Original Plaintiff) i.e. the permissions taken by the earlier owner i.e. the Trust in
respect of repairs to be carried out to the said Structure. The Trial Court has also not
rendered any finding in respect of the structural audit report dated 13 January 2025,
which categorically came to the conclusion that the said building is a C-3 structure i.e.
“No Eviction - needs minor repairs” which showed that the building required minor
repairs. The Trial Court further failed to consider the Appellant’s (Original Plaintiff’s)
contention that the notice dated 31st July 2025 issued under Section 354A of the Act
did not give the exact details, measurements and/or specifications of the unauthorized
structural repair and only a vague and omnibus statement regarding the unauthorized
structure has been made in the notice.
5. The Trial Court has also failed to consider that when the notice was issued
under Section 354A of the Act, there was no work in progress i.e. repairs which were
being carried out by the Appellant (Original Plaintiff). I am further of the view that the
Page 7 of 10
Bharati
15 - AO-720-2026.DOC
reliance placed by learned counsel on behalf of the Appellant (Original Plaintiff) on the
decision of Goverdhan Ramnaresh Singh (Supra) is apposite to the facts of the present
case inasmuch as even in the present case, the repairs to the building have concluded
prior to the issuance of the notice under Section 354A of the Act. The relevant
paragraph of the aforesaid decision is reproduced below: -
“5. A perusal of sub section (1) shows that if the unauthorized construction had
been commenced or is being unlawfully carried upon any premises, the
Commissioner or for that purpose the person authorized by him may require the
person carrying out such unauthorized construction or executing the unauthorized
work stop; such construction or work within time specified in the notice. Sub
section (2) of section 354A provides the remedy to the Commissioner to remove
such unauthorized construction if the erection of the building or execution of the
work is not stopped by the person within the period specified in the notice given
under sub section (1). The condition precedent for invocation of power under sub
section (2) of section 354A is non-compliance of the notice by the noticee given
under sub section (1) of section 354A. In the present case on the face of the notice
itself it is clear that by the time notice under section 354A was issued and even to
the notice construction was complete and was in occupation. If a 354A(1) was
issued, the remedy to the Corporation is under section 351 of the BMC Act and not
under section 354A. The trial court has also observed "here one fact is clear so far as
such stop work notice is even though styled, no record is coming before the court
that really the work was in progress and the stages of progress of the construction is
recorded by the office of the defendants. If the Corporation had no material in its
possession at the time of issuance of the notice under section 354A that the activity
of construction was going on, obviously notice under section 354A could not have
been issued. In this background the order of the trial court cannot be sustained since
admittedly no notice under section 351 was given by the Corporation to the original
plaintiff and since section 354A of the BMC Act was not attracted the removal of
the so called unauthorized construction in implementation of, the notice under
section 354A prima facie cannot be said to be justified.”
(emphasis supplied)
6. Therefore, the Trial Court without forming a prima facie view on the
documents has merely sought to dismiss the Notice of Motion and has not recorded any
finding in respect of the same. The Trial Court while exercising jurisdiction under
Order XXXIX Rule 1 and 2 of the CPC, was required to come to prima facie view and
as per the settled principles of law regarding balance of convenience and irreparable loss
also needed to be taken into consideration before exercising the aforesaid jurisdiction.
Page 8 of 10
Bharati
15 - AO-720-2026.DOC
In my considered view, the Trial Court has failed to apply the aforesaid principles
before passing the impugned order. I am further of the view that the Trial Court has
also not verified whether the alleged unauthorized repair to the structure/building was
actually being carried out on the date of issuance of notice dated 31 st July 2025 under
Section 354A of the Act. I am therefore of the considered view that the Trial Court has
not passed the impugned order which is supported by material on record and the
discretion exercised by the Trial Court is arbitrary, perverse and contrary to settled
principles. In these circumstances, interference in the Trial Court’s impugned order is
warranted.
7. In the present case, the Trial Court by not rendering a finding or forming a
prima facie view on the submissions made by the Appellant (Original Plaintiff) has
erred in exercising its discretion in dismissing the Notice of Motion filed by the
Appellant (Original Plaintiff). Further, the Trial Court has also not given a finding as to
how the tenantable repairs require permission under Section 342 of the Act and has
proceeded on the basis of the vague notice dated 31st July 2025 issued under Section
354A of the Act which does not specify any details of the unauthorized repairs carried
out to the said building. In my view, therefore the refusal of injunction would cause
irreparable injury and harm to the Appellant (Original Plaintiff) and if the injunction is
granted, the Respondents (Original Defendant) would suffer no comparable prejudice.
The balance of the convenience lies in favour of the Appellant (Original Plaintiff). In
my view therefore, the impugned order cannot be sustained and accordingly the Appeal
is allowed.
Page 9 of 10
Bharati
15 - AO-720-2026.DOC
ORDER
i. The Appeal from Order is allowed in the following terms:
ii. The impugned order dated 15 July 2026 passed by the Trial Court in the
Notice of Motion No. 3046 of 2026 in LC Suit No. 1247 of 2026 is hereby set aside.
iii. The Respondents (Original Defendant), its servant, agents and persons are
hereby restrained from acting upon the notice dated 31st July 2025 under Section 354A
of the Act pending herein and final disposal of the suit. It will be open to the
Respondent (Original Defendant) to issue fresh notice to the concerned
person/Appellant (Original Plaintiff) in respect of any other unauthorized structure
other than that covered in the notice dated 31 st July 2025 in accordance with law for
the removal of unauthorized construction if any. The learned Trial Court shall dispose
of the pending suit as expeditiously as possible.
iv. Appeal is disposed of in the aforesaid terms. In view of the disposal of the
above Appeal, pending Interim Application, if any, also stands disposed of.
(AARTI SATHE, J.)
Page 10 of 10
Bharati
Checking your session…