Bombay High Court
Nikhil Sakharam ChavhanversusDIVISIONAL CONTROLLAR MSRTC, AURANGABAD
- Disposal
- Admitted/Allowed/Granted/Rule Absolute
Holding
The Court held that the applicant may withdraw 75 % of the deposited compensation amount, subject to an undertaking and with the balance kept in fixed deposit until further orders.
Summary
The applicant, Nikhil Sakharam Chavhan, filed an application before the Bombay High Court seeking to withdraw the compensation amount that had been awarded by a Tribunal and deposited by an insurance company. The Tribunal had endorsed the applicant’s entitlement after hearing the rival contentions of the parties. The Court examined the competing interests of the applicant and the respondent and considered the need to balance those interests. It held that allowing a partial withdrawal was appropriate in the circumstances. Consequently, the Court ordered that the applicant may withdraw 75 % of the deposited amount together with accrued interest, subject to an undertaking that disbursement remains contingent on the final outcome of the first appeal. The remaining balance is to be kept in a fixed deposit for an initial period of three years, renewable until further orders of the Court.
Issues considered
- Whether the applicant is entitled to withdraw a portion of the compensation amount deposited by the insurance company pending the final determination of the first appeal
Subjects
- compensation award
- tribunal decree
- withdrawal of funds
- fixed deposit
- pending appeal
- civil procedure
Judgment
2026:BHC-AUG:42392
C.A. No.10225/2026
:: 1 ::
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD
CIVIL APPLICATION NO.10225 OF 2026 IN
FIRST APPEAL NO. 2354 OF 2026
Nikhil Sakharam Chavhan … APPLICANT
VERSUS
Divisional Controller, MSRTC, Aurangabad … RESPONDENT
.......
Ms M.V. Manal, Advocate for applicant
Mr. S.N. Janakwade, Advocate for respondent No.1.
....…
CORAM : SACHIN S. DESHMUKH, J.
DATE : 15th SEPTEMBER, 2026
PER COURT :
1. The applicant has presented this application seeking
withdrawal of the amount of compensation awarded by the Tribunal,
which is deposited by the Insurance Company.
2. Considering the facts and circumstances that the entitlement
of the applicant is endorsed by the Tribunal after considering the rival
contentions of the litigating sides and to strike the balance in the
competing interest, it will be appropriate to permit the applicant to
C.A. No.10225/2026
:: 2 ::
withdraw the amount.
3. Thus, the application is partly allowed.
4,. The applicant is permitted to withdraw 75% of the deposited
amount along with interest accrued thereon.
5. The applicant shall furnish an undertaking to the satisfaction
of the Registrar (Judicial) of this Court that disbursement would remain
subject to final outcome of the First Appeal.
6. The balance amount shall be kept in Fixed Deposit of any
Nationalised Bank initially for the period of three (03) years, the same
shall be renewed periodically until further orders of this Court.
(SACHIN S. DESHMUKH, J.)