Created by Fuzzy Cloud

Bombay High Court

NANASAHEB PANDHARI GITTEversusTHE STATE OF MAH AND ORS

Disposal
PARTLY ALLOWED AND PARTLY DISMISSED

Holding

The appeals are partly allowed, fixing compensation for dry land at Rs. 2181 per R with statutory benefits and interest as per the Land Acquisition Act and the coordinate‑bench precedent.

Summary

The acquisition proceedings for the Yeldariwadi Storage Tank project, initiated in 2004, resulted in a 2011 award by the District Judge. The original claimants appealed the award, arguing that a later coordinate‑bench order (FA No. 1132/2012, dated 23‑April‑2026) had already determined the market values of irrigated and non‑irrigated land for the same project. The Court accepted that the controversy was identical to the earlier decision and therefore applied its findings. It partially allowed the appeals, fixing compensation for dry (jirayat) land at Rs. 2181 per R, and granted all statutory benefits and interest under Sections 28 and 34 of the Land Acquisition Act as clarified in State of Maharashtra v. Kailas Shiva Rangari (2016). The original award was modified accordingly, and pending civil applications were disposed of.

Issues considered

  • What compensation rate should apply to dry (non‑irrigated) land in the Yeldariwadi Storage Tank acquisition?
  • Whether the appeals should be decided independently or be bound by the coordinate‑bench order in FA No. 1132/2012?
  • Entitlement of claimants to statutory benefits and interest under the Land Acquisition Act.

Legislation cited

Subjects

  • land acquisition
  • compensation
  • dry land
  • statutory benefits
  • interest
  • coordinate bench precedent
  • Yeldariwadi Storage Tank

Judgment

2026:BHC-AUG:39501

                                                                    FA 882/12 & Ors.
                                              1

                        IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   BENCH AT AURANGABAD

                              16 FIRST APPEAL NO. 882 OF 2012

                           KAMALBAI ANNASAHEB GUTTE AND ORS
                                           VERSUS
                                 THE STATE OF MAH AND ORS
                                              ...
                           Advocate for Appellant : Mr. Kale Ajeet B.
                       AGP for Respondent/State : Mr. S.N. Morampalle
                       Advocate for Respondent 3 : Mr. Mukul S. Kulkarni
                                              …

                                            WITH
                     CIVIL APPLICATION NO. 15596 OF 2015 IN FA/888/2012
                                            WITH
                     CIVIL APPLICATION NO. 1177 OF 2016 IN FA/882/2012
                                            WITH
                     CIVIL APPLICATION NO. 1180 OF 2016 IN FA/884/2012
                                            WITH
                     CIVIL APPLICATION NO. 1168 OF 2016 IN FA/881/2012
                                            WITH
                     CIVIL APPLICATION NO. 1172 OF 2016 IN FA/883/2012
                                            WITH
                     CIVIL APPLICATION NO. 1173 OF 2016 IN FA/883/2012
                                            WITH
                     CIVIL APPLICATION NO. 1170 OF 2016 IN FA/881/2012
                                            WITH
                                FIRST APPEAL NO. 881 OF 2012
                                            WITH
                                FIRST APPEAL NO. 887 OF 2012
                                            WITH
                                FIRST APPEAL NO. 888 OF 2012
                                            WITH
                     CIVIL APPLICATION NO. 15595 OF 2015 IN FA/888/2012
                                            WITH
                     CIVIL APPLICATION NO. 1175 OF 2016 IN FA/882/2012
                                            WITH
                                FIRST APPEAL NO. 883 OF 2012
                                            WITH
                     CIVIL APPLICATION NO. 6000 OF 2015 IN FA/887/2012
                                            WITH
                     CIVIL APPLICATION NO. 5999 OF 2015 IN FA/887/2012
                                            WITH
                     CIVIL APPLICATION NO. 1181 OF 2016 IN FA/884/2012
                                                              FA 882/12 & Ors.
                                       2

                                  WITH
                       FIRST APPEAL NO. 884 OF 2012
                                    …

                     CORAM          : SIDDHESHWAR S. THOMBRE, J.
                     Dated          : August 24, 2026

PER COURT :-

1.    As the acquisition proceedings were initiated in the year 2004, heard

finally with the consent of learned counsel for respective parties.

2.    By   these   appeals,   the   appellants/original   claimants   assail   the

judgment and award dated 18.10.2011 passed by the learned District

Judge-1, Ahmedpur in LAR Nos. 318, 320, 317, 319, 316 and 315 of 2011,

respectively.

3.    Both the counsel tendered across bar the copy of order dated

23.4.2026 passed by the coordinate bench of this Court in FA No.

1132/2012 (Bhagwanrao Dharbaji Gutte and others Vs. The State of

Maharashtra and Ors.) and other connected matter. They submit that the

present appeals as well as FA No. 1131/2012 (supra) arise from the same

project i.e. Yeldariwadi Storage Tank, Taluka Ahmedpur, District Latur. In FA

No. 1131/2012 (supra) the coordinate bench of this Court has determined

the market value of irrigated land at the rate of Rs.4362/- per R. and non

irrigated land at the rate of Rs.2181/- per R. They submit that the said

order covers the present matters and and consequently, the present appeals

deserve to be disposed of in terms thereof.

4.    Having considered the submissions advanced by the learned counsel

for the respective parties, and in view of the admitted position that the

controversy involved in the present appeals is identical to the one decided

by the Coordinate Bench in FA No. 1132/12 (supra), I see no reason to take
                                                                FA 882/12 & Ors.
                                         3

a different view. The present appeal, therefore, deserves to be disposed of

in terms of the said judgment and order. Hence, the following order :-

                                    ORDER

(i)     First appeals filed by the original claimants are partly allowed.

(ii)    The claimants are entitled to receive compensation at the rate of

Rs.2181/- per R. for Jirayat/dry.

(iii)   The claimants are further entitled to all consequential statutory

benefits on enhanced compensation in accordance with the provisions of the

Land Acquisition Act.

(iv)    The claimants are further entitled to interest under section 28 and 34

of the Act, strictly in accordance with the law laid down by the the Full

Bench of this Court in the case of State of Maharashtra Vs. Kailas Shiva

Rangari, 2016 (4) Mh.L.J. 457.

(v)     The impugned judgment and award of the reference court is modified

accordingly.

(vi)    Claimants to pay the deficit court fees, if any, on enhanced amount.

(vii)   Pending civil applications, if any, also stand disposed of.



                                             ( SIDDHESHWAR S. THOMBRE, J. )

ssc/
