Holding

The court held that the 58‑day delay in filing the appeal was condonable and that a stay of execution may be granted provided the appellant deposits 75 % of the award with interest within twelve weeks.

Summary

The City and Industrial Corporation (CIDCO) filed a civil application seeking condonation of a 58‑day delay in filing its first appeal, arguing the delay was due to necessary administrative procedures. The court, after hearing opposition from the claimants and the Attorney General, condoned the delay and allowed the application. In a separate application, CIDCO sought a stay of execution of a judgment and award dated 31 January 2026, offering to deposit 75% of the awarded amount with interest and contending that the reference court had overlooked agricultural‑land considerations and development charges. The court, considering the submissions and opposition, granted a stay of execution on the condition that CIDCO deposits the stipulated 75% within twelve weeks. Thus, both the condonation and the stay were granted subject to the deposit condition.

Issues considered

  • Whether a delay of 58 days in filing a first appeal can be condoned under procedural law.
  • Whether a stay of execution of a judgment and award may be granted pending partial deposit of the awarded amount.
  • Whether the reference court erred in not accounting for agricultural land status and development charges.

Subjects

  • condonation of delay
  • stay of execution
  • civil appeal
  • partial deposit
  • development charges
  • agricultural land
  • High Court
  • Civil Application

Judgment

2026:BHC-AUG:42568
                                                  1                         958-CA-6484-2026.odt




                           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                      BENCH AT AURANGABAD

                               958 CIVIL APPLICATION NO. 6484 OF 2026
                                          IN FAST/16552/2026

                  The City And Industrial Corporation Through Its Administrator, Cidco,
                                              Aurangabad
                                                VERSUS
                           Abdul Razzak Mohammad Yasin Quadri And Others

                                                 WITH
                                  CIVIL APPLICATION NO. 6485 OF 2026
                                          IN FAST/16552/2026

               The City And Industrial Corporation Through Its Administrator, Cidco,
                                           Aurangabad
                                             VERSUS
                        Abdul Razzak Mohammad Yasin Quadri And Others
                                                 ...
             Mr.Shambhuraje V. Deshmukh for the Applicant.
             Dr.Kalpalata Patil Bharaswadkar, Addl. G.P. for the Respondent/State.
             Mr.Anand Bhandari for Respondent Nos.1 and 3.
                                                ….
                                   CORAM        : MANJUSHA DESHPANDE, J.
                                      DATE            : 10.09.2026
             PER COURT :

             CIVIL APPLICATION NO. 6484 OF 2026

             1.              This Civil Application for condonation of delay in filing the

             First Appeal is filed by the Acquiring Body. There is a delay of 58 days in

             filing the Appeal.

             2.              It is submitted that the delay in filing the Appeal has

             occurred on account of the administrative process required to be

             undertaken by the Acquiring Body prior to filing the Appeal. Therefore,

             the same deserves to be condoned.

             Sunny Thote
                                   2                        958-CA-6484-2026.odt


3.            The prayer made in the Application is opposed by the

learned Advocate for the Claimant as well as the learned AGP.

4.            In view of the explanation given by the Applicant, the delay

caused in filing the Appeal is condoned. The Civil Application is allowed

in terms of prayer clause [B].



CIVIL APPLICATION NO. 6485 OF 2026


5.            The learned Advocate for the Applicant seeks leave to amend

the Civil Application for stay by incorporating the prayer clauses which

could not be added inadvertently. Leave is granted. Necessary

amendment shall be carried out forthwith.

6.            The Appellant has filed the present Application seeking stay

to the execution and implementation of the Judgment and Award passed

by the learned Civil Judge, Senior Division, Aurangabad, in L.A.R. No.

160 of 2019 dated 31st January, 2026.

7.            The learned Advocate for the Applicant submits that the

Applicant is ready to deposit 75% of the amount awarded under the

Award. He, therefore, submits that this Court may stay the execution and

implementation of the said Award.

8.            The learned Advocate for the Applicant further submits that

the Reference Court has failed to take into consideration the fact that the

sale instance relied upon by the Reference Court pertains to agricultural


Sunny Thote
                                  3                        958-CA-6484-2026.odt


land and that the necessary deduction towards development charges has

not been considered in the present matter. He, therefore, submits that the

execution and implementation of the Award deserves to be stayed.

9.            In view of the aforementioned grounds, the learned Advocate

for the Applicant submits that the Applicant is ready to deposit 75% of

the amount, along with accrued interest, as awarded by the Reference

Court.

10.           The aforesaid submissions are opposed by the learned

Advocate appearing for the claimants as well as the learned AGP.

Considering the grounds raised in the Appeal, it is submitted that the

Appellant may be directed to deposit 75% of the amount awarded by the

Reference Court.

11.           The execution and implementation of the Judgment and

Award passed by the Reference Court is stayed, subject to the condition

that the Appellant deposits 75% of the amount awarded under the

Award, along with accrued interest, within a period of twelve weeks.




                                         [ MANJUSHA DESHPANDE, J. ]




Sunny Thote


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.