The Executive Engineer Majalgaon Canal Division no 7 Gangakhed ParbhaniversusThe State of maharashtra through The Collector Beed and ors

Disposal
Admitted/Allowed/Granted/Rule Absolute

Holding

The delay of 369 days is condoned as the applicant’s explanation is satisfactory.

Summary

The Executive Engineer (Majalgaon Canal Division No 7, Gangakhed, Parbhani) filed Civil Application No. 7870 of 2025 seeking condonation of a 369‑day delay in the acquisition process against the State of Maharashtra. The State, represented by the Collector Beed, opposed the condonation. The court examined the explanation provided by the applicant’s counsel for the delay. Finding the explanation satisfactory, the court held that the delay could be legally condoned. Consequently, the application was allowed and the matter was disposed of.

Issues considered

  • Whether the 369‑day delay in the acquisition process can be condoned under the applicable procedural rules.

Subjects

  • condonation of delay
  • civil procedure
  • acquisition
  • application allowed
  • procedural compliance

Judgment

2026:BHC-AUG:38383
                                                   1                        944-CA-7870-2025.odt




                           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                      BENCH AT AURANGABAD

                               944 CIVIL APPLICATION NO. 7870 OF 2025
                                          IN FAST/11089/2025

                The Executive Engineer Majalgaon Canal Division No 7 Gangakhed
                                             Parbhani
                                             VERSUS
                  The State Of Maharashtra Through The Collector Beed And Ors
                                                ...
             Adv. G.S. Khande h/f Mr.N.L. Jadhav for the Applicant.
             Ms. Meenakshi Sangit, AGP for the State.
                                                ...
                                              WITH
                             CIVIL APPLICATION NO. 8243 OF 2026
                                      IN FAST/11089/2025
                                              WITH
                             CIVIL APPLICATION NO. 7871 OF 2025
                                      IN FAST/11089/2025
                                                ….

                                      CORAM            : MANJUSHA DESHPANDE, J.
                                      DATE             : 21.08.2026

             PER COURT :


             1.              The Civil Application No.7870 of 2025 is filed by the

             Acquiring Body for condoning the delay of 369 days. The explanation

             given by the learned Advocate for the Acquiring Body for the delay is

             found to be satisfactory.

             2.              In view of the satisfactory explanation given by the Acquiring

             Body, the delay of 369 days is condoned.




             Sunny Thote
                                  2                      944-CA-7870-2025.odt


3.            As such, the Civil Application No.7870 of 2025 is allowed

and the same accordingly disposed off.




                                         [ MANJUSHA DESHPANDE, J. ]




Sunny Thote


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.