Bombay High Court
The Superintendent Engineer, Tapi Irrigation Development Corporation Jalgaon And AnrversusVitthal Pandurang Mali Died Thr. Lrs. Kusum Vitthal Mali and ors
- Disposal
- Admitted/Allowed/Granted/Rule Absolute
Holding
The Court condoned the delay in filing the appeal and confirmed the stay upon receipt of the 75% deposit.
Summary
The Superintendent Engineer of TAPI Irrigation Development Corporation filed an appeal after a delay of 2,434 days. The delay was explained and the corporation deposited 75% of the award amount as directed by the Court. The respondents were served and an Additional Government Pleader appeared for respondents 7 and 8. The Court, after considering the reasons and the partial deposit, condoned the delay and disposed of the civil application for condonation. Subsequently, having received the 75% deposit, the Court confirmed the stay previously granted on 19‑08‑2025. Both the condonation application and the stay application were therefore disposed of.
Issues considered
- Whether a delay of 2,434 days in filing an appeal can be condoned under the provisions governing civil applications for condonation of delay.
- Whether the stay granted earlier should be confirmed upon the appellant's deposit of 75% of the award amount.
Subjects
- condonation of delay
- stay of execution
- award deposit
- civil application
- high court
- appeal delay
Judgment
2026:BHC-AUG:42280
1 973..odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
CIVIL APPLICATION NO. 8898 OF 2025
IN FAST/21373/2025
WITH
CIVIL APPLICATION NO. 8899 OF 2025
IN FAST/21373/2025
THE SUPERINTENDENT ENGINEER, TAPI IRRIGATION
DEVELOPMENT CORPORATION JALGAON AND ANR
VERSUS
VITTHAL PANDURANG MALI DIED THR. LRS. KUSUM VITTHAL
MALI AND ORS
...
Advocate for Applicants : Mr. Tambe Rahul Ashokrao
AGP for Respondent nos. 7 & 8 : Ms. Preeti Diggikar
…
CORAM : MANJUSHA DESHPANDE, J.
DATE : 11th SEPTEMBER, 2026
PER COURT :
Civil Application for condonation of delay :
1. The Appeal has been filed by the acquiring body. There is a
delay of 2434 days in filing the Appeal.
2. All the Respondents are served. Learned AGP appears for
Respondent nos. 7 and 8.
3. The delay occurred in filing the Appeal has been explained
by the acquiring body and they have also deposited 75% of the amount
under the award as directed by this Court.
2 973..odt
4. For the satisfactory reasons mentioned in the Civil
Application, the Civil Application for condonation of delay deserves to
be allowed. Delay is condoned.
5. Civil Application is accordingly disposed of.
Civil Application for stay :
6. In furtherance of the order passed by this Court on
19.08.2025, the Appellant / acquiring body has deposited the amount on
20.04.2026.
7. In view of the deposit of 75% of the amount under the
award, the stay granted by this Court vide order dated 19.08.2025, is
confirmed.
8. Civil Application for stay is disposed of.
( MANJUSHA DESHPANDE, J. )
SPC