Created by Fuzzy Cloud

Bombay High Court

M/S.MAHINDRA UGINE STEEL CO. LTD.versusSHREE SHAKTI MILLS LTD.

Decided
Disposal
DISPOSED OFF
Bench
REGISTRY DISPOSAL OS

Holding

The Court directed the petitioner to produce the assignment documents for the workers' claims and ordered the Official Liquidator to scrutinise them and place a modified report for sanction.

Summary

In a petition under the Companies Act, 1956 concerning M/s Shree Shakti Mills Ltd., the petitioner, represented by Mr. Amit Shethi, claimed that a large number of workers' dues had been paid back and that he possessed assignment documents in his favour for those claims. The Official Liquidator, Mr. S.C. Gupta, was present. The Court directed the petitioner to produce the said assignment documents before the Official Liquidator within two weeks. The Official Liquidator was ordered to scrutinise the documents and, after examination, to place a modified report before the Court for sanction. No further orders were made beyond this procedural direction.

Issues considered

  • Whether the assignment documents presented by the petitioner in respect of workers' claims are valid and can be relied upon for the liquidation proceedings

Legislation cited

Subjects

  • Companies Act 1956
  • Liquidation
  • Assignment of claims
  • Workers' dues
  • Official Liquidator

Judgment

                     1


       IN THE HIGH COURT OF JUDICATURE AT BOMBAY

          ORDINARY ORIGINAL CIVIL JURISDICTION

           COMPANY PETITION NO. 308 OF 1978



                   In the matter of Companies Act, I

                   of 1956.

                            And

                   In the matter of M/s. Shree

                   Shakti Mills Ltd., (in

                   Liqn.)



Mr. Amit Shethi i/by Wadia Ghandhy & Co.

for Ms. Ajay Poddar.

Mr. S. C. Gupta, Official Liquidator

          present.

                              ..

                   CORAM : S.U. KAMDAR, J.

                   DATE   : 20TH JANUARY,2005.



ORDER ON OFFICIAL LIQUIDATOR’S REPORT DATED

16.9.2004.



P.C.



1.        Mr.   Sethi appearing for Mr.   Ajay Poddar

states that large number of workers are paid back by

them.    He further states that he has necessary

documents of assignment in his favour in respect of
                  2
the said claims of the workers.   He is directed to

produce the necessary documents before the Official

Liquidator and the official Liquidator to scrutinise

the same within a period of two weeks from today.

After scrutinising the said documents, the Official

Liquidator will place modified report for sanction

before the Court.


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.