Bombay High Court
Sanjeev MittalversusState of Maharashtra
- Decided
- Disposal
- Disposed Off
Holding
The Court held that the corporation is given a further six‑week period to comply with the earlier order and disposed of the contempt petition.
Summary
Petitioner Sanjeev Mittal filed a writ petition seeking an order directing Thane Municipal Corporation (TMC) to remove an alleged unauthorized encroachment by a private person in the common areas of a building, invoking the Maharashtra Regional and Town Planning Act, 1966. The Division Bench of the High Court, on 16 March 2026, ordered TMC to decide the representation made by the petitioner within three months and to follow the procedures under the MRTP Act and the Maharashtra Municipal Corporation Act. The petitioner later filed a contempt petition alleging that TMC willfully failed to comply with that order. The Court granted TMC an additional six‑week period to comply, warning that failure would permit the petitioner to move an application for recalling the order, and consequently disposed of the contempt petition.
Issues considered
- Whether Thane Municipal Corporation willfully disobeyed the order dated 16 March 2026.
- Whether contempt proceedings are warranted against the corporation for alleged non‑compliance.
Legislation cited
Subjects
- contempt
- writ petition
- encroachment
- municipal corporation
- MRTP Act
- Maharashtra Municipal Corporation Act
- compliance
- court order
Judgment
(4)-CP-421-26.doc
PANCHAL
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
BALAJI
Digitally
signed by
BALAJI
GOVINDRAO
CONTEMPT PETITION NO. 421 OF 2026
GOVINDRAO PANCHAL
PANCHAL Date:
2026.09.24
10:51:48
+0530
IN
WRIT PETITION NO. 2609 OF 2026
Sanjeev Mittal ...Petitioner
Versus
State of Maharashtra & Ors. ...Respondents
...
Mr. Rishikesh Soni a/w Ms. Raveena Yaddav i/by Ms. Raveena
Yaddav, for the Petitioner.
Mrs. Neha S. Bhide, GP a/w Mr. O. A. Chandurkar, Addl. GP &
Mrs. G. R. Raghuwanshi, for the Respondent-State.
...
CORAM : MAHESH CHANDRA TRIPATHI, CJ. &
ADVAIT M. SETHNA, J.
DATE : 23rd SEPTEMBER, 2026.
P.C.:
1. The instant Contempt Petition is preferred alleging
therein that the Respondent No.2 has willfully and deliberately
disobeyed the order dated 16 th March, 2026 passed by the
Division Bench of this Court. For ready reference, the same is
reproduced hereunder :-
“1. The Petitioner wants this Court to issue directions to
Respondent No.2- Thane Municipal Corporation to remove
unauthorized encroachment alleged to be made by
Respondent No.3 private person in the common areas of the
building by name Lavino Kapoor Compound. It is true as per
provisions of the Maharashtra Regional and Town Planning
Act, 1966, it is the responsibility of the planning authority to
take action for removal of the encroachment. It may be on a
private land or on a public land, or it may be in the private
building. It is very well true that to take any action, the
1
(4)-CP-421-26.doc
planning authority is expected to follow the procedure laid
down in the said Act and after arriving at the satisfaction
they are supposed to take initial action.
2. If the Petitioner claims that Respondent No.3 has done
encroachment on a common area, certainly he has got right to
make complaint to the planning authority i.e. corporation. It is
the planning authority before whom only the complaint can be
made about removal of unauthorized construction. The
Petitioner through advocate’s notice dated 18 th November
2025 has brought it to the notice of corporation about said
unauthorized construction. It is his grievance that neither the
corporation has taken any action nor informed to the
Petitioner. That is why this Petition.
3. Considering the limited reliefs we are inclined to grant
relief. We do not find necessary to hear the Respondents. It is
made clear that the Corporation is the final authority to take
call on this complaint. It is for the corporation to decide
whether any construction in the common areas is made and
whether it is authorized. Even Respondent No.3 is to be
heard. There are certain averments made in the Petition about
right to hold the first floor and second floor premises and the
lift. The Petitioner has also made certain averments about the
history of his title. As, we are only issuing a direction to
decide representation, we are not making any comment about
the averments made in the Petition. We leave it to the decision
of Respondent No.2. Hence, the following order:
ORDER
(i) The Writ Petition is allowed.
(ii) The Respondent No.2- Thane Municipal Corporation is
directed to decide the representation made through legal
notice dated 18th November 2025 issued by the Petitioner
within the period of three months from communication of
the order.
(iii) The Petitioner is directed communicate this order to
Respondent No.2.
(iv) Respondent No.2 is directed to take a decision about
the grievance by following the procedure as laid down in
MRTP Act and in Maharashtra Municipal Corporation
Act.
4. Writ Petition is disposed of.”
2. Considering the order dated 16 th March, 2026, we
find that one more opportunity/indulgence is extended to the
2
(4)-CP-421-26.doc
Respondent No.2 to comply with the order of this Court dated
16th March, 2026 within six weeks, failing which the Petitioner
would be at the liberty to move appropriate application for
recalling the order passed today. Copy of this order be served
upon the Respondents within one week from its uploading to
ensure necessary compliance.
3. With the aforesaid directions, Contempt Petition is
Disposed Of.
[ADVAIT M. SETHNA, J.] [CHIEF JUSTICE]