Bombay High Court
MR. MADHUKAR VISHNU TALEKARversusMR. PANDURANG ATMARAM PAI (SEANCE DECEASED) AND ORS.
- Decided
- Disposal
- Disposed Off
Holding
The interim applications were allowed, and the revision applications were scheduled for final hearing on 18 September 2026.
Summary
The court considered two interim applications filed by Gopal Ganpat Samrit and Madhukar Vishnu Talekar seeking to expedite the hearing of their civil revision applications (Nos. 425 of 2014 and 695 of 2014) against the estate of the deceased Pandurang Atmaram Pai and others. The applicants contended that delay would prejudice their rights, while the respondents raised no substantive objection. The bench examined whether procedural rules permitted granting interim relief to set a final hearing date. Finding no impediment, the court allowed both interim applications, directing that the revision applications be listed for final hearing on 18 September 2026. The interim applications were thereafter disposed of.
Issues considered
- Whether an interim application for expediting the hearing of a civil revision may be granted
Subjects
- interim application
- civil revision
- expediting hearing
- procedural law
- Bombay High Court
Judgment
Neeta Sawant 15-IA-1850-2025 & 1854-2025.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
INTERIM APPLICATION NO. 1850 OF 2025
IN
CIVIL REVISION APPLICATION NO. 425 OF 2014
Mr. Gopal Ganpat Samrit …..Applicant
(Orig. Applicant/
Orig. Defendant)
: Versus :
Mr. Pandurang Atmaram Pai,
Deleted (Since Deceased) & Ors. ….Respondents
(Orig. Respondents/
Orig. Opponents)
INTERIM APPLICATION NO. 1854 OF 2025
IN
CIVIL REVISION APPLICATION NO. 695 OF 2014
Mr. Madhukar Vishnu Talekar …..Applicant
(Orig. Applicant/
Orig. Defendant)
: Versus :
Mr. Pandurang Atmaram Pai,
Deleted (Since Deceased) & Ors. ….Respondents
(Orig. Respondents/
Orig. Opponents)
_____________________________________________________________________________
PAGE NOS. 1 of 2
Thursday, 3 September 2026
Neeta Sawant 15-IA-1850-2025 & 1854-2025.docx
Mr. Arman Grewal i/b. N.N. Vaishnawa & Co. for the Applicant.
Mr. Hemant Ghadigaonkar with Pallabi Chatterjee for the Petitioner in
WP-1802 of 2015.
Ms. Riddhi Dhamecha i/b. Mr. Dhiren Shah, for the Respondent-Society.
Ms. Smita Sawant, for the Proposed Respondent.
CORAM : SANDEEP V. MARNE, J.
DATED : 3 SEPTEMBER 2026.
P.C :
1) The Interim Applications are filed for expediting the hearing of
the Revision Applications.
2) Perused the Interim Applications. For the reasons stated in
the applications, the same are allowed. Add the Revision Applications to
the final hearing board on 18 September 2026. Interim Applications are
accordingly disposed of.
Digitally
signed by
NEETA
NEETA SHAILESH
SHAILESH SAWANT
SAWANT Date:
2026.09.07
16:52:22 [SANDEEP V. MARNE, J.]
+0530
_____________________________________________________________________________
PAGE NOS. 2 of 2
Thursday, 3 September 2026
Checking your session…