Bombay High Court
ICICI LOMBARD GENERAL INSURANCE CO. LTD. THR LEGAL OFFICER NANDITHA PILLAIversusAUDREY DINIZ AND 2 ORS
- Disposal
- Allowed
Holding
The court condoned the 53‑day delay and allowed the application.
Summary
ICICI Lombard General Insurance Co. Ltd., through its legal officer, filed a miscellaneous civil application seeking condonation of a 53‑day delay in filing an appeal. The applicant explained that after obtaining the certified copy of the impugned order on 8 January 2026, the resignation of the officer handling the file caused a delay in forwarding it for legal approval, which was only obtained on 10 April 2026. Subsequent procedural steps required sending the file to the Regional Office at Hubli and then to the Head Office in Bengaluru before sanction to file the appeal could be secured. The respondent opposed the application, but the court found the explanation, though somewhat sketchy, sufficient to justify condonation. Consequently, the court allowed the application, condoned the 53‑day delay, and disposed of the matter.
Issues considered
- Whether a delay of 53 days in filing an appeal can be condoned under the procedural rules.
Subjects
- delay condonation
- civil procedure
- appeal filing
- procedural law
- miscellaneous civil application
Judgment
2026:BHC-GOA:1844
32 MCA 412 2026
Sonam
IN THE HIGH COURT OF BOMBAY AT GOA
MISC.CIVIL APPLICATION NO.412 OF 2026
IN
FIRST APPEAL NO.1518 OF 2026 (F)
ICICI LOMBARD GENERAL INSURANCE
CO. LTD. THR LEGAL OFFICER
NANDITHA PILLAI ... APPLICANT
Versus
AUDREY DINIZ AND 2 ORS ... RESPONDENTS
Mr. James Lopes, Advocate for the Applicant.
Mr. A. Godinho and Mr. K. Dessai, Advocates for Respondent
No. 1.
CORAM:- VALMIKI MENEZES, J.
DATED :- 11th September, 2026
P.C.:
1. Though the application has been opposed by the Respondent
No. 1, the delay of 53 days stands condoned for the following
reasons:
The Applicant has set out that after obtaining the certified copy
of the impugned order and collecting the same on 08.01.2026, due
to the resignation of the officer maintaining the Applicant’s
office, there was a delay in the file being forwarded for legal
approval. The Legal approval was obtained on 10.04.2026, after
which the file had to be sent to the Regional Office at Hubli and
Page 1 of 2
11th September, 2026
32 MCA 412 2026
then Head Office at Bangaluru, after which the sanction was
obtained to file the Appeal. The application is supported by an
Affidavit. Though the explanation given is bit sketchy for the block
period for the time spent in moving the file, considering that the
delay is a general explanation, I allow the application and the delay
of 53 days stands condoned.
2. The application stands disposed of.
VALMIKI MENEZES, J.
Page 2 of 2
11th September, 2026