Bombay High Court
Shobha Neelkamal TejwaniversusSUBHASHISH DEVELOPERS
- Decided
- Disposal
- Disposed Off
Holding
The Court held that there was no apparent error or substantial ground to review the order dated 10 June 2026.
Summary
The petitioner, Shobha Neelkamal Tejwani, filed a review petition challenging the order dated 10 June 2026 passed by this Court in Second Appeal No. 238 of 2026 against Subhashish Developers. The petition sought relief on the ground that the earlier order contained an apparent error or other substantial ground warranting review. The Court examined the record and the contentions raised by the petitioner’s counsel, Mr. Vikrant Khare, along with Ganesh Pandit and Arhat Dhivare. It held that no error was apparent on the face of the record and that the petitioner had not demonstrated any substantial ground for review. Consequently, the Court dismissed the review petition, leaving the original order undisturbed.
Issues considered
- Whether there is any error apparent on the face of the record in the order dated 10 June 2026
- Whether the petitioner has any substantial ground to seek a review of that order
Subjects
- review petition
- civil appellate jurisdiction
- error on record
- substantial ground
- dismissal
Judgment
33-RPS-1-2026.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
REVIEW PETITION NO. 1 OF 2026
IN
SECOND APPEAL NO. 238 OF 2026
Shobha Neelkamal Tejwani ..Petitioner
Versus
Subhashish Developers …Respondent
Mr. Vikrant Khare, with Ganesh Pandit and Arhat Dhivare, for the
Petitioner.
CORAM: N. J. JAMADAR, J.
DATE : 9th SEPTEMBER 2026
P.C.:
1. Heard the learned Counsel for the Petitioner.
2. There is no error apparent on the face of the record nor there is
any substantial ground to review the order dated 10 th June 2026 passed
ARUN
RAMCHANDRA
by this Court.
SANKPAL
Digitally signed by
ARUN RAMCHANDRA
SANKPAL
3. Review Petition stands dismissed.
Date: 2026.09.11
10:09:23 +0530