Bombay High Court
DEEP HOMES AND CONSTRUCTIONS LLPversusMRS. MEGHANA ABHISHEK LAKHOTIA
- Decided
- Disposal
- Disposed Off
Holding
Possession is deemed delivered only upon issuance of the occupation certificate; the force‑majeure clause does not excuse the delay; and the COVID‑19 moratorium is inapplicable, so the promoter must pay interest up to 14 June 2021.
Summary
The allottees purchased a flat from Deep Homes and Construction LLP under a sale agreement that required possession by 31 March 2019. The promoter delivered fit‑out possession on 25 March 2021 without an occupation certificate, which was only obtained on 14 June 2021. The allottees complained to MahaRERA and were awarded interest only up to the fit‑out possession date, with a COVID‑19 moratorium benefit. Both parties appealed; the Appellate Tribunal reversed the order, directing interest until the occupation certificate date and disallowing the moratorium. The promoter challenged this, invoking a force‑majeure clause and arguing the moratorium applied. The High Court held that possession is deemed delivered only upon issuance of the occupation certificate, the force‑majeure clause does not cover the delays, and the moratorium is inapplicable because the contractual possession date preceded the pandemic, thereby dismissing the appeal.
Issues considered
- Whether delivery of fit‑out possession without an occupation certificate constitutes possession for the purpose of interest liability under RERA.
- Whether the force‑majeure clause in the sale agreement exempts the promoter from liability for delay.
- Whether the COVID‑19 moratorium notifications apply to interest payable for delay when the contractual possession date predates the pandemic.
- Whether any substantial question of law arises for consideration.
Legislation cited
- Real Estate (Regulation and Development) Act, 2016 — s. 11(4), 18(1), 19(10), 19(6), 6
Subjects
- RERA
- possession
- occupation certificate
- interest liability
- force majeure
- COVID-19 moratorium
- delay in real estate projects
- consumer protection
Judgment
-SA-389-2026.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
SECOND APPEAL NO. 389 OF 2026
Deep Homes And Construction LLP ..Appellant
Versus
Meghana Abhishek Lakhotia & Anr …Respondents
Mr. Sanjay Chaturvedi, for the Appellant.
Mr. Keshav Borhade, for the Respondents.
CORAM : N. J. JAMADAR, J.
DATE : 19th AUGUST 2026
ORDER:
1. This Second Appeal is directed against a common judgment and
order dated 2nd April 2026 in Appeal No. AT006000000103939 of 2022
and Appeal No. AT006000000134059, whereby the Appeal preferred by
the Allottees against a common order dated 27 th May 2022 passed by
the Maharashtra Real Estate Regulatory Authority (“MahaRERA”), came
ARUN
RAMCHANDRA
to be partly allowed and the Appellant-Promoter was directed to pay
SANKPAL
Digitally signed by
ARUN
RAMCHANDRA
the interest on the amount of Rs.1,36,50,167/- paid by the Allottees to
SANKPAL
Date: 2026.08.27
21:02:39 +0530
the Appellant-Promoter towards consideration at the SBI’s hightest
Marginal Cost Lending Rate (MCLR) plus 2% with effect from 1 st April
2019 till 14th June 2021 and the Appeal preferred by the Appellant-
Promoter came to be dismissed.
ARS 1/8
-SA-389-2026.DOC
2. The Appeals arose in the backdrop of the following facts.
2.1 The Respondents-Allottees had agreed to purchase Flat No. 1601
on the 16th floor in a building named, “Auralis The Twins”, then being
developed by the Appellant-Promoter, under a registered Agreement for
Sale dated 31st January 2019, for a total consideration of
Rs.1,36,81,500/-. Under the terms of the contract, the Promoter was to
deliver the possession of the subject flat on or before 31st March 2019.
2.2 The project got delayed. The Promoter gave fit out possession of
the subject flat on 25th March 2021 without obtaining occupation
certificate. Eventually, the occupation certificate was obtained on 14 th
June 2021.
2.3 The Allottees filed a complaint before the MahaRERA alleging
delay in the delivery of possession of the subject flat and sought interest
on the amount of consideration parted with by the Allottees on account
of delay in delivery of possession, rental income and compensation for
the delay in the project.
2.4 The Authority was persuaded to partly allow the complaint and
direct the Promoter to pay interest to the Allottees for the period
commencing from 1st April 2019 to the delivery of fit out possession on
25th March 2021, only. The Authority was also persuaded to grant the
benefit of moratorium in regard to the payment of interest during the
COVID-19 pandemic period pursuant to the Notifications/Orders Nos.
ARS 2/8
-SA-389-2026.DOC
13 and 14 dated 2nd April 2020 and 18th May 2020 issued by the
MahaRERA.
2.5 Being aggrieved, the Allottees preferred an Appeal, being Appeal
No. AT006000000134059 of 2022. The Promoter also preferred an
Appeal, being Appeal No. AT006000000103939 of 2022.
2.6 By the impugned order, the Appellate Tribunal was persuaded to
interfere with the order passed by the Authority, primarily on two
counts. First, since the occupation certificate was obtained on 14 th June
2021, the delivery of fit out possession on 25 th March 2021 did not
amount to delivery of possession of the subject flat. And, thus, the
Allottees were entitled to payment of interest on the amount of
Rs.1,30,50,167/- from 1st April 2019 till the issue of occupation
certificate on 14th June 2021. Second, the MahaRERA was in error in
granting the benefit of the moratorium to the Promoter as agreed date
of delivery of possession, i.e. 31 st March 2019 was much prior to the
onset of COVID 19 pandemic. Thus the promoter was not entitled to the
benefit of moratorium. Therefore, the Appellate Tribunal directed the
Promoter to pay interest at the aforesaid rate with effect from 1 st April
2019 till 14th June 2021..
2.7 Being aggrieved, the Promoter has preferred this Appeal.
ARS 3/8
-SA-389-2026.DOC
3. Mr. Sanjay Chaturvedi, the learned Counsel for the Appellant,
submitted that the Appellate Tribunal committed manifest error in law
in directing the payment of interest till 14 th June 2021, though
admittedly the fit out possession was delivered on 25 th March 2021.
Secondly, the disallowance of the benefit of the moratorium was in the
teeth of the express Notifications/Orders. Thirdly, the delay in the
delivery of possession of the subject flat was not at all attributable to
the Promoter as the delay occurred on account of the unforeseen events
beyond the control of the Promoter. Inviting attention of the Court to
the recitals in Clause 21 of the Agreement for Sale, Mr. Chaturvedi
submitted that the parties had explicitly agreed that upon occurrence of
the force majeure events as enumerated therein, the Promoter would be
entitled to extension of time for delivery of possession of the subject
flat. Lastly, Mr. Chaturvedi would submit that, the Appellate Tribunal
did not advert to the corresponding obligation of the Allottees under
Section 19(6) of the Real Estate (Regulation and Development) Act,
2016 (“RERA 2016”). These infirmities give rise to substantial questions
of law, urged Mr. Chaturvedi.
4. In opposition to this, Mr. Keshav Borhade, the learned Counsel
for Respondent Nos. 1 and 2-Allottees, would submit that in the
backdrop of the uncontroverted facts the impugned order is wholly
justifiable. The grounds now sought to be urged by the Promoter are
ARS 4/8
-SA-389-2026.DOC
clearly untenable. The failure to deliver the possession of the subject flat
in accordance with the terms of the Agreement between the parties,
give rise to indefeasible right of the Allottees to receive interest on the
amount of consideration, for the delayed period. Thus, no substantial
question of law arises for consideration.
5. There is not much controversy over the foundational facts. First,
the execution of the registered Agreement for Sale and the terms of the
bargain incorporated therein are not put in contest. Incontrovertibly the
possession of the subject flat was agreed to be delivered on or before
31st March 2019. Indisputably the project got delayed and only fit out
possession and that too without occupation certificate, was delivered on
25th March 2021. Occupation Certificate was obtained on 14 th June
2021.
6. In the backdrop of aforesaid uncontroverted facts, the submission
on behalf of the Petitioner that the possession of the subject flat was
delivered on 25th March 2021 does not advance the cause of the
Promoter. The Appellate Tribunal was justified in holding that the
delivery of fit out possession without occupation certificate does not
amount to delivery of possession of the subject flat in accordance with
the terms of the Agreement. Under Section 11(4), it is the obligation of
the Promoter to obtain the occupation certificate. Conversely, under
Section 19(10), the liability of the Allottee is to take possession of the
ARS 5/8
-SA-389-2026.DOC
apartment within a period of two months of the grant of occupancy
certificate. Thus, possession sans occupancy certificate is non est in the
eye of law. The Appellate Tribunal was thus within its right in
construing the delivery of date of possession as the date on which
occupation certificate was obtained by the Promoter.
7. The support sought to be drawn by Mr. Chaturvedi from Clause
21 of the Agreement for Sale to the submission that on account fo force
majeure events the parties had agreed that the period of delivery of
possession would stand extended, appears to be of little assistance.
8. A bare perusal of the Clause 21 of the Agreement for Sale
indicates that routine and mundane events have also been incorporated
therein as the situations beyond the control of the Promoter. For
instance, unavailability of the building material, water or electricity
supply; any directives by the Government and/or by the Local Authority,
economic downturn, changes in any Rules and Regulations, Bye-laws of
various Statutory Bodies and Authorities, delay in the issue of
occupation certificate and/or any other sanction and/or grant of any
permission, approvals etc.
9. The aforesaid events ex-facie do not constitute a force majeure
event within the meaning of Section 6 of RERA 2016. The Explanation
appended to Section 6 provides that for the purpose of that section, the
expression “force majeure” shall mean a case of war, flood, drought,
ARS 6/8
-SA-389-2026.DOC
fire, cyclone, earthquake or any other calamity caused by nature
affecting the regular development of the real estate project.
10. By no stretch of imagination, the afore enumerated
events/contingencies in Clause 21 of the Agreement for Sale can qualify
as force majeure events. The decision of the Division Bench of this Court
in the case of Neelkamal Realtors Suburban Pvt And Anr Vs Union of
India & Ors1 was thus rightly relied upon by the Appellate Tribunal to
negate the claim premised on force majeure events.
11. Similarly, disallowance of the benefit of the moratorium in the
matter of the application of the interest by the Appellate Tribunal
appeared to be sustainable. The possession of the subject flat was
agreed to be delivered on or before 31 st March 2019, well a year before
the COVID 19 Pandemic restrictions were imposed.
12. The right of Allottees to get interest from the Promoter on the
amount of consideration paid to the Promoter in the event of delay in
delivery of possession has been construed to be an indefeasible right. In
the case of M/s Newtech Promoters And Developers Pvt Ltd Vs State of
U.P. & Ors2, the Supreme Court has enunciated in clear and explicit
terms that Section 18(1) gives an indefeasible right to the allottee to get
a return of the amount on demand if the promoter is unable to hand
over possession in terms of the Agreement for Sale or has failed to
1 (2017) SCC OnLine Bom 9302.
2 2021 SCC OnLine SC 1044.
ARS 7/8
-SA-389-2026.DOC
complete the project by the date specified. In the case of Imperia
Structures Ltd. Vs. Anil Patni and Another3, the Supreme Court held
that, Section 18 confers an unqualified right upon an allottee to get a
refund of the amount deposited with the promoter and interest at the
prescribed rate, if the promoter fails to complete or is unable to give
possession of an apartment as per the date specified in the agreement.
The proviso to Section 18(1) contemplates a situation where the
allottee does not intend to withdraw from the project, in that case, he is
entitled to and must be paid interest for every month of delay till the
handing over of the possession.
13. For the forgoing reasons, no question of law, much less a
substantial question of law, arises for consideration.
14. The Second Appeal thus stands dismissed.
[N. J. JAMADAR, J.]