Holding

The court directed Respondent No.2 to decide the appointment proposal after the petitioners remedy the identified deficiencies, and to do so within six weeks.

Summary

The petitioners sought a court direction compelling Respondent No.2 to decide on a proposal dated 2 February 2022 for appointing Petitioner's first petitioner as a Shikshan Sevak in the Management School. The respondents disclosed that on 27 February 2026 they had communicated certain deficiencies in the proposal, which remained unaddressed. The High Court ordered the petitioners/management to remedy the deficiencies within two weeks of the order. Upon compliance, Respondent No.2 was directed to decide the proposal on its merits, in accordance with law, and to render the decision within six weeks. The petition was disposed with these directions.

Issues considered

  • Whether the court can issue a mandatory direction to an administrative authority to decide a pending appointment proposal within a stipulated time
  • Whether the petitioners must first comply with the deficiencies identified by the authority before the decision can be made

Subjects

  • writ petition
  • appointment
  • Shikshan Sevak
  • administrative direction
  • deficiency compliance
  • expeditious decision

Judgment

2026:BHC-KOL:8655-DB

                                                                      27-WP-10502-2025(C).doc


                              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                       CIRCUIT BENCH AT KOLHAPUR
                                      CIVIL APPELLATE JURISDICTION

                                    WRIT PETITION NO. 10502 OF 2025

               Swati Subhash Meharkar And Another                        ...Petitioners
                         Versus
               The State of Maharashtra and Others                       ...Respondents

                                              ——————
               Mr. Sagar Mane, for the Petitioners.
               Mr. Ashok M. Misal for Respondent No.2.
               Ms. Tejas J. Kapre, AGP for the Respondent-State.
                                               ——————

                                                CORAM :        SHARMILA U. DESHMUKH &
                                                               NEERAJ P. DHOTE, JJ.

                                                DATE       :   SEPTEMBER 08, 2026.

               P. C. :

               1.        The Petition was filed seeking a direction to Respondent No.2 to

               decide the proposal dated 2 nd February, 2022, seeking approval to the

               appointment of Petitioner No.1 as Shikshan Sevak in the Petitioner No.2

               Management School. The affidavit-in-reply discloses that on 27th

               February, 2026, the Management was communicated the deficiencies,

               which have not yet been complied.

               2.           Let the Petitioner/Management comply with the deficiencies

               within a period of two weeks from today.




               Jamadar-SL                         1 of 2
                                                     27-WP-10502-2025(C).doc


3.     After the deficiencies are complied with, the Respondent No.2 to

decide the proposal on its own merits and in accordance with law,

expeditiously, and in any event within a period of six weeks after the

compliance of the deficiencies by the Petitioner/Management.

4.     The Petition is disposed of in the above terms.




 [NEERAJ P. DHOTE, J.]                    [SHARMILA U. DESHMUKH, J.]




Jamadar-SL                       2 of 2


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.