Bombay High Court
BANK OF MAHARASHTRA THROUGH ITS CHIEF MANAGERversusTHE ADDITIONAL DISTRICT MAGISTRATE DHARASHIV AND ANOTHER
- Disposal
- DISPOSED OFF
Holding
The writ petition is withdrawn and disposed of, with permission granted to the petitioner to approach the DRT.
Summary
The Bank of Maharashtra filed a writ petition before the Bombay High Court, Aurangabad Bench, challenging an order of the Additional District Magistrate, Dharashiv. The petitioner sought relief, but the Court was not inclined to grant it. The petitioner’s counsel then requested permission to withdraw the petition and to approach the Debt Recovery Tribunal (DRT) instead. The Court granted permission to withdraw and disposed of the writ petition as withdrawn. The Court also observed that, in the absence of any interim order from the DRT in favour of the borrower, the Tehsildar is empowered to execute the order.
Subjects
- withdrawal of writ petition
- Debt Recovery Tribunal
- execution of order
- Tehsildar
- bank litigation
Judgment
2026:BHC-AUG:39095-DB
1 41.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
41 WRIT PETITION NO. 10669 OF 2026
BANK OF MAHARASHTRA THROUGH ITS CHIEF MANAGER
VERSUS
THE ADDITIONAL DISTRICT MAGISTRATE DHARASHIV AND ANOTHER
...
Advocate for the Petitioner : Mr. Adwant S.V.
AGP for Respondent/State : Mr. N.D. Batule
…
CORAM : NITIN B. SURYAWANSHI AND
ABASAHEB D. SHINDE, JJ.
DATE : 27.08.2026
PER COURT :
. After arguing for sometime, when this Court was not inclined to
grant relief, learned Advocate for the petitioner seeks permission to
withdraw the petition with liberty to approach the Debts Recovery
Tribunal (DRT). Permission is granted. Writ Petition is disposed of as
withdrawn.
2. We may observe that, since there is no interim order passed by
the DRT in favour of the borrower, the Tehsildar can execute the order.
( ABASAHEB D. SHINDE, J. ) ( NITIN B. SURYAWANSHI, J. )
vsj..