Bombay High Court
MOHAMMED YUSUF ABDUL KARIM ALIAS YUSUF KARIMversusPUNE METROPOLITIAN REGISION DEVELOPMENT AUTHORITY THROU. METROPOLITIAN COMMISSIONER AND ORS
- Decided
- Disposal
- Disposed Off
Holding
The demolition order was held to be premature and the court ordered that the petitioner be allowed to file a regularisation application, with no coercive action to be taken until the application is decided.
Summary
The petitioner challenged a demolition order dated 29 July 2026 issued by the Pune Metropolitan Region Development Authority (PMRDA) against structures on land acquired between 1980 and 1993. The petitioner argued that he had obtained a construction permission from the Gram Panchayat on 18 February 1999, which had been continuously recognized through tax assessments and other documents. The court found that the demolition order was passed without considering the legal effect of that permission and therefore was premature. It directed the petitioner to file a regularisation application under the MRTP Act within two weeks and required the respondents to hear the application and pass a reasoned order within 60 days. Until the application is decided, the respondents were barred from any coercive action, including demolition, and no costs were awarded.
Issues considered
- Whether a demolition order can be issued without first considering the construction permission granted by the Gram Panchayat.
- Whether the petitioner must seek regularisation of the structures under the MRTP Act before any demolition can be effected.
- Whether the respondents may take coercive action against the petitioner pending the outcome of a regularisation application.
Legislation cited
Subjects
- demolition order
- regularisation
- construction permission
- planning authority
- writ jurisdiction
- MRTP Act
- property tax
- Gram Panchayat
Judgment
bdp
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.10811 OF 2026
Mohammed Yusuf Abdul Karim @
Yusuf Karim .. Petitioner
Vs.
Pune Metropolitan Region Development
Authority and Ors. .. Respondents
Mr. Hemant Ingle with Mr. Pratik Ingle, Mr. Mrunal Ingle, Mr. Imtiyaz
S. and Mr. Umar Kazi, i/by Mr. Prashant S. Goyal, Advocates for the
Petitioner.
Mr. Rohit Sakhadeo, Advocate for Respondent Nos.1 and 2-PMRDA.
Mrs. Pooja Patil, AGP for the Respondent-State of Maharashtra.
CORAM : RAVINDRA V. GHUGE, ACJ. &
GAUTAM A. ANKHAD, J.
DATE : 20th August, 2026.
P.C. :
1. The Petitioner challenges the demolition order dated 29th
July, 2026 passed by Respondent No.2 in relation to structures standing
on Gat Nos. 221, 222 and 223, at Mouje Vaksai, Taluka Maval, District
Pune.
2. Mr. Hemant Ingle, learned counsel appearing for the
Petitioner, submits that the Petitioner acquired the aforesaid lands under
registered conveyances executed between 1980 and 1993. The impugned
1/5
916-WP-10811-2026.odt
order concerns the structures subsequently constructed on the said lands.
The Petitioner filed an Application dated 21st November 1998 to
Respondent No.3, Gram Panchayat, which was considered in the
meeting held on 23rd November, 1998 and Resolution No.47/2 was
passed. Pursuant thereto, Respondent No.3 granted construction
permission dated 18th February, 1999. Since then, the structures have
been continuously assessed by Respondent No.3 and property taxes have
been recovered from the Petitioner from 1998-1999 onwards. There are
documents including Zone Certificate dated 29th December 2016 and
correspondence relating to the electricity meter connection. The action
against the Petitioner has been initiated pursuant to a motivated
complaint made by Respondent No.5. The Petitioner had submitted a
detailed representation placing the aforesaid facts and documents on
record. However, the same has not been duly considered by Respondent
Nos.1 and 2 before passing the impugned order dated 29th July, 2026.
3. On the other hand, Mr. Rohit Sakhadeo, learned counsel
appearing for Respondent Nos.1 and 2, vehemently submits that the
impugned order is a reasoned order and has been passed after
considering all relevant aspects in the matter. He, therefore, submits that
no interference is warranted in exercise of the writ jurisdiction of this
Court.
2/5
916-WP-10811-2026.odt
4. We have heard the learned counsel for the parties and
perused the record. The Petitioner has placed on record the construction
permission dated 18th February, 1999 issued by Respondent No.3. The
validity of the said permission has not been dealt with in the impugned
order. In these circumstances, a demolition order ought not to have been
passed without first considering the legal effect of the permission
granted by Respondent No.3 and the other documents relied upon by the
Petitioner.
5. Mr. Sakhadeo submits that Respondent No.1 has
subsequently been appointed as the Planning Authority and that the
requisite permission of the Planning Authority would be necessary. We
do not express any opinion on the merits of this contention. In our view,
the controversy can be resolved in the following terms:
(i) Since the Petitioner relies upon the permissions granted by
Respondent No.3, the Petitioner is at liberty to file a
regularization application or such application under the
MRTP Act as may be advised, within a period of two weeks
from today. The Application shall be complete in all
respects and shall be accompanied by all requisite
documents.
3/5
916-WP-10811-2026.odt
(ii) Respondent Nos.1 and 2 shall consider the said Application
on its own merits, after granting an opportunity of hearing
to the Petitioner and thereafter pass a reasoned order within
a period of 60 days from the date of receipt of the
Application.
(iii) The Petitioner shall not seek unnecessary adjournments and
shall extend full cooperation for the expeditious disposal of
the Application.
6. Until the aforesaid Application is decided and a copy of the
order is served upon the Petitioner, Respondent Nos.1 and 2 shall not
take any coercive action against the Petitioner and shall not demolish the
structures in question.
7. We clarify that we have not expressed any opinion on the
legality of the structures or as conferring any right of regularization upon
the Petitioner. The competent authority shall decide the Petitioner’s
Application strictly in accordance with the applicable law.
8. If, upon such consideration, Respondent No.2 finds that any
part of the structure is unauthorized or ought to be demolished,
4/5
916-WP-10811-2026.odt
Respondent No.2 shall be at liberty to take appropriate action after
following the due procedure in law.
9. The Writ Petition is disposed off in the above terms. There
shall be no order as to costs.
[ GAUTAM A. ANKHAD, J. ] [ ACTING CHIEF JUSTICE ]
BHARAT
DASHARATH
PANDIT
Digitally signed by
BHARAT
DASHARATH
PANDIT
Date: 2026.08.21
12:21:11 +0530
5/5
916-WP-10811-2026.odt
Checking your session…