The Court held that Respondent No.1 must decide the petitioner’s proposal dated 22‑07‑2025 within eight weeks of receipt of the order.
Summary
Shalimar Transport and Carting Contractor, through its proprietor, filed a writ petition before the High Court of Bombay, Aurangabad Bench, challenging the State of Maharashtra. The petitioner sought a decision on a proposal it had submitted on 22 July 2025. The Court examined the petition and directed Respondent No.1 to decide the proposal that had been forwarded by Respondent No.3. The decision was to be rendered within eight weeks from the date the Court's order is received. Accordingly, the writ petition was disposed.
Subjects
- writ petition
- administrative decision
- procedure
- Maharashtra
Judgment
2026:BHC-AUG:43174-DB
*1* 5-wp-11697-2026
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
5 WRIT PETITION NO. 11697 OF 2026
Shalimar Transport And Carting Contractor Through Its
Proprietor
VERSUS
State Of Maharashtra Through The Secretary And Others
...
Mr. Rahul R. Karpe, Advocate for the Petitioner
Ms. S. S. Joshi, AGP for Respondents/State
...
CORAM : NITIN B. SURYAWANSHI &
ABASAHEB D. SHINDE, JJ.
DATE : 22nd SEPTEMBER 2026
P. C. :-
1. Writ Petition is disposed of by directing Respondent No.1
to decide the proposal of the petitioner dated 22.07.2025
forwarded by Respondent No.3 within a period of eight (8)
weeks from the date of receipt of copy of this order.
(ABASAHEB D. SHINDE, J.) (NITIN B. SURYAWANSHI, J.)