Bombay High Court
RAJENDRA MADHAVRAO PATIL AND ANOTHERversusEXECUTIVE ENGINEER MIDC OFFICE CHH SAMBHAJINAGAR
- Disposal
- DISPOSED OFF
Holding
The High Court ordered the continuation of the status‑quo order until 16 September 2026, pending the hearing of the miscellaneous civil appeals, without prejudice to the parties.
Summary
The petitioners sought to prevent demolition of structures on plots in the MIDC, Waluj, alleging that the notice issued by the MIDC for demolition did not comply with the one‑month notice requirement under Section 53(1)(a) of the Maharashtra Regional and Town Planning Act, 1966. They had earlier obtained a status‑quo order in the trial court, which was later set aside, and filed miscellaneous civil appeals seeking its continuation. The High Court noted the urgency, the lack of a proper notice, and the pending appeals, and therefore ordered that the status‑quo order continue until the hearing of the appeals on 16 September 2026, without prejudice to the parties. The court directed the district judge to decide the merits of the applications independently. The writ petitions were subsequently disposed of.
Issues considered
- Whether the notice issued by the MIDC on 4 September 2026 complies with the one‑month notice period mandated by Section 53(1)(a) of the Maharashtra Regional and Town Planning Act, 1966.
- Whether the petitioners are entitled to an extension of the status‑quo order pending the hearing of their miscellaneous civil appeals.
- Whether the High Court can grant interim protection without issuing a notice to the respondent.
Legislation cited
- Maharashtra Regional and Town Planning Act, 1966 — s. 53(1)(a)
Subjects
- demolition
- unauthorised construction
- notice period
- status quo
- interim relief
- Maharashtra Regional and Town Planning Act
- High Court
- writ petition
Judgment
2026:BHC-AUG:41879
1 901 & 904-WP-12152-2026.odt
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD
901 WRIT PETITION NO. 12152 OF 2026
Rajendra Madhavrao Patil And Another
VERSUS
Executive Engineer Midc Office Chh Sambhajinagar
AND
904 WRIT PETITION NO. 12189 OF 2026
Manik Tukaram Karche And Others
VERSUS
Executive Engineer Midc Office Chh Sambhajinagar
...
Mr. Gawande Sambhaji Ankushrao for the Petitioners.
...
CORAM : MANJUSHA DESHPANDE, J.
DATE : 10.09.2026
PER COURT :
1. The learned Advocate for the Petitioners places on record the
communication dated 7th September, 2026, intimating the Deputy
Engineer, MIDC, Railway Station Road, Chh. Sambhajinagar, about the
filing of the present Writ Petitions and further informing him that the
matter would be listed for admission today. Despite such intimation, none
appears for the MIDC. Hence, considering the urgency in the matters,
matters are being heard. The said communication is taken on record and
marked as ‘X’ for identification.
2. The Petitioners are apprehending the demolition of the
structure that is a construction over the Plot Nos.RM-140, 125 and 141
Sunny Thote
2 901 & 904-WP-12152-2026.odt
situated at Bajajnagar, MIDC, Waluj, Chh. Sambhajinagar, which is put to
residential as well as commercial use. It is the case of the Petitioners that
they have instituted R.C.S. Nos. 770 of 2025 and 203 of 2026, seeking an
injunction against the Respondent–MIDC, Chh. Sambhajinagar,
restraining it from taking any coercive action pursuant to and in
furtherance of the notice dated 12 th September, 2025 and 20th February,
2026 in their respective Suits, issued by the defendant/MIDC.
3. The applications filed by the Petitioners below Exhibit-5 have
been rejected, against which the Petitioners have also filed Misc. Civil
Appeal No.133 of 2026 and 134 of 2026, before the District Court,
Aurangabad. In these Misc. Civil Appeals a prayer is made for
continuation of the existing status quo order that was granted vide order
8th May, 2026. However, the learned Judge of the District Court has
issued notice making returnable on 16th September, 2026, without
granting any interim protection of continuation of status quo order. It is
submitted that the MIDC has issued a fresh notice for demolition on 4 th
September, 2026, calling upon the Petitioners to remove the so called
unauthorized construction within seven days from receiving the notice.
According to the Petitioners, Section 53(1)(a) of the Maharashtra
Regional and Town Planning Act, 1966 (of the ‘Said Act, 1966’), which
pertains to removal of unauthorized development contemplates notice
period of at least one month for taking necessary steps as specified in the
notice, which has not been followed in the present cases. Although the
Sunny Thote
3 901 & 904-WP-12152-2026.odt
previous communication has been issued on 15 th April, 2026 against
which they have filed a suits before the learned Trial Court, the
Respondent/MIDC has claimed in the suit that, it is not a notice, but only
a intimation given by the Respondent/MIDC.
4. It is also observed by the learned Judge of the Trial Court,
while deciding the Exhibit-5 applications, that a fresh notice is required
to be issued before any demolition. The learned Judge of the Trial Court
rejecting the application has observed that the Respondent/MIDC can
take action in respect of unauthorized construction by following the due
procedure of law. In view of the observations made by the learned Civil
Judge Senior Division, the Respondents have issued a fresh notice on 4 th
September, 2026 requiring the Petitioners to remove the unauthorized
construction within a period of seven days. The notice dated 4 th
September, 2026 is contrary to Section 53(1)(a) of the Said Act, 1966,
since the said section contemplates a notice period of at least one month.
5. The learned Advocate for the Petitioners submits that,
although the Petitioners have filed an application seeking continuation of
the status quo order in the pending M.C.A. Nos. 133 of 2026 and 134 of
2026 on 5th September, 2026, the said application have not yet been
heard by the District Court, Aurangabad. Therefore, he submits that the
Petitioners are constrained to approach this Court. He further submits
that the next date in the said matters is 16th September, 2026.
Sunny Thote
4 901 & 904-WP-12152-2026.odt
6. Considering the apprehension expressed by the Petitioners,
in my view, it would be appropriate to grant interim protection to the
Petitioners by continuing the status quo order till 16 th September, 2026,
i.e., till the date of hearing of the Misc. Appeals filed by the Petitioners
even without issuing any notice to the Respondents as this is only an
interim arrangement, without prejudice to the rights and contentions of
the parties. Accordingly, the order of status quo shall continue to operate
till the hearing of M.C.A. Nos. 133 of 2026 and 134 of 2026 filed by the
Petitioners on 16th September, 2026.
7. The learned District Judge shall thereafter decide the said
applications of the Petitioners on its own merits without being influenced
by any observations made by this Court in the present Writ Petitions.
8. All the contentions of the respective parties are kept open to
be agitated before the District Judge.
9. In view of the directions, these Writ Petitions stand disposed
off.
10. Parties to act on authenticated copy of this order.
[ MANJUSHA DESHPANDE, J. ]
Sunny Thote
Checking your session…