Bombay High Court
SHANKAR GULAB PATHAREversusTHE SPECIAL LAND ACQUITION OFFICER AND ORS
- Decided
- Disposal
- Disposed Off
Holding
The Court held that the petitioners may be granted TDR certificates proportionate to their share, the monetary compensation must be refunded to the Municipal Corporation, and possession of the land must be handed over, thereby disposing of the writ petitions.
Summary
The petitioners challenged the award of land acquisition by the Special Land Acquisition Officer, seeking compensation in the form of Transferable Development Rights (TDR) instead of monetary payment. The Municipal Corporation had already deposited the monetary compensation with the SLAO. The Court allowed amendment of the petition to correct and add petitioners' names, and directed the petitioners to file applications for TDR certificates. It ordered the Municipal Corporation to process these applications within four weeks, to refund the deposited monetary compensation with interest, and to grant TDR certificates proportionate to the petitioners' shares under Section 126(1)(b) of the Maharashtra Regional and Town Planning Act, 1966, after a measurement exercise. The petitioners were also directed to hand over peaceful possession of the land within two weeks, and the earlier interim order was vacated. Consequently, the writ petitions were disposed.
Issues considered
- Whether the petitioners are entitled to receive Transferable Development Rights in lieu of monetary compensation under the Maharashtra Regional and Town Planning Act, 1966.
- Whether the monetary compensation deposited with the Special Land Acquisition Officer should be refunded to the Municipal Corporation.
- What procedural steps must be followed for granting TDR certificates, including public notice and measurement of land.
- Whether the interim order restraining road construction can be vacated in view of the settlement.
Legislation cited
- Maharashtra Regional and Town Planning Act, 1966 — s. 126(1)(b)
Subjects
- land acquisition
- transferable development rights
- compensation
- Maharashtra Regional and Town Planning Act
- interim order
- possession
- municipal corporation
Judgment
bipin prithiani
1
908-wp-12432.23 & anr.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 12432 OF 2023
Shankar Gulab Pathare … Petitioner
Versus
The Special Land Acquisition Officer & Ors. … Respondents
WITH
WRIT PETITION (L) NO. 32312 OF 2023
Dattatraya Balu Pathare & Ors. … Petitioners
Versus
The Special Land Acquisition Officer & Ors. … Respondents
******
Mr. Vishwajit Sawant, Senior Advocate, i/by Mr. Sugandh
Deshmukh for Petitioner in both Writ Petitions.
Mrs. M. S. Bane, AGP for Respondent-State in WP/12432/2023.
Mr. R. S. Pawar, AGP for Respondent-State in WPST/32312/2023.
Mr. Kedar B. Dighe for Respondent Nos.4 to 6-PCMC.
Mr.Khadatare S.S., Asst. Director, Town Planning, PCMC, Present.
Mr. Kute A. B., Deputy Engineer, PCMC, Present.
******
CORAM : MANISH PITALE AND
SHREERAM V. SHIRSAT, JJ.
DATE : 2nd SEPTEMBER 2026
P.C. :
. On 30th June 2026, after hearing the learned counsel for the
parties, this Court passed the following order :
“. At the outset, learned senior counsel appearing for the
Petitioners sought leave to amend Writ Petition (ST) No.
32312 of 2023 in order to correct the name of Petitioner No.
9 as “Sunita Lalasaheb Pathare”. He further submitted that
due to inadvertance, the name of the remaining son of
deceased Lalasaheb Pathare was not shown as a Petitioner in
bipin prithiani
2
908-wp-12432.23 & anr.doc
the said with Petition. In that light, leave is sought to add the
name of Aniket Lalasaheb Pathare as Petitioner No. 10 in the
said petition. In the interest of justice, the prayer made on
behalf of the Petitioners in the said writ petition is granted.
Accordingly, the name of Petitioner No. 9 shall be corrected
and the name of Aniket Lalasaheb Pathare shall be added as
Petitioner No. 10 in the said Petition.
2. Amendment be carried out forthwith.
3. Having heard the learned counsel for the parties, we
find that these petitions can be disposed of by issuing
appropriate directions. The learned counsel for the
Respondent - Municipal Corporation has informed this Court
that the monetary compensation pertaining to the shares of
the Petitioners has been already deposited with the Special
Land Acquisition Officer (SLAO). In that light, it is submitted
that the Respondent - Municipal Corporation will not be able
to consider granting compensation in the form of Transferable
Development Rights (TDR) Certificates in lieu of monetary
compensation, but we are of the opinion that if an
appropriate direction is issued for considering such an
application that may be moved by the Petitioners for grant of
TDR Certificates, a further direction can be issued for
returning the monetary compensation pertaining to the shares
of the Petitioners from the SLAO to the Respondent -
Municipal Corporation and in view thereof, the TDR
Certificates can be issued. We are inclined to consider issuing
such directions in the light of the fact that due to the ad-
interim order passed by this Court on 09/10/2023, further
construction of the subject road has been hampered. This is
causing serious prejudice to the public at large.
4. The challenge raised in these petitions with regard to
alleged deviation from the alignment of the road as per the
development plan may be given up by the Petitioners if they
are adequately compensated by issuing TDR Certificates.
5. At the same time, we do find substance in the
contention of the learned counsel appearing for the
Respondent - Municipal Corporation that relevant rules and
regulations will have to be followed, while considering the
bipin prithiani
3
908-wp-12432.23 & anr.doc
applications that may be submitted by the Petitioners for grant
of TDR Certificates in lieu of monetary compensation. We are
informed that public notices for a specific period are required
to be issued for inviting objections, if any, in the light of
consideration of the applications that may be moved by the
Petitioners for grant of such TDR Certificates. The requisite
procedure will have to be followed, in accordance with law.
6. At this stage, the learned counsel for the Respondent-
Municipal Corporation is pressing for a direction to the
Petitioners to hand over possession of the subject land
forthwith, while their applications proposed to be filed for
TDR Certificates can be considered in accordance with law.
On the other hand, the learned Senior Counsel appearing for
the Petitioners submits that this Court may issue appropriate
directions for expeditious consideration of the proposals for
grant of TDR Certificates and that the ad-interim order may
not be varied.
7. In view of the above, the following directions are
issued:
(a) The Petitioners shall submit applications for grant of
TDR Certificates before the competent officer of the
Respondent- Municipal Corporation on or before
06/07/2026.
(b) The Respondent- Municipal Corporation shall
forthwith start processing the said applications in
accordance with the relevant rules and regulations.
(c) The process shall be completed by the Respondent –
Municipal Corporation at the earliest possible and in any
case within four weeks from 06/07/2026, while the actual
issuance of the TDR Certificates shall be kept in abeyance
till further orders by this Court.
(d) In the event, the Petitioners are required to obtain
certain documents from revenue authorities and other
officers of the Respondent – State, such authorities and
officers are directed to cooperate with the Petitioners, so
that the timeline indicated hereinabove can be complied
with.
bipin prithiani
4
908-wp-12432.23 & anr.doc
8. This Court shall consider disposing of the Petition on
the next date of hearing by issuing appropriate directions for
handing over of possession of the subject land to the
Respondent- Municipal Corporation in the light of the
developments that shall take place in pursuance of the
directions issued hereinabove.
9. List on 4th August 2026 to be included in the
supplementary list.
10. Ad-interim order shall continue to operate till the next
date.”
2. Thereafter, the hearing in these petitions was adjourned on
few occasions and eventually, it was indicated that the dispute
could be worked out amicably. The respondent-Municipal
Corporation is concerned with disposal of these writ petitions, at
the earliest, in the light of an ad-interim order dated 9 th October
2023, due to which construction of a road is hampered.
3. Although by these writ petitions, the petitioners, inter alia,
challenged the land acquisition award, in the light of the
observations made in the above quoted order dated 30 th June
2026, the petitioners are willing to accept Transferable
Development Rights (TDR)/Floor Space Index (FSI) in lieu of
monetary compensation.
4. It appears that the parties have been able to reach common
ground and in the light of the submissions made before this Court
today, the writ petition itself can be disposed of. It is to be noted
that the petitioners have indicated their willingness to surrender
the subject lands, subject to measurement exercise being completed
and thereupon, TDR being given to the petitioners, as
bipin prithiani
5
908-wp-12432.23 & anr.doc
compensation in lieu of monetary compensation, upon submission
of all necessary documents before the respondent-Municipal
Corporation.
5. In view of the above, the writ petitions are disposed in the
following terms :
(a) The monetary compensation of Rs.26,39,45,004/-
deposited by the respondent-Municipal Corporation with
the respondent-Special Land Acquisition Officer (SLAO)
shall be refunded to the respondent-Municipal
Corporation by the SLAO, with interest, if any, accrued
on the said amount.
(b) In view thereof, the respondent-Municipal Corporation
shall grant TDR to the petitioners, as per the provisions
of Section 126(1)(b) of the Maharashtra Regional and
Town Planning Act, 1966, proportionate to their share
against the area of lands, as per actual measurements,
concerning the subject lands. This would be subject to the
measurement exercise being completed within three
months and submission of all necessary documents by the
petitioners with the TDR proposal, in accordance with
law, before the respondent-Municipal Corporation.
(c) The petitioners shall hand over peaceful and
unencumbered possession of the subject lands, as per the
award, within a period of two weeks from today, in
bipin prithiani
6
908-wp-12432.23 & anr.doc
respect of which registered possession documents shall be
executed, in accordance with law.
6. In view of the above, the ad-interim order passed by this
Court, stands vacated.
7. It is made clear that this order is passed in the peculiar facts
and circumstances of the present case.
8. The petitioners would be at liberty to approach this Court in
case of any difficulty.
9. Pending applications, if any, also stand disposed of.