Bombay High Court
PEOPLES EDUCATION SOC THR ITS CHAIRMAN AND ANRversusSTATE OF MAHARASHTRA THR THE PRINCIPAL SECRETARY AND ORS
- Decided
- Disposal
- Disposed Off
Holding
The Court upheld the BCI's refusal to grant provisional approval, holding that the college must first remedy the identified deficiencies before approval can be considered for the next academic year.
Summary
The petitioners sought a direction compelling the Bar Council of India (BCI) to grant provisional approval for Yashwant Law College, Pune, to commence a three‑year LL.B. programme for the 2026‑27 academic year. The BCI had declined the application, citing various deficiencies in the new college and stating that approval could not be given until those were remedied. The petitioners highlighted that the State of Maharashtra and Pune University had already granted permission for the college to start in the same academic year. The Court examined the BCI’s statutory role in ensuring standards for legal education and found no infirmity in its decision to withhold approval. Consequently, the Court ordered the petition dismissed, allowing the college to rectify the deficiencies and re‑apply for approval for the 2027‑28 academic year, and kept the petition open for such a future application.
Issues considered
- Whether the Bar Council of India can lawfully refuse provisional approval for a new law college despite approvals from the State and the affiliating university.
- Whether the writ petition seeking immediate approval for the 2026‑27 academic year is maintainable.
Subjects
- Bar Council of India
- law college approval
- LL.B. programme
- academic year
- deficiencies
- state permission
- university affiliation
- writ petition
Judgment
902-WP 12690.2026.doc
Kavita S.J.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO.12690 OF 2026
People’s Education Society & Anr., ...Petitioners
Versus
State of Maharashtra & Ors., ...Respondents
----------
Mr. Prashant V. Malik for Petitioners.
Smt. Vaishali S. Nimbalkar, AGP for Respondent Nos. 1 & 2 – State.
Mr. Prasad L. Gajbhiye a/w Mr. Jayvrat Sakhare & Ms. Rutuja Joshi
for Respondent No. 4 – BCI.
Mr. Nikhil Chavan for Respondent No.5 – CET Cell.
Mr. Anandraj Ambedkar, Chairman of Petitioner No.2 present.
----------
CORAM : R.I. CHAGLA AND
FIRDOSH P. POONIWALLA, JJ.
DATE : 24th SEPTEMBER, 2026.
ORDER:
1. By this Petition, the Petitioner has sought direction to
Respondent No.4 - Bar Council of India (“BCI”) to forthwith consider
KAVITA
SUSHIL
JADHAV
and grant provisional approval to the Petitioner No.2 - Yashwant Law
Digitally
signed by
KAVITA
SUSHIL
JADHAV
Date:
2026.09.28
College, Yerwada, Pune (hereinafter referred to as “the said
14:01:18
+0530
College”), in respect of the Petitioners’ online application on the
official portal of Respondent No.4 - BCI, dated 8th September 2026,
1/3
902-WP 12690.2026.doc
bearing Reference No.YLC/2026-27/006, seeking approval for
commencement of the 3 Year LL.B. Course at the said College for
Academic Year 2026-27. Further consequential relief has been
sought.
2. Mr. Gajbhiye, learned Counsel appearing for Respondent
No.4 - BCI has referred to the fact that by a communication dated
14th September 2026, Respondent No.4 - BCI has not granted
approval citing various deficiencies on the part of the said College,
which is a new college. He has accordingly stated that the Petitioners
would be required to remove the deficiencies and without which
Respondent No.4 - BCI cannot grant approval for current Academic
Year 2026-2027.
3. Mr. Prashant Malik, learned Counsel appearing for the
Petitioners has pointed out that the Respondent Nos.1 and 2 - State
has granted permission to start the said College for Academic Year
2026-2027.
4. Respondent No.3 - Pune University, has also granted its
approval for starting the new college.
2/3
902-WP 12690.2026.doc
5. We do not find any infirmity in the decision taken by
Respondent No.4 - BCI in not granting the approval. The Petitioner
No.2 - College being a new College, is required to remove the
deficiencies and then only it may be allowed to start the said College
which can now only be for the next Academic Year viz. 2027-2028.
6. Accordingly, we dispose of the present Petition. We keep
it open for the Petitioners to apply to the Respondent Nos.1 and 2 –
State and Respondent No.3 – Pune University for granting approval
for the next Academic Year viz. 2027-2028 and upon such application
being made, the Respondents shall expeditiously decide the
application.
7. The Writ Petition is accordingly disposed of with no
order as to costs.
[ FIRDOSH P. POONIWALLA, J. ] [ R.I. CHAGLA, J. ]