Holding

The Court granted an extension of time till 30 September 2026 for the DRT to dispose of the pending securitisation application.

Summary

Petitioners filed a praecipe seeking an extension of time for the Debt Recovery Tribunal (DRT) in Mumbai to dispose of a pending securitisation application. The High Court had earlier ordered the DRT to decide the matter by 15 May 2026, but the hearing remained pending. The Court considered the request and, noting the delay, granted the DRT an extension until 30 September 2026 to dispose of the application. No further extensions were permitted. The praecipe was thereafter disposed of.

Issues considered

  • Whether the Debt Recovery Tribunal can be granted an extension of time to dispose of the pending securitisation application?

Subjects

  • extension of time
  • Debt Recovery Tribunal
  • securitisation
  • civil procedure
  • writ petition

Judgment

                                                                                                   P1_WPL5157_26.doc



                                       IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                            ORDINARY ORIGINAL CIVIL JURISDICTION
                                                WRIT PETITION (L) NO.5157 OF 2026

                              Rozina Firoz Hajiani and others                          …       Petitioners
                              Vs.
                              Union of India through Ministry of Corporate
                              Affairs and others                                       …       Respondents

                              Mr. Harsh Gutka for Petitioners.
                              Mr. Anup Khaitan for Respondent No.2-Bank.
                              Mr. Pratik Bakot i/b. Ms. Kruti Bhavsar for Respondent Nos.3 to 7.


                                                           CORAM : MANISH PITALE &
                                                                   SHREERAM V. SHIRSAT, JJ.
                                                           DATE       : AUGUST 04, 2026

                              P.C. :

                              .        Not on Board. Mentioned by way of praecipe seeking extension
                              of time for the Debts Recovery Tribunal - I, Mumbai (DRT) to dispose
                              of the pending securitisation application.

                              2.       By an order dated 18.03.2026, this Court had directed the pending
                              application to be disposed of on or before 15.05.2026. The learned
                              counsel for the parties inform this Court that the hearing is still pending
                              before the DRT.

                              3.       In view of the above, the DRT is granted extension of time till
                              30.09.2026 to dispose of the pending securitisation application. No
MINAL by
           Digitally signed
          MINAL

SANDIP Date:
       SANDIP PARAB


PARAB 2026.08.04
       17:33:11 +0530
                              further extension of time will be granted.

                              4.       The praecipe is disposed of.



                              (SHREERAM V. SHIRSAT, J.)                          (MANISH PITALE, J.)

                              Minal Parab                                                                       1/1


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.