Bombay High Court
MAHAMMED HASASN SHASTIKARversusTHE MUNICIPAL CORPORATION OF GREATER MUMBAI THROUGH THE COMMISSIONER
- Decided
- Disposal
- DISPOSED OFF
Holding
The court disposed the petition, directing the petitioner and Respondent No.5 to file regularisation applications within 15 days and the corporation to decide them within 60 days, keeping all contentions open.
Summary
Mahammed Hasan Shastikar filed a writ petition alleging that the Municipal Corporation of Greater Mumbai treated him differently by ordering demolition of his unauthorised mezzanine floor while other parties were favoured. The petitioners had not filed any application for regularisation of the structure, and the corporation had issued a notice under Section 351(1) and related provisions of the Mumbai Municipal Corporation Act, 1888, leading to an order for demolition. The court observed that the petitioner had not sought regularisation and that the corporation was willing to consider such applications if filed with requisite documents. It directed both the petitioner and the newly added Respondent No.5 to file regularisation applications within 15 days, and the corporation to decide them within 60 days, issuing a reasoned order. The petition was disposed, with all parties' contentions kept open for future determination.
Issues considered
- Whether the Municipal Corporation can order demolition of an unauthorised structure without the petitioner filing a regularisation application.
- Whether the petitioner is entitled to equal treatment compared to other respondents regarding regularisation.
- Whether the corporation must consider regularisation applications on their merits under the Mumbai Municipal Corporation Act.
Legislation cited
- Mumbai Municipal Corporation Act, 1888 — s. 351, 351(1), 352, 352A, 354A
Subjects
- municipal law
- building regularisation
- unauthorised structure
- equal treatment
- procedural fairness
- Mumbai Municipal Corporation Act
Judgment
Digitally
signed by
GAURI AMIT
GAURI GAEKWAD
909.WP-3576-2025.odt
AMIT Date:
GAEKWAD 2026.08.21
10:38:00
+0530 IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
WRIT PETITION NO.3576 OF 2025
Mahammed Hasan Shastikar ….Petitioner
Versus
The Municipal Corporation of
Greater Mumbai and Ors. ….Respondents
----
Mr. Ranjeev Carvalho a/w. Mr. Uzair Kaize and Ms. J. Pereira for
the Petitioner.
Mr. Ramdas Hake a/w. Ms. Sheetal Metakari for the Respondent,
the BMC.
Mrs. Varsha Sawant, AGP for Respondent No.3.
Mr. Aseem Naphade a/w. Mr. Zulfiqar Jariwala and Advocate
Maryam Borsadwala i/b. Jariwala Associates for Respondent No.5.
----
CORAM : RAVINDRA V. GHUGE, ACJ.
&
GAUTAM A. ANKHAD, J.
DATE : 20th AUGUST, 2026
P.C. :-
1. We have perused the ad-interim order passed by this
Court on 2nd September, 2024. Respondent No.5 was specifically
arrayed as a party by way of an amendment carried out by the
Petitioner, on the ground that the Corporation was leaning
favourably towards Respondent No.5 and that the Petitioner was
being singled out for action against an offending structure.
Gauri Gaekwad 1 of 4
909.WP-3576-2025.odt
2. Having considered the submissions of the learned
Advocates for the respective sides, it is now undisputed that the
Petitioner has not even moved an application for regularisation of
his mezzanine floor. After he received the impugned notice dated
2nd August, 2024, from the Corporation exercising powers under
Section 351(1) of the Mumbai Municipal Corporation Act, 1888,
and Sections 351, 352, 352A and 354A, an order dated 23rd August,
2024 was passed with regard to the unauthorised structure on the
entire first floor. The Petitioner’s grievance was that different
treatment was being meted out by the Corporation to different
persons.
3. Today, the learned Advocate for the Corporation
submits that, since the Petitioner did not tender any documents, the
impugned order was passed on 23rd August, 2024. If the Petitioner
files a proper application seeking regularisation, accompanied by
appropriate documents as are required to be considered while
dealing with such applications, the request for regularisation would
be considered on its own merits.
Gauri Gaekwad 2 of 4
909.WP-3576-2025.odt
4. Since the Corporation has made the above statement,
we grant the same liberty to the added Respondent No.5 to file an
application seeking regularisation, along with all relevant
documents which the party may desire to annex. The Corporation
would consider the applications of the Petitioner, as well as,
Respondent No.5, on their own merits, strictly in accordance with
law, and pass a reasoned order. The Corporation would refrain from
taking a shifting stand with regard to both these applications and
shall apply the same parameters as are required to be applied while
deciding such applications.
5. If these parties make such applications for
regularisation within a period of 15 days from today, the
Corporation would deal with the said applications within a period of
60 days thereafter and pass a reasoned order. We record the fact that
Respondent No.5 has, by himself, removed the offending structure.
His application would now be at par with the application of the
Petitioner and, if regularisation is granted to the Petitioner, the
added Respondent would then be at liberty to construct the
mezzanine floor as per the permission granted by the Corporation.
Gauri Gaekwad 3 of 4
909.WP-3576-2025.odt
6. In view of the above, this Petition is disposed off.
7. All contentions of all the parties are kept open.
(GAUTAM A. ANKHAD, J.) (ACTING CHIEF JUSTICE)
Gauri Gaekwad 4 of 4
Checking your session…