Bombay High Court
RAEES MADARSA AND WELFARE SOCIETY (MASJID)versusSTATE OF MAHARASHTRA THROUGH GP OS
- Decided
- Disposal
- DISPOSED OFF
Holding
The court held that it will not interfere with the demolition order already executed and directed the petitioner to seek the alternative site through the prescribed procedure under the Maharashtra Regional and Town Planning Act, 1966.
Summary
The petitioners, Raees Madarsa and Welfare Society, filed a writ petition under Article 226 seeking to quash and stay an order dated 23 June 2026 that authorized demolition of their madarsa under the Maharashtra Regional and Town Planning Act, 1966. The demolition had been carried out in 2018 after a notice under Section 53(1) and an alternative site was allotted in a notice dated 15 September 2025, which the petitioners failed to occupy, opting instead for unauthorised construction on the original site. The respondents argued that the Act is self‑contained and that any permission for reconstruction must follow the procedure in Section 45 of the Act. The Court, without delving into the merits, declined to interfere with the demolition already executed and directed the petitioners to apply for the alternative site within three months of the certified copy of the order. The writ petition was disposed, leaving the parties’ remaining contentions to be decided in appropriate proceedings.
Issues considered
- Whether the order dated 23 June 2026 authorising demolition can be quashed under Article 226.
- Whether a stay of the demolition order is warranted.
- Whether the petitioners are entitled to an alternative site without complying with the procedure under the Maharashtra Regional and Town Planning Act, 1966.
- Whether the court can interfere with demolition that has already been carried out.
Legislation cited
- Maharashtra Regional and Town Planning Act, 1966 — s. 45, 53(1)
Subjects
- Article 226
- demolition
- alternative site
- Maharashtra Regional and Town Planning Act
- self-contained statute
- unauthorised construction
Judgment
19-wp-3604-26.doc - corrected
INGALE
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Digitally signed
ORDINARY ORIGINAL CIVIL JURISDICTION
by URMILA
URMILA PRAMOD
INGALE
PRAMOD Date:
INGALE 2026.09.18
16:27:31
+0530 WRIT PETITION NO. 3604 OF 2026
Raees Madarsa and Welfare Society (Masjid) ...Petitioner
Versus
State of Maharashtra and ors. ...Respondents
...
Mr. A.N.Giri a/w Mr. Sagar Batavia, for the Petitioner.
Mr.Milind V. More, Addl. GP, for the Respondent No.1-State.
Mr. Akshay Shinde, for Respondents No. 2 & 3.
...
CORAM : MAHESH CHANDRA TRIPATHI, CJ.
& ADVAIT M. SETHNA, J.
DATE : 16th SEPTEMBER, 2026
P.C.:
1. We have heard learned counsel for the Petitioner,
learned AGP appearing for the Respondent No.1-State and
learned counsel for the Respondents No. 2 & 3.
2. The instant Writ Petition filed under Article 226 of
the Constitution of India is preferred seeking the following
substantive reliefs.
“a) That a writ of certiorari, writ of mandamus or any other
appropriate writ, order or direction be issued calling for the
records and after examining the legality and proprieties of the
proceeding order dated 23rd June, 2026 passed/issued by
respondent No.3 be quashed and set aside.
1
19-wp-3604-26.doc - corrected
b) Pending the hearing and final disposal of this writ petition
the operation of order dated 23rd June, 2026 passed/issued by
respondent No.3 be stayed.”
3. We find that while passing the order, initially notice was
served under Section 53(1) of the Maharashtra Regional and
Town Planning Act, 1966 (“the said Act of 1966”, for short)
indicating therein that in view of the Government of
Maharashtra Circular No. Petition/2014/No.219 (Part 4/UD-
20 dated 05/11/2016, instructions were issued to implement
the said proceedings as per time bound schedule. Whereas,
the subject Madarsa is located at G Block, Bandra East, Mouje
Kole Kalyan, Taluka, Andheri (opposite MTNL), fell within the
Costal Regulation Zone and was classified under ‘Category B’
for demolition.
4. Accordingly, the demolition has been carried out in the
year 2018 and admittedly, while issuing a Notice on
15/09/2025, it has also been indicated that in lieu thereof
Unit No. 08 in Building 19A of Hiranandani Mankhurd Colony
was allotted. Admittedly, alternative site has accorded. Instead
of occupying the said allotted site, the Petitioner indulged in
unauthorised construction at the initial/earlier site.
2
19-wp-3604-26.doc - corrected
4. Learned counsel for the Respondents, in this
background, raised the objection that the said Act of 1966 is a
self contained Act. Admittedly, the Notice has been issued and
later on, after carrying out demolition, the alternative site has
also been allotted. It is also admitted case that till date, no
such effort has been ever made to accord any such permission
for raising construction even though the exhaustive procedure
in this regard, is enshrined under the Section 45 of the said
Act of 1966. In case any such effort will be made, definitely, the
same can be initiated by the authority. During the midst of the
arguments, learned counsel for the Petitioner submits that till
date, alternate site has not been settled in favour of the
Petitioner.
5. Be that as it may. Without entering into merits of
the case, as actual demolition is carried out, at this stage, we
are not inclined to interfere with the issue of alleged
demolition. However, the Petitioner insists for alternative site.
It is always expected that an Application to that effect shall be
processed in the light of the Notice/Communication dated
15/09/2025 expeditiously, preferably, within a period of 3
3
19-wp-3604-26.doc - corrected
months from the date of production of certified copy of this
order.
6. The Writ Petition is Disposed Of in the above terms,
leaving all contentions of parties open to be decided in
appropriate proceedings.
[ADVAIT M. SETHNA, J.] [CHIEF JUSTICE]