Holding

The petition is disposed as the respondent has furnished a specific undertaking to carry out the development work within a reasonable time.

Summary

Merry Blessings Co‑op. Housing Society Ltd. filed a writ petition seeking an order directing the Brihanmumbai Municipal Corporation (BMC) and other respondents to carry out a change of a pipeline of about 1.20 metres in circumference. The respondents, particularly Respondent No.4, submitted a specific undertaking to the BMC that they would undertake the development work within a reasonable time and requested a three‑week period to complete it. The petitioners asked the Court to direct the BMC to inspect the site after completion and to ensure compliance with the undertaking. The Court noted the categorical undertaking already furnished by Respondent No.4 and found no need for further directions. Accordingly, the Court disposed of the writ petition, directing that the work be completed within the stipulated period and inspected by the BMC.

Issues considered

  • Whether the BMC and the other respondents are legally bound to carry out the pipeline alteration as claimed by the petitioner.
  • Whether the Court can dispose of the writ petition based solely on the specific undertaking furnished by a respondent.

Subjects

  • municipal corporation
  • co‑operative housing society
  • pipeline alteration
  • undertaking
  • writ petition
  • civil jurisdiction
  • BMC
  • development work

Judgment

                                                                          (18)-WP-4219-26.doc

       PANCHAL

                            IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                ORDINARY ORIGINAL CIVIL JURISDICTION
          Digitally
          signed by
          BALAJI
BALAJI    GOVINDRAO
GOVINDRAO PANCHAL
PANCHAL   Date:
                                   WRIT PETITION NO. 4219 OF 2026
          2026.10.01
          10:32:49
          +0530


                       Merry Blessings Co-op. Housing Society Ltd. ...Petitioner
                            Versus
                       Brihanmumbai Municipal Corporation
                       (BMC) & Ors.                                ...Respondents
                                                    ...
                       Mr. Ashutosh Gole i/by Mr. Amit Nikam & Mr. Rishikesh P.
                       More, for the Petitioner.

                       Ms. Sheetal Metakari i/by Ms. Komal Punjabi, for Respondent
                       Nos.1 & 2-BMC.

                       Smt. Fatima R. Lakadawala, AGP for the Respondent No.3-
                       State.

                       Mr. Mukesh Vashi, Senior Advocate a/w Ms. Manisha Desai
                       i/by M. P. Vashi & Associates, for Respondent Nos.4 & 5.

                       Mr. Santosh Shingade, S. E. (Maint.), K/West Ward – present.

                       Mr. Dayanand Patil, S. E. (SWD), W.S. - present.
                                                    ...

                                    CORAM : MAHESH CHANDRA TRIPATHI, CJ. &
                                            ADVAIT M. SETHNA, J.

                                      DATE : 30th SEPTEMBER, 2026.

                       P.C.:

                       1.        Learned Senior Advocate, Mr. Mukesh Vashi for

                       Respondent Nos.4 and 5, on instructions, submits that an

                       undertaking is already furnished by the Respondent No.4 to

                       the BMC that it is inclined to carry out the development work


                                                     1
                                                   (18)-WP-4219-26.doc


i.e. change of pipeline, which has a circumference of about

1.20 meters. Such work to be carried out by the Respondent

Nos.4 and 5 as per the requirement of the BMC within a

reasonable time, for which Mr. Vashi, learned Senior Counsel

would request for three weeks’ time.

2.         Once the work is complete, we expect the BMC

officials to inspect the site and submit a report to this Court

through their Advocate.

3.         As a   specific undertaking is already furnished by

the Respondent No.4 in this regard, we expect the same to be

complied with within four weeks. Moreover, after completion

of the said work, the Respondent-BMC may also inspect the

site so as to ascertain, whether the work is carried out

satisfactorily.

4.         Considering the facts as noted above, coupled with

the categorical undertaking furnished by the Respondent No.4,

Writ Petition is Disposed Of.




[ADVAIT M. SETHNA, J.]                      [CHIEF JUSTICE]




                                2


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.