Bombay High Court
SANJAY NAGARI SRA SAHAKARI GRUHA NIRMAN SANSTHAversusTHE CHIEF EXECUTIVE OFFICE SLUM REHABILITATION
- Decided
- Disposal
- Disposed Off
Holding
The petition is dismissed as the termination of the developer's appointment under Section 13(2) eliminates the cause of action, and the petitioner must seek other remedies for rent matters.
Summary
The petitioner, Sanjay Nagari SRA Sahakari Gruha Nirman Sanstha, filed a writ petition challenging actions of the Slum Rehabilitation Authority (SRA) after the SRA terminated the appointment of a developer under Section 13(2) of the Maharashtra Slum Areas (Improvement, Clearance and Redevelopment) Act, 1971. The petition also sought relief concerning pending rent and arrears of rent. The Court noted that the termination communication dated 8 April 2026 effectively removed the basis for the petition, leaving no matter for further consideration. It directed the petitioner to pursue appropriate remedies against the SRA's subsequent letter dated 5 May 2026 and to approach the Rent Committee for the rent issues. Consequently, the Court disposed of the petition without granting any relief.
Issues considered
- What is the effect of the SRA's termination of the developer's appointment under Section 13(2) on the petitioner's writ petition?
- Whether the petitioner can seek relief for pending rent and arrears of rent despite the termination?
- Whether the petition remains maintainable after the termination communication?
Legislation cited
Subjects
- termination of developer appointment
- Slum Rehabilitation Authority
- rent arrears
- Maharashtra Slum Areas Act
- writ petition
- rent committee
Judgment
17-WP-689-2026.doc
Digitally
signed by
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
PURTI
PURTI PRASAD
PRASAD PARAB
CIVIL APPELLATE JURISDICTION
PARAB Date:
2026.08.31
18:03:18
+0530
WRIT PETITION NO. 689 OF 2026
Sanjay Nagari SRA Sahakari Gruha Nirman
Sanstha … Petitioner
Versus
The Chief Executive Officer
Slum Rehabilitation Authority and Ors. ... Respondents
__________________________
Mr. Kunal Damle i/b Mr. J.P. Singh for the Petitioner.
Mr. Yash Bhat i/b Ms. Ravleen Sabharwal for the Respondent – SRA.
Mr. Chirag Balsara a/w Mr. Nikhil Wable i/b Jayakar & Partners for
Respondent Nos. 2 and 3.
Ms. S.D. Vyas, Addl. G.P. a/w Ms. V.s. Nimbalkar, AGP for the Respondent –
State.
__________________________
CORAM : M. S. KARNIK AND
SANDESH D. PATIL, JJ.
DATED : 31st AUGUST, 2026.
P.C. :
1. Learned Counsel for the Petitioner has placed on record a copy
of the communication dated 8th April, 2026 received from SRA terminating
the appointment of the developer under Section 13(2) of the Maharashtra
Slum Areas (Improvement, Clearance and Redevelopment) Act, 1971. In
view of such communication nothing survives for further consideration in
this Petition.
2. The learned Counsel for the Respondent No.2 placed on
Purti Parab 1/2
17-WP-689-2026.doc
record a copy of the letter dated 5 th May, 2026 addressed by the SRA to the
Petitioner. In the light of the subsequent development, it is open for the
Petitioner to take appropriate remedies against the communication dated
5th May, 2026 in accordance with law.
3. So far as the pending rent and arrears of rent are concerned it
is open for the Petitioner to seek appropriate remedies including
approaching the Rent Committee which has been constituted pursuant to
the orders passed by this Court. The SRA to proceed further in accordance
with law.
4. The Petition is accordingly disposed of.
(SANDESH D. PATIL, J.) (M. S. KARNIK, J.)
Purti Parab 2/2