Bombay High Court
KHAN AYESHA SIDDIQA ABUBAKARversusSTATE OF MAHARASHTRA THRU G P AND ORS
- Decided
- Disposal
- Disposed Off
Holding
The Court ordered the petitioner to produce the required documents by 9 June 2026, failing which the petitioner must demolish the structure himself within a week, and the petition was disposed accordingly.
Summary
The petitioner, Khan Ayesha Siddiqa Abubakar, filed a civil writ petition challenging the demolition of a structure. The Court directed the petitioner to produce documents proving the structure's legality before the Tahsildar and Executive Magistrate by 9 June 2026. Upon receipt, the respondent authority must decide the matter within two weeks, during which no coercive action can be taken. If the petitioner fails to produce the documents, he must demolish the structure himself within one week of the deadline, failing which the competent authority may demolish it. The petition was disposed subject to these terms.
Issues considered
- Whether the petitioner must produce documents establishing the legality of the subject structure.
- What are the consequences if the petitioner fails to produce the required documents?
Subjects
- civil writ petition
- demolition
- unauthorized structure
- compliance order
- procedural direction
Judgment
P.H. Jayani 19 WP6931.2026.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
CIVIL WRIT PETITION NO. 6931 OF 2026
Khan Ayesha Siddiqa Abubakar …. Petitioner
Vs.
The State of Maharashtra and Ors. …. Respondent
Mr. Abdul Azim Shaikh for the Petitioner.
Shri. V.D. Badgujar, AGP for Respondent Nos.1 to 3 – State.
CORAM : SHYAM C. CHANDAK AND
FARHAN P. DUBASH, JJ.
DATED : 03rd JUNE, 2026
(VACATION COURT)
P.C. :-
1) After hearing the Petition for some time, Mr. Badgujar, the
learned AGP, on instructions, submitted that let the Petitioner produce the
relevant documents establishing his contention that the subject matter
structure is authorized and legal. Upon production of such documents, the
Respondent No.2 – The Tahsildar and Executive Magistrate, Kalyan, Dist.
Thane shall examine the matter and dispose of the same in accordance with
the law.
2) Mr. Shaikh, learned Counsel for the Petitioner, on instructions
states that the Petitioner will produce the required documents before the
Respondent No.2 on or before 9th June, 2026.
3) Once the Petitioner produces the documents within stipulated
period as stated above, Respondent No.2 shall decide the matter within two
1/2
P.H. Jayani 19 WP6931.2026.doc
weeks therefrom. During the said two-week period, no coercive action shall
be taken against the Petitioner.
4) Mr. Shaikh, the learned Counsel for the Petitioner, on
instructions, agreed that if the Petitioner fails to produce the documents as
aforesaid, the Petitioner shall demolish the subject matter structure himself
within one week from 9th June, 2026. The said statement is accepted.
4.1) Otherwise, the Competent Authority will be at liberty to take
necessary measures to demolish the subject structure in accordance with the
law.
5) Petition stands disposed of in aforesaid terms.
(FARHAN P. DUBASH, J.) (SHYAM C. CHANDAK, J.)