Holding
The Court ordered the petitioner to produce the required documents by 9 June 2026 and set a two‑week decision period for the Tahsildar, failing which the petitioner must demolish the structure himself.
Summary
Petitioner Abdul Fazal Khan filed a civil writ petition challenging the demolition of a structure. The Court directed the petitioner to produce documents proving the structure’s legality before the Tahsildar and Executive Magistrate of Kalyan by 9 June 2026. The Tahsildar was instructed to examine the documents and decide the matter within two weeks, during which no coercive action could be taken against the petitioner. If the petitioner fails to produce the documents, he must demolish the structure himself within one week of 9 June 2026, otherwise the competent authority may demolish it. The petition was disposed subject to these terms.
Issues considered
- What procedural steps must the petitioner follow to establish the legality of the structure before demolition?
Subjects
- civil writ petition
- demolition
- illegal structure
- procedural compliance
- high court order
Judgment
P.H. Jayani 20 WP6933.2026.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
CIVIL WRIT PETITION NO. 6933 OF 2026
Abdul Fazal Khan …. Petitioner
Vs.
The State of Maharashtra and Ors. …. Respondents
Mr. Abdul Azim Shaikh for the Petitioner.
Shri. V.D. Badgujar, AGP for Respondent Nos.1 to 3 – State.
CORAM : SHYAM C. CHANDAK AND
FARHAN P. DUBASH, JJ.
DATED : 03rd JUNE, 2026
(VACATION COURT)
P.C. :-
1) After hearing the Petition for some time, Mr. Badgujar, the
learned AGP, on instructions, submitted that let the Petitioner produce the
relevant documents establishing his contention that the subject matter
structure is authorized and legal. Upon production of such documents, the
Respondent No.2 – The Tahsildar and Executive Magistrate, Kalyan, Dist.
Thane shall examine the matter and dispose of the same in accordance with
the law.
2) Mr. Shaikh, learned Counsel for the Petitioner, on instructions
states that the Petitioner will produce the required documents before the
Respondent No.2 on or before 9th June, 2026.
3) Once the Petitioner produces the documents within stipulated
period as stated above, Respondent No.2 shall decide the matter within two
1/2
P.H. Jayani 20 WP6933.2026.doc
weeks therefrom. During the said two-week period, no coercive action shall
be taken against the Petitioner.
4) Mr. Shaikh, the learned Counsel for the Petitioner, on
instructions, agreed that if the Petitioner fails to produce the documents as
aforesaid, the Petitioner shall demolish the subject matter structure himself
within one week from 9th June, 2026. The said statement is accepted.
4.1) Otherwise, the Competent Authority will be at liberty to take
necessary measures to demolish the subject structure in accordance with the
law.
5) Petition stands disposed of in aforesaid terms.
(FARHAN P. DUBASH, J.) (SHYAM C. CHANDAK, J.)