ABHIJIT A. DUDWADKARversusSTATE OF MAHARASHTRA THROUGH GOVT. PLEADER

Decided
Disposal
DISPOSED OFF

Holding

The court directed the Assistant Engineer (TP), G/South Ward Office of MCGM to decide the petitioner's eligibility representation within eight weeks and disposed of the petition.

Summary

The petitioner, an occupant of a hut slated for demolition under a Letter of Intent issued by the Deputy Chief Engineer of the Slum Rehabilitation Authority (S.R.A.), sought a declaration of his eligibility for accommodation as mandated by clause 14 of that letter. He filed a writ petition challenging the demolition and requesting the Municipal Corporation of Greater Mumbai (MCGM) to decide his eligibility. The court examined the terms of the Letter of Intent, particularly the requirement to accommodate huts cut along the demarcated plot boundary. Finding that the relief sought required a determination by the competent municipal authority, the court directed the Assistant Engineer (TP) of the South Ward Office, MCGM, to decide the petitioner's representation within eight weeks. The petition was thereafter disposed of.

Issues considered

  • Whether the petitioner is eligible for accommodation of the hut being cut as per clause 14 of the Letter of Intent dated 3 November 2007.
  • Whether the court may direct the municipal authority to decide the petitioner's representation within a specified time.

Subjects

  • Writ Petition
  • Housing Rehabilitation
  • Municipal Corporation
  • Eligibility
  • Demarcation
  • Slum Rehabilitation Authority
  • Letter of Intent

Judgment

                                                          34. WP 699-2024.doc

              IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                  ORDINARY ORIGINAL CIVIL JURISDICTION

                       WRIT PETITION NO.699 OF 2024

Abhijit A. Dudwadkar                        …     Petitioner
          Versus
State of Maharashtra
Through Government Pleader                  …     Respondent

                                  …..
Adv. Aseem Naphade a/w Adv. Haamid Ahmad for Petitioner.
Smt. Vrushali Kabre, A.G.P. for Respondent No.1-State.
Adv. Yashi Bhatt i/b Mr. Ravleen Sabharwal for Respondent-S.R.A.
Ms. Jyoti Mhatre i/b Smt. Komal Punjabi for Respondent No.3-
MCGM.
                                  …..

                                 CORAM: M.S. KARNIK &
                                        SANDESH D. PATIL, JJ.

                                 DATED : 16th SEPTEMBER 2026
P.C.

1.         Heard learned Counsel for the Petitioner as well as for S.R.A.

and MCGM.


2.        The learned Counsel for the Petitioner has invited our attention

to the Letter of Intent dated 3 rd November 2007, issued by Deputy

Chief Engineer, S.R.A. Clauses 13 and 14, reads thus :-




RaJesh Chittewan, PS                                                       1/3
                                                                    34. WP 699-2024.doc

        “13. That you shall get the plot boundaries demarcated and the
             compound wall shall be constructed prior to commencing
             building works and the same shall be certified by the concerned
             Architect before requesting for C.C. beyond the plinth level.


        14. That you shall accommodate the huts getting cut along with the
             boundary of the plot demarcated by the staff of the City survey
             office.”


3.        The learned Counsel submits that the Petitioner is one of the

occupants of the hut which was getting cut along the boundary of the

plot demarcated by the staff of the City Survey Office in terms of

clause 14.


4.        The Petitioner, therefore, through his Advocate made a

representation to the MCGM as well as S.R.A. for deciding his

eligibility.


5.        Considering the nature of relief in the Petition, we direct the

Competent Authority, i.e. the Assistant Engineer (TP), G/South Ward

Office of the MCGM to decide the representation dated 20 th

September 2023, which is at page 117 of the Petition, and in any

case within a period of eight weeks of date of communication of this

Order.




RaJesh Chittewan, PS                                                                 2/3
                                                     34. WP 699-2024.doc

6.        The Petition stands disposed of.



(SANDESH D. PATIL, J.)                       (M.S. KARNIK, J.)




RaJesh Chittewan, PS                                                  3/3
                  Digitally signed
RAJESH            by RAJESH
                  VASANT
VASANT            CHITTEWAN
CHITTEWAN         Date: 2026.09.17
                  13:22:24 +0530


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

Lawyer court records for this case

Associated through the court’s case reference.

For a signed copy suitable for filing, refer to the court's website.