Bombay High Court
INDURI FARMS PRIVATE LIMITEDversusNAKUBAI BARKU VAJE SINCE DECD. THR HEIRS
- Decided
- Disposal
- Disposed Off
Holding
The SDO exceeded his jurisdiction; the order setting aside the mutation entry is quashed and the matter is remitted for proper consideration of the condonation of delay application.
Summary
The petitioner sought to enforce a mutation entry recorded in 1966, which the respondents challenged in 2025 after a 58‑year delay under Section 247 of the Maharashtra Land Revenue Code, 1966. The respondents filed an appeal and applied for condonation of the delay, while the Sub‑Divisional Officer (SDO) used powers under Sections 3 and 4 of the Maharashtra Restoration of Lands to Scheduled Tribes Act, 1974 to set aside the mutation entry without giving notice to the petitioner. The petitioner contended that the SDO had no jurisdiction to exercise suo‑moto powers under the Act in a matter limited to condonation of delay and that the petitioner was not afforded a hearing. The court held that the SDO had exceeded his jurisdiction, as no application under the 1974 Act was filed and no notice was issued, and therefore quashed the impugned order. The matter was remitted to the appropriate authority to consider the condonation application afresh, and the writ petition was disposed.
Issues considered
- Whether the Sub‑Divisional Officer can exercise suo‑moto powers under the Maharashtra Restoration of Lands to Scheduled Tribes Act, 1974 (Sections 3 and 4) without notice in a proceeding limited to condonation of delay under Section 247 of the Maharashtra Land Revenue Code.
- Whether a delay of 58 years in challenging a mutation entry can be condoned.
- Whether the SDO exceeded his jurisdiction by setting aside the mutation entry without following the procedural requirements of the 1974 Act.
Legislation cited
Subjects
- mutation entry
- land revenue
- condonation of delay
- jurisdiction
- suo moto power
- Scheduled Tribes Act
- writ petition
- land restoration
Judgment
Gitalaxmi 26-WP-9441-2026.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION
WRIT PETITION NO. 9441 OF 2026
INDURI FARMS PRIVATE LIMITED ...PETITIONER
Versus
NAKUBAI BARKU VAJE SINCE DECD. THROUGH
HEIRS AND ANOTHER ...RESPONDENTS
Mr. Birendra Saraf, Sr. Counsel a/w Mr. Omar Ahmad, Mr.
Vikram Shah, Ms. Gauri Joshi & Mr. Tuhin Dubey i/b Ganesh
& Co., learned counsels for the Petitioner.
Mr. Divyesh K. Jain, learned counsel for the Respondents.
S. L. Babar, learned AGP for the State-Respondent.
CORAM : ARUN R. PEDNEKER, J.
DATE : 7th SEPTEMBER, 2026.
Per Court :
1. Heard learned counsel appearing for the parties.
2. Mr. Birendra Saraf, learned senior counsel for the Petitioner
submits that the mutation entry made in the year 1966 has been
challenged by the Respondents in the year 2025, i.e. after a period of
58 years, under Section 247 of the Maharashtra Land Revenue Code,
1966 (“MLRC”).
Page 1 of 4
7th SEPTEMBER, 2026
Gitalaxmi 26-WP-9441-2026.docx
3. In the appeal preferred by the Respondents, an application
for condonation of delay of 58 years has been filed, and the said
application was under consideration. The arguments before the
Appellate authority were restricted to the reasons of condonation of
delay. It is the case of Petitioner that the delay of 58 years should
not be condoned in challenging the mutation entry.
4. Learned senior counsel for the Petitioner submits that the
SDO has decided the appeal by exercising powers under the
provisions of Sections 3 and 4 of the Maharashtra Restoration of
Lands to Scheduled Tribes Act, 1974, (“the Act”) and the mutation
entry in favour of the Petitioner has been set aside. In this regard,
learned senior counsel for the Petitioner submits that there was no
application under the Act, so also suo moto powers under the Act
cannot be exercised without notice and enquiry. The Petitioner was
also not put to notice of exercise of the powers under the Act. The
proceedings pending before the Sub-Divisional Officer (“SDO”)
related to the mutation entry entered in the year 1966 and the
application for condonation of delay was under consideration.
5. Learned senior counsel for the Petitioner submits that while
considering the application for condonation of delay, there was no
occasion for the SDO to exercise powers under the Act.
6. Per contra, Mr. Divyesh Jain, learned counsel for the
Respondents submits that the SDO has jurisdiction to exercise
Page 2 of 4
7th SEPTEMBER, 2026
Gitalaxmi 26-WP-9441-2026.docx
powers under the provisions of Act, particularly under Sections 3 and
4 of the Act and such powers can be exercised suo moto or an
application and that the authority concerned has rightly exercised the
powers within 30 years from the year 2004.
7. Having perused the records, it appears that the application
is filed challenging the mutation entry of the year 1966 and the
proceedings before the SDO is related to the condonation of delay
alone. The arguments canvassed by the parties are also related only
to the condonation of delay. There is no application for exercise of
powers under the provisions of Act. As such, the concerned authority
could not have never travelled beyond the application invoking the
same, without appropriate notice to the Petitioner. The concerned
authority could have either condoned the delay on its merits or
dismissed the application for condonation of delay. The SDO has not
issued any notice under the Act.
8. Considering the same, this Court finds that the SDO has
exceeded his jurisdiction and pass the impugned order and
accordingly, the impugned order is quashed and set aside and the
matter is remitted back to the concerned authority. The authority
concerned to consider the arguments on delay condonation
application and pass the appropriate orders thereon. In the event the
SDO condones the delay, he may admit the appeal for hearing.
Page 3 of 4
7th SEPTEMBER, 2026
Gitalaxmi 26-WP-9441-2026.docx
9. With these observations, the present Writ Petition stands
disposed of.
[ ARUN R. PEDNEKER, J. ]
Digitally signed
by GITALAXMI
GITALAXMI KRISHNA
KRISHNA KOTAWADEKAR
KOTAWADEKAR Date:
2026.09.12
13:22:27 +0530
Page 4 of 4
7th SEPTEMBER, 2026
Checking your session…