The Court held that the necessary steps have been taken to effect possession and therefore disposed of the petition without further directions.

Summary

Edelweiss Asset Reconstruction Company Ltd., a secured creditor, filed a writ petition seeking enforcement of an order dated 7 August 2026 directing that physical possession of a secured asset be handed over to it. The petition raised a grievance that the Court Commissioner’s request for police assistance to take possession had not been acted upon. The learned Additional Government Pleader informed the Court that police officers had initially been unable to take possession, but after the August 7 order, they provided assistance and secured possession on 14 August 2026. The Court examined whether the steps taken satisfied the grievance raised by the Court Commissioner. Satisfied with the AGP’s statement, the Court held no further directions were required and disposed of the petition.

Issues considered

  • Whether appropriate steps have been taken with respect to the grievance raised by the Court Commissioner regarding possession of the secured asset
  • Whether the petitioner is entitled to physical possession of the secured asset as directed in the order dated 7 August 2026

Subjects

  • secured creditor
  • possession of secured asset
  • Court Commissioner
  • police assistance
  • writ petition
  • disposal

Judgment

                                   bipin prithiani
                                                                      1
                                                                                          905-wp-9614.26.doc

                                           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                                   CIVIL APPELLATE JURISDICTION

                                                     WRIT PETITION NO. 9614 OF 2026

                                   Edelweiss Asset Reconstruction Company Ltd. …         Petitioner
                                        Versus
                                   The State of Maharashtra & Ors.             …         Respondents
                                                               ******
                                   Ms. Priyanka Fadia (through V.C.) i/by Mr. Shashank N. Fadia for
                                   Petitioner.
                                   Mrs. G. R. Raghuwanshi, AGP for Respondent-State.
BIPIN
DHARMENDER
PRITHIANI
             Digitally signed by
             BIPIN DHARMENDER
             PRITHIANI
             Date: 2026.09.02
                                                               ******
                                                          CORAM : MANISH PITALE AND
             10:54:29 +0530




                                                                     SHREERAM V. SHIRSAT, JJ.

                                                             DATE     : 1st SEPTEMBER 2026

                                   P.C. :

                                   .         In the order dated 20th August 2026 we had already
                                   recorded the statements made on behalf of the petitioner (secured
                                   creditor) that physical possession of the secured asset was handed
                                   over to the petitioner, as per directions contained in the order
                                   dated 7th August 2026.

                                   2.        We have kept this petition today for the learned AGP to
                                   inform this Court that as to whether appropriate steps had been
                                   taken with regard to the grievance raised by the Court
                                   Commissioner.

                                   3.        The learned AGP, on instructions, informs this Court that
                                   the concerned police officers had taken steps in the matter, at the
bipin prithiani
                                   2
                                                        905-wp-9614.26.doc

request made by the Court Commissioner, but on earlier dates,
physical possession could not be taken. It was further submitted
that after the order dated 7th August 2026 was passed, the police
officials provided adequate assistance to the Court Commissioner,
as a consequence of which, possession of the secured asset was
taken on 14th August 2026.

4.        In the light of the statement made by the learned AGP, we
are satisfied that no further directions are necessary in this
petition. Accordingly, the petition is disposed of. Pending
applications, if any, also stand disposed of.



  (SHREERAM V. SHIRSAT, J.)                     (MANISH PITALE, J.)


Continue reading with your account

Sign in to read the full judgment. It’s free.

Sign in to read

Checking your session…

For a signed copy suitable for filing, refer to the court's website.