AKSHAY & ANR.versusADITYA & ORS.
- Citation
- 2024 INSC 657
- Decided
- 29 August 2024
- Disposal
- Dismissed
Holding
The appellants remain jointly and severally liable for the builder’s acts under the irrevocable Power of Attorney until its lawful termination, as the JVA was not revoked and the revocation letter only affected liability thereafter.
Summary
The appellants, owners of a parcel of land, entered into a Joint Venture Agreement (JVA) and an irrevocable Power of Attorney (IPA) dated 6‑July‑2013 in favour of Respondent No.2, a builder, to develop the land and construct flats. The builder subsequently sold units to the complainants and the complainants filed consumer complaints alleging deficiency in service and seeking joint and several liability of both the landowners and the builder to complete construction and execute sale deeds. The State Consumer Disputes Redressal Commission held the appellants and the builder jointly liable, an order affirmed by the National Consumer Disputes Redressal Commission. The appellants argued that they had revoked the IPA by a letter dated 12‑August‑2014 and therefore should not be liable for the builder’s acts. The Supreme Court examined whether the revocation was effective, noting that the JVA remained in force and the revocation letter only sought to limit liability “henceforth”, while the builder’s contracts with the complainants were entered into before the revocation. The Court held that the appellants remained bound by the builder’s acts under the irrevocable Power of Attorney until its lawful termination and upheld the lower courts’ orders. Consequently, the appeals were dismissed.
Issues considered
- Whether the landowner appellants are bound by the acts of the builder performed under an irrevocable Power of Attorney that was purportedly revoked by a letter of revocation.
- Whether the Joint Venture Agreement, which was not revoked, continues to impose joint and several liability on the appellants for deficiency in service.
- Whether the consumer complaints are maintainable against the landowners under the Consumer Protection Act, 1986.
Legislation cited
Subjects
Judgment
[2024] 8 S.C.R. 847 : 2024 INSC 657
Akshay & Anr.
v.
Aditya & Ors.
(Civil Appeal Nos. 3642-3646 of 2018)
29 August 2024
[Bela M. Trivedi and Satish Chandra Sharma, JJ.]
Issue for Consideration
Appellants-landowners executed a Joint Venture Agreement and
an irrevocable power of attorney in favour of the Respondent
No.2-builder for the development of the land and construction
of flats. Respondent No.2 entered into sale agreements with the
complainants-respondents for the units in question. Complaints
filed by the respondents against the appellants and Respondent
No.2 inter alia for declaration that they were guilty of deficiency
in service and were jointly and severally liable to complete the
construction as per the terms and conditions agreed between the
parties and put the complainants in possession of the properties
after completing the construction as also to execute the registered
sale deeds in respect thereof. Complaints allowed by the State
Commission. Order upheld by NCDRC. Whether the appellants
were bound by the acts of the Respondent No.2 carried out pursuant
to the irrevocable Power of Attorney till it was terminated.
Headnotes†
Consumer Dispute – Deficiency in service – Non-compliance
of the terms and conditions of Joint Venture Agreement
(JVA) by Respondent No.2-builder – Appellants-landowners
and the Respondent No.2-builder, if were jointly and severally
liable as held by State Commission and upheld by NCDRC:
Held: Yes – Though allegedly the power of attorney was revoked
by the appellants by the letter of revocation, the JVA was not
revoked and it continued to be in force – In the revocation letter,
the appellants had stated to be not liable “Henceforth”, i.e after
the said letter was sent – Thus, the appellants were bound by the
acts/deeds of the Respondent No.2 carried out pursuant to the
irrevocable Power of Attorney till it was terminated, in accordance
with law – Appellants liable for the acts of Respondent No.2 –
Judgment of NCDRC not interfered with. [Paras 8, 9]
848 [2024] 8 S.C.R.
Digital Supreme Court Reports
List of Acts
Consumer Protection Act, 1986.
List of Keywords
Consumer Dispute; Joint Venture Agreement; Power of attorney;
Irrevocable power of attorney; Landowners; Development of
the land; Construction of flats; Deficiency in service; Jointly and
severally liable; Power of attorney revoked; Revocation letter;
“Henceforth”.
Case Arising From
CIVIL APPELLATE JURISDICTION : Civil Appeal Nos. 3642-3646
of 2018
From the Judgment and Order dated 28.11.2017 of the National
Consumers Disputes Redressal Commission, New Delhi in FA Nos.
1664-1668 of 2017
Appearances for Parties
Kailash Vasdev, Sr. Adv., R. Mohan, V. Balaji, Asaithambi MSM, B.
Dhananjay, S. Devendran, Limrao Singh Rawat, Rakesh K. Sharma,
Advs. for the Appellants.
Siddhartha Dave, Sr. Adv., Piyush Singhal, Bijnender Singh, Praveen
Swarup, Alekhya Shastry, Ms. Arundati Mukherjee, Ms. Amita Singh
Kalkal, Abhinav Ramkrishna, Advs. for the Respondents.
Judgment / Order of the Supreme Court
Judgment
1. This set of five Appeals arises out of the common Judgment
and Order dated 28-11-2017 passed by the National Consumer
Disputes Redressal Commission, New Delhi (here-in-after, referred
to as “NCDRC”) in First Appeal Nos.1664-1668 of 2017, whereby
the NCDRC has dismissed the said Appeals filed by the present
appellants challenging the Judgment and Order dated 10-7-2017
passed by the Maharashtra State Consumer Disputes Redressal
Commission, Circuit Bench, Nagpur (here-in-after, referred to as
“State Commission”) in a Consumer Complaint No. 85 of 2015.
[2024] 8 S.C.R. 849
Akshay & Anr. v. Aditya & Ors.
2. The appellants – herein are the owners of the land in question. They
entered into a Joint Venture Agreement with Respondent No.2 –
Glandstone Mahaveer Infrastructure Pvt. Ltd. for the development of
the land and for construction of flats as mentioned herein. It appears
that the appellants also executed Irrevocable Power of Attorney dated
6-7-2013 in favour of Respondent No.2 with regard to the said land.
The Respondent No.2 on the basis of the said documents, entered
into the sale agreements with the respondents – complainants for
the units in question.
3. The respondents – complainants filed the complaints before the ‘State
Commission’ under Section 17 of the Consumer Protection Act, 1986
against the present appellants and Respondent No.2 seeking inter
alia the declaration that the present appellants and the Respondent
No.2 were jointly and severally involved in the unfair trade practices
and were guilty of deficiency in service, that they were jointly and
severally liable to complete the activities and construction as per the
terms and conditions agreed upon between the parties and put the
complainants in possession of the properties mentioned in Schedule
‘D’ after completing the construction as also to execute the registered
sale deeds in respect thereof.
4. The ‘State Commission’ after considering the pleadings of the parties
allowed the said complaints. The ‘State Commission’ holding opponent
Nos.1 to 3 (the present appellants and Respondent No.2) liable
for the completion of the construction of dwelling units as per the
agreement with the complainants and passed the following order:-
“i. The complaints as referred Nos. CC/15/85, CC/15/86,
CC/15/99, CC/15/100 & CC/15/111 are partly allowed.
ii. The OP Nos. 1,2&3 to provide the possession of the
dwelling unit agreed in Agreement to Sell (SA) with
each complainant in the span of six months from
the date of the receipt of copy of this order and the
complainants to pay the entire consideration of the
dwelling unit as per the stages and the final amount
at the time of sale deed and possession as per the
agreement.
iii. The OP Nos. 1,2,&3 after completion of construction
of dwelling units as per agreement to sell & on
850 [2024] 8 S.C.R.
Digital Supreme Court Reports
receiving full consideration as per agreement as
above, shall execute sale deed of respective dwelling
units as per agreement to respective complainant.
The complainants shall bear expenses for execution
and registration of sale deeds.
iv. The O.P. Nos.2&3 to cooperate with O.P. No.1 in the
compliance of trhe agreement signed by the O.P.
No.1 with the complainants as per the conditions of
the Joint Venture Agreement (JVA) and (Irrevocable
Power of Attorney (IPA).
v. The O.P. No.1 to provide the compensation of
Rs.1,00,000/- to each of complainant for physical
and mental harassment in the span of one month
from the date of receipt of copy of this order and on
failure, to pay interest at the rate of 9% p.a. upon it,
till the final payment.
vi. The O.P.No.1 to provide the cost of Rs.10,000/- to
each of the complainant in the span of 30 days from
the date of the receipt of copy of this order & on
failure to pay interest upon it at the rate of 9% p.a.,
till final payment.
vii. No order against O.P.No.4
viii. Copy of the order be provided to both the parties,
free of cost.”
5. Being aggrieved by the said order, the present appellants, preferred
the First Appeals before the `NCDRC’, which came to be dismissed
by the `NCDRC’ vide the impugned common order holding as under:-
“8. The State Commission have brought out in their order
that the Joint-Venture Agreement (JVA) and the Irrevocable
Power of Attorney (IPA) were prepared on 06.07.2013. As
per condition No.15 of the said agreement, the builder had
been given the authority to sell the constructed Units on
the property. The IPA also authorised the OP-1 builder to
execute the registered sale deeds etc. and receive the
consideration. The State Commission, further, observed
that the present appellants/OP-2 and 3 had issued notice,
[2024] 8 S.C.R. 851
Akshay & Anr. v. Aditya & Ors.
by which they claimed that they had cancelled the JVA
and the IPA. However, the said notice was issued on
12.08.2014, which was much after the agreement made
by the OP-1 with the complainants. The State Commission
concluded that at the time of the agreement between the
builder and the complainants, the JVA and IPA were very
much operative. It is evident, therefore, that the appellants
cannot wash their hands off from the matter, as it would
result in grave injustice to the complainants consumers.
9. At the time of hearing also in these appeals, the learned
counsel for the appellants was asked that in case the plea
taken by them in the appeals were accepted, how shall
it be possible to safeguard the interests of the consumer,
who had invested in the said project, after looking at the
agreement between them and the OP-1 builder. However,
no satisfactory reply could be given by the appellants on
that score. It is made out, therefore, that the interests of
the complainants/ consumers shall be heavily jeopardised,
if the plea of the appellants/OP-2 and 3 is accepted.
10. The appellants have referred to the orders made by the
Hon’ble Supreme Court in the case, Faqir Chand Gulati
vs. Uppal Agencies Pvt. Ltd. & Anr., (2008) 10 SCC 345
and in the case, Sunga Daniel Babu vs. Sri Vasudeva
Constructions & Ors., (2016) 8 SCC 429, in support of
their arguments before the State Commission as well as
this Commission. I, however, agree with the contention of
the State Commission that these two judgments are not
applicable in the present cases. In the said judgments, it
was concluded that a landowner, who was supposed to
be provided a portion of the devloped property after the
development made by the builder, was a consumer vis-a-
vis the builder. The issue in the present case is, however,
different, as the present complaints have been filed by
the complainants against the builder as well as the land
owners/appellants. The orders made by the Hon’ble Apex
Court are, therefore not applicable in the present cases.
11. From the discussion above, it is held that the appellants/
OP-2 and 3 landowners cannot be allowed to escape their
852 [2024] 8 S.C.R.
Digital Supreme Court Reports
responsibility/role in the matter of providing relief to the
complainants/consumers in terms of the impugned order
passed by the State Commission. It is held, therefore, that
the impugned order does not suffer from any illegality,
irregularity or jurisdictional error of any kind and the
same is upheld. The present appeals are ordered to be
dismissed in limine.”
6. It is vehemently submitted by the learned Senior counsel – Mr.
Kailash Vasdev that the appellants had already revoked the Power
of Attorney executed by them in favour of Respondent No.2, by the
letter of revocation dated 12-8-2014, coupled with Public Notice of
the same date and hence the appellants could not be held liable
for any act done by Respondent No.2, who had allegedly entered
into agreements with the complainants. He also submitted that
the Complaints as such are not maintainable under the Consumer
Protection Act against the appellants, who were not privy to the
agreement between the Respondent No.2 and the complainants.
However, the learned Senior counsel – Mr. Siddhartha Dave for the
Respondent No.2 submitted that the said respondent is still ready to
honour the JVA entered into by the appellants and Respondent No.2
and ready to complete the construction work with the cooperation of
the appellants. He further submitted that the Irrevocable Power of
Attorney was executed by the appellants in favour of Respondent
No.2 after receiving consideration of Rs.1.51 Crores, pursuant to
which, the Respondent No.2 had entered into the agreement with
the complainants.
7. The learned Senior counsel – Mr. Gopal Sankaranarayan drawing the
attention of the Court to the alleged letter of revocation dated 12-8-
2014, submitted that even as per the said letter, the appellants had
stated that they could not be liable for the acts of the Respondent
No.2 “henceforth” meaning thereby after the said letter, however,
the Respondent No.2 had entered into the agreement with the
complainants i.e consumers prior to the said letter and pursuant to
the JAV executed between the appellants and Respondent No.2,
which has not been cancelled so far.
8. Having regard to the submissions made by the learned Senior
counsels for the parties, and to the impugned Judgments and
orders passed by the `State Commission’ as well as the `NCRDC’, it
[2024] 8 S.C.R. 853
Akshay & Anr. v. Aditya & Ors.
clearly transpires that undisputedly an irrevocable power of attorney
dated 6-7-2013 was executed by the appellants in favour of the
Respondent No.2 along the JAV of the same date, pursuant to which
the Respondent No.2 had undertaken to develop the land in question.
It further appears that though allegedly the said power of attorney
was revoked by the appellants vide the letter dated 12-8-2014,
the JAV has not been revoked so far and the same still continues
to be in force. As rightly submitted by the learned counsel for the
respondents, in the letter daeted 12-8-2014, the appellants had stated
to be not liable “Henceforth”, i.e. after the said letter was sent. The
appellants therefore were bound by the acts/deeds of the Respondent
No.2 carried out pursuant to the irrevocable Power of Attorney till
it was terminated, in accordance with law. It is also not denied that
the appellants have not taken any action whatsoever against the
respondent No.2 with regard to the alleged non-compliance of the
terms and conditions of JAV by the said Respondent. Under the
circumstances, it does not lie in the mouth of the appellants to say
that the appellants are not liable for the acts of Respondent No.2.
9. The ‘NCDRC’ having considered all the issues with regard to the
joint liability of the appellants as well as the Respondent No.2, we
do not find any good ground to interfere with the same.
10. In that view of the matter, the Appeals being devoid of merits and
are dismissed.
Result of the case: Appeals dismissed.
†
Headnotes prepared by: Divya Pandey
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.