Created byFuzzy Cloud

Supreme Court of India

AMAN SEMI-CONDUCTORS (PVT.) LTDversusHARYANA STATE INDUSTRIAL DEVELOPMENT CORPORATION LTD. & ANR.

Citation
2023 INSC 172
Decided
27 February 2023
Disposal
Dismissed

Holding

HSIDC was justified in resuming the plot as the appellant failed to comply with the enforceable conditions of the allotment agreement, and the appellant is entitled only to a refund of the amount paid with interest.

Summary

Aman Semi-Conductors Pvt. Ltd. obtained an industrial plot from the Haryana State Industrial Development Corporation (HSIDC) on the condition that it would construct and commence production within stipulated timeframes. The company failed to start any construction, repeatedly sought extensions citing lack of infrastructure, and did not provide any concrete plans or progress reports. HSIDC issued multiple show‑cause notices and eventually resumed the plot on 18‑09‑1998, refunding the paid amount. The appellant challenged the resumption, alleging violation of natural justice and arguing that infrastructural deficiencies excused non‑compliance. The Supreme Court held that the conditions in the allotment agreement were valid and enforceable, the appellant’s inaction was insincere, and HSIDC was justified in resuming the plot; the appellant is entitled only to a refund of Rs 1,66,425 with interest. The appeals were dismissed.

Issues considered

  • The validity and enforceability of the conditions in the industrial plot allotment agreement under the Transfer of Property Act.
  • Whether HSIDC’s cancellation and resumption of the plot violated principles of natural justice.
  • Whether lack of infrastructural facilities excuses the appellant’s failure to comply with the agreement.
  • Whether the appellant is entitled to a refund only or also to additional relief.
  • Whether the NCDRC’s order should be interfered with by the Supreme Court.

Legislation cited

Subjects

industrial plot allotmentcancellationresumptionnatural justiceTransfer of Property Actconsumer disputerefundinterestcompliance with conditionsindustrial development corporation

Judgment

130                       [2023]
               SUPREME COURT     3 S.C.R. 130
                              REPORTS                        [2023] 3 S.C.R.


A                 AMAN SEMI-CONDUCTORS (PVT.) LTD
                                         v.
             HARYANA STATE INDUSTRIAL DEVELOPMENT
                   CORPORATION LTD. & ANR.
B                     (Civil Appeal No(s). 572-573 of 2010)
                              FEBRUARY 27, 2023
           [S. RAVINDRA BHAT AND DIPANKAR DATTA, JJ.]
            Consumer Protection – Industrial plot was alloted in favour
      of the appellant by respondent-Corporation – However, the
C
      allotment was cancelled and the respondent resumed the plot stating
      that the appellant was not serious in implementing the proposed
      project and that the plot was lying vacant – Justification of – Held:
      The idea behind development of industrial plots and allotting them
      to deserving applicants is to act as a catalyst to promote economic
D     growth – In the present case, the development of industrial areas
      was part of the State’s overall project for promoting industries and
      growth of its economy with the objective of providing livelihood –
      Agreement entered into between the respondent and the appellant
      stipulated that the allottee would enjoy the right of possession as
      long as he complied with all terms and conditions of allotment
E
      contained in the agreement – The stipulation in the allotment letter
      requiring allottees to construct their respective projects and start it,
      was essential – However, the appellant was always insincere and
      perhaps never intended to follow up and set up the industrial project,
      which he proposed to the respondent, as the basis for allotment of
F     his plot – Impugned order of NCDRC holding that the respondent
      was justified in resuming the plot does not call for interference.
            Dismissing the appeals, the Court
             HELD: 1.1 The allotment made in favour of the appellant
      by HSIDC contains several conditions. The HSIDC and the
G     appellant entered into an agreement. Clause 4 (iii) of the
      agreement stipulates that the allottee would enjoy the right of
      possession as long as he complied with all terms and conditions
      of allotment contained in the agreement. Besides this, there were
      other mandatory stipulations. The development of industrial areas,
H     was part of the state’s overall project for promoting industries
                                        130
     AMAN SEMI- CONDUCTORS (PVT.) LTD v. HARYANA STATE                  131
            INDUSTRIAL DEVELOPMENT CORP. LTD.


and growth of its economy, with the objective of providing              A
livelihood. The HSIDC therefore, correctly contends that the
stipulation in the allotment letter, requiring allottees to construct
their respective projects and start it, was essential. The appellant
too had furnished a project report, proposing to set up an FM
radio and audio component manufacturing unit. This project was
                                                                        B
appraised, he was interviewed and after satisfying itself about its
feasibility, HSIDC allotted the plot. There is no denial of the fact
that the allottee did not take any step towards setting up the unit
he proposed. His pleading, before the District Consumer Forum,
was that the infrastructural facilities, such as road and external
development had not come up. He claims to have applied for              C
electricity connection. On the other hand, there is nothing on
the record- even till date- pointing to any plan to construct a
factory or industrial unit. He did not supply any plans for approval;
nor did he ever show inclination to procure the needed machinery
and equipment required for his proposed industrial unit. Other
                                                                        D
steps such as securing tax registration, etc., too were not shown
to have been done. Thus, the appellant was always insincere and
perhaps never intended to follow up and set up the industrial
project, which he proposed to HSIDC, as the basis for allotment
of his plot. [Paras 16-18][137-E; 138-E,G-H; 138-A-C]
      Indu Kakkad v. Haryana State Industrial Development               E
      Corporation Ltd 1999 (2) SCC 37 : [1998] 3 Suppl.
      SCR 277– referred to.
       1.2 The idea behind development of industrial plots and
allotting them to deserving applicants is to act as a catalyst to
promote economic growth. In the present case, the facts are             F
stark; the appellant never made any genuine effort to start its
unit. There is no material to disclose that upon receipt of no less
than three show cause notices, the appellant showed any sense
of urgency in taking steps to live up to the bargain, (of setting up
an industrial unit). The inference which this court is left to draw,    G
is that the allottee’s intention was perhaps never to set up any
industrial unit, despite its promise to the contrary, and
speculatively deal with the plot. Having regard to these facts and
circumstances, the court is of the opinion that the impugned order
does not call for interference. In view of the above conclusions,
                                                                        H
132              SUPREME COURT REPORTS                                 [2023] 3 S.C.R.


A     this court would have been justified in holding that the appellant
      is only entitled to refund of the sum of 1,66,425/- which was
      paid for the plot. However, there is no denial of the fact that the
      cheque issued to him was returned and HSIDC had the benefit of
      those monies all these years. In these circumstances, HSIDC to
      refund the sum of 1,66,425/- with interest at 6% p.a. from
B
      18.09.1998 till date. [Paras 21-23][140-H; 141-D-F]
             Managing Director, Haryana Industrial Development
             Corporation & Ors. v Hari Om Enterprises & Ors 2009
             (16) SCC 208 : [2008] 9 SCR 821– held inapplicable.
C                                 Case Law Reference
      [1998] 3 Suppl. SCR 277                referred to                  Para 19
      [2008] 9 SCR 821                       held inapplicable            Para 20
            CIVIL APPELLATE JURISDICTION : Civil Appeal Nos.572-
D     573 of 2010.
             From the Judgment and Order dated 07.11.2008 and 11.01.2007
      of the National Consumer Dispures Redressal Commission, New Delhi
      in MA No.711 of 2008 in RP No.3125 of 2003.
            Rajiv K. Garg, Ashish Garg, Lalit Nagar, T. L. Garg, Advs. for
E     the Appellant.
            Alok Sangwan, Sr. AAG, Ravindra Bana, Sumit Sharma, Samar
      Vijay Singh, Sanjay Kumar Visen, Advs. for the Respondents.
             The Judgment of the Court was delivered by
F            S. RAVINDRA BHAT, J.
             1. The present appeals, by special leave, are directed against
      orders1 of the National Consumer Disputes Redressal Commission
      (hereinafter “NCDRC”). The NCDRC allowed a revision petition filed
      by the respondent corporation.
G           2. The brief facts of the case are that the appellant, a proprietary
      concern applied for an industrial plot of the proposed project on
      28-02-1994 in Industrial State Udyog Vihar, Gurgaon. The respondent
      corporation (hereinafter HSIDC”) called the appellant’s proprietor, Modi
      1
        Dated 11.01.2007 in RP No.3125/2003 and order dated 07.11.2008 in Misc. Application
H     No. 711/2008 in Revision Petition No. 3125/2003.
        AMAN SEMI- CONDUCTORS (PVT.) LTD v. HARYANA STATE                        133
      INDUSTRIAL DEVELOPMENT CORP. LTD. [S. RAVINDRA BHAT, J.]


Lal Gupta, for an interview on 09-09-1994. A letter of intent was issued         A
indicating certain conditions on 05-10-1994. The appellant informed that
he could not start the production in time on the ground that there were
no basic infrastructure facilities as electricity, sewerage, telephone and
proper road, etc., and requested for extension of time of three months.
After sanction of the loan by HSIDC, on 13-09-1995, a letter of allotment
                                                                                 B
of plot was issued which stipulated certain terms and conditions. On
02-11-1995 possession was handed over to the allottee/appellant.
       3. The appellant did not fulfil the required conditions of the
allotment. No concrete step to set up the industrial unit on the allotted
site was initiated by it. As a result, HSIDC issued a notice, on
13-12-1996 asking the appellant to show cause why the plot should not            C
be resumed on account of its failure to fulfil the terms and conditions of
the allotment. In response, the appellant, on 12-02- 1998, wrote back to
the HSIDC. The letter or reply alleged that no basic infrastructure facilities
as electricity, sewerage, telephone and proper road, etc., existed near
the site, and, as a result, it was not possible to start the construction. The   D
appellant sought extension of time by a year.
       4. On 23-03-1998, HSIDC issued final notice asking why the plot
should not be resumed for the appellant’s failure to fulfil the terms and
conditions of allotment. The appellant wrote a letter, again on
19-04-1998 requesting for extension of time. Since appellant did not come        E
forward to satisfy the HSIDC by producing any document in response
to its letter dated 19-04-1998 about the steps taken, HSIDC, on
18-09-1998 resumed the plot stating that the appellant was not serious in
implementing the project and that the plot was lying vacant. HSIDC
enclosed a cheque for a sum of ` 1,66,425 with the letter towards the
refund and the appellant was requested to handover the possession of             F
the plot to the Field Officer.
       5. The appellant approached the District Forum, Gurgaon2 with a
complaint. The District Forum, Gurgaon, assumed that since the State
Government has changed the policy without referring to the policy, it
went on to hold that the complainant was unable to complete the project          G
not on account of negligence on the part of the complainant but because
of the circumstances which were beyond its control. HSIDC appealed
to the State Commission. The State Commission dismissed the appeal 3,
2
    In CPA No 1697 of 07.10.1998
3
    In First Appeal No 1010 of 29.04.2003                                        H
134             SUPREME COURT REPORTS                             [2023] 3 S.C.R.


A     upon which HSIDC filed a revision petition before the NCDRC, which
      was dismissed on the ground of delay4. The HSIDC’s special leave
      petition to this court succeeded, and an order was made on 10.11.2003 5
      directing the NCDRC, to hear and dispose of the appeal on its merits.
             6. The NCDRC, after remand, allowed HSIDC’s revision
B     application. It held that the grounds taken and the reasons given by the
      appellant were vague and evasive and does not disclose any particular
      date or any time frame for taking up and completing construction. It was
      also held that the appellant did not show what concrete steps were taken
      and that his conduct and correspondence could not be taken to be a
      proper explanation or sufficient ground for non-completion of the
C     construction and non-installation of the machines and not starting the
      production in terms of the agreement. The NCDRC also held that the
      plot remained in possession of the complainant from 29-12-1995 till 18-
      12-1998. Relying on the decision of this court in Indu Kakkad v Haryana
      State Industrial Development Corporation Ltd6, where this court relied
D     on a clause similar to clause 6 of the current agreement, the NCDRC
      held that the HSIDC was justified in resuming the plot.
             Contentions of the appellant
              7. Mr. Rajiv K. Garg, learned counsel appearing for the appellant,
      urged that the appellant did not violate any of the terms of the allotment
E     letter and took due steps in terms of the allotment letter. After the allotment
      of the plot (No 182-M, Udyog Vihar, Phase - IV, Gurgaon) he took all
      the required steps such as:
             (a) obtaining the required certificate from the Industrial
             Department;
F            (b) applying to the electrical department for grant of power
             connection for which he had deposited the requisite amount with
             the HSEB;
             (c) applying for financial assistance with the Financial Corporation.

G          However, on account of change in policy of the Government, the
      same was not granted, therefore, the appellant arranged the same from

      4
        In Revision Petition No 3125 of 2003
      5
        In Civil Appeal No 5672/2004
      6
        Indu Kakkad v Haryana State Industrial Development Corporation Ltd, 1999 (2)
H     SCC 37
     AMAN SEMI- CONDUCTORS (PVT.) LTD v. HARYANA STATE                           135
   INDUSTRIAL DEVELOPMENT CORP. LTD. [S. RAVINDRA BHAT, J.]


outside. Thus, the appellant took all effective steps for implementation         A
of the project which were within his power and control.
       8. It was urged that the appellant is a duly qualified engineer, who
wanted to be an entrepreneur, and acted upon the novel idea of
manufacturing components for FM radios and audios. However, the delay
in granting permission and not releasing capital resulted in no construction.    B
       9. Learned counsel further submitted that the NCDRC’s impugned
order is in error, because it overlooked the fact that the resumption order
was issued without granting any opportunity to the appellant; furthermore,
the order was also vitiated as it was non-speaking. Learned counsel
relied on the judgment of this court in Managing Director, Haryana               C
Industrial Development Corporation & Ors. V. Hari Om Enterprises
& Ors.7, in support of the argument that cancellation of allotment without
adherence to principles of natural justice vitiates the action of HSIDC.
       Contentions of HSIDC
       10. Mr. Alok Sangwan, learned Additional Advocate General for             D
Haryana, urged this court not to interfere with the findings of the
NCDRC. He submitted that the record would show that sufficient
opportunity was granted to the appellant, and show cause notice too
was issued to him, asking him why steps were not taken to construct the
industrial unit upon the plot. Counsel relied on several letters exchanged       E
between the parties. He argued that the appellant did not show any,
much less substantial progress or interest in carrying on industrial activity
on the plot.
        11. Mr. Sangwan submitted that the object behind allotment of
plots in industrial areas, was to promote industrial activity, especially by     F
qualified engineers. He highlighted that allotment is based on appraisal
of the project proposed by applicants, and having regard to their feasibility.
The overall objective of the scheme under which plots were allotted
was to promote industrialization and thereby promote economic growth,
and also ensure employment. The persistent inaction of the appellant
and his inability to show any inclination to fulfil these objectives, despite    G
grant of several opportunities, and most importantly his inability to take
any initiative despite lapse of five years from allotment, meant that he
was not interested in constructing upon, or using the plot for any industrial
7
  Managing Director, Haryana Industrial Development Corporation & Ors. v Hari
Om Enterprises & Ors, 2009 (16) SCC 208                                          H
136             SUPREME COURT REPORTS                            [2023] 3 S.C.R.


A     activity, but rather to speculate and wait for its value to increase, and
      thereafter dispose it off.
              12. Learned counsel relied upon several conditions in the allotment
      letter and stated that the appellant was obliged to not only take swift and
      timely action towards putting up the unit, but also the allotment was
B     hedged with several conditions, many of which, upon violation, entailed
      cancellation. Therefore, there was nothing abhorrent or reprehensible in
      HSIDC’s action in resuming the plot.
            Analysis and Reasoning
              13. The record in this case indicates that the appellant had applied
C     for allotment of the industrial plot on 28-02-1994. After he was interviewed
      and his credentials verified, he was issued with the letter of intent on 09-
      09-1994. The final payment was made in respect of the plot on 06-09-
      1995. Later the next month on 27-10-1995, an agreement was executed
      between HSIDC and the appellant in which he agreed to complete the
D     project in 2 years. The agreement also contained the condition that
      extension could be granted upon payment of a fee. The appellant took
      possession of the plot on 29-12-1995. The appellant was called upon to
      show cause why he did not complete construction and set up the unit, in
      1997. Upon receiving this notice, he replied on 12-02- 1998 that he could
      not start the unit due to lack of infrastructural facilities. He alleged that
E     road and electricity facilities were not adequate, which had hindered his
      project. The HSIDC issued a show cause notice to the appellant, again
      on 23-03-1998. Yet again on 29-04-1998, another show cause notice
      was issued by HSIDC, asking the appellant to indicate the steps that he
      had taken to put up the industrial unit and start production. However, the
F     appellant did not apparently respond to this. Finally, on 18-09-1998, the
      HSIDC communicated that it had resumed the plot and cancelled the
      allotment. It refunded the sum of ` 1,66,425, through a cheque, which
      was sent to the appellant. The latter upon receipt of this intimation did
      not accept the cheque and returned it back on 06-10-1998.

G            14. In the meanwhile, the appellant approached the District
      Consumer Forum, Gurgaon, on 30-09-1998. The District Consumer
      Forum allowed the complaint on 16-05-2000 and directed the HSIDC to
      withdraw the resumption order. It also directed HSIDC, not to allot the
      plot to any other person; HSIDC was granted 3 months’ time to comply
      with the requirement of allotting the plot to the appellant. The HSIDC’s
H     appeal was rejected on 29-04-2003 by the State Consumer Commission.
     AMAN SEMI- CONDUCTORS (PVT.) LTD v. HARYANA STATE                            137
   INDUSTRIAL DEVELOPMENT CORP. LTD. [S. RAVINDRA BHAT, J.]


It approached the NCDRC belatedly. On 10-11-2003 NCDRC dismissed                  A
its revision petition as time-barred. Subsequently, the HSIDC approached
this court, which remitted the matter by its order dated 20- 01-2004 to
the NCDRC for fresh consideration on merits. By the impugned order,
the revision petition was allowed.
       15. As the previous discussion reveals the appellant’s arguments           B
are twofold. The first is that HSIDC violated principles of natural justice,
did not grant him a hearing and unilaterally cancelled the allotment. The
added point made was that the allotment was followed by payment of
full consideration and that, in these circumstances, some minimum hearing
ought to have been given before adverse action of resumption was taken.
It was also alleged in this regard that cancellation order did not disclose       C
any application of mind; no reasons are forthcoming. The second
substantial argument made was that in the absence of essential
infrastructural facilities such as roads, overall development of the industrial
area availability of electricity and other amenities, HSIDC could not
have expected the appellant or any other allottee to construct the plot           D
within the time granted, i.e two years.
       16. The allotment made in favour of the appellant by HSIDC
contains several conditions. The HSIDC and the appellant entered into
an agreement on 27-10-1995. Clause 4 (iii) of the agreement stipulates
that the allottee would enjoy the right of possession as long as he complied      E
with all terms and conditions of allotment contained in the agreement.
Clause 6 which is important in the present context reads as follows:
       “6. That the allottee shall start on the site construction of
       building for setting up the aforesaid industry within a period
       of 6 months and complete the construction thereof within 1 1/              F
       2 years from the date of the possession. The plans thereof
       shall be in accordance with the rules made as per the
       directions given from time to time by the Town and country
       planning and Urban estate Department, in this respect and
       approved by the Director Town & Country planning
       department or any officer duly authorised by him in this behalf.           G
       Further the allottee shall complete the construction and
       installation and machinery and commence production within
       a period of 2 years from the date of possession after
       constructing a minimum of 25% of the permissible covered
       area, failing which the plot shall be liable to be resumed by              H
138             SUPREME COURT REPORTS                            [2023] 3 S.C.R.


A            the Corporation.
             Provided that the scheme shall be deemed not to have been
             implemented unless the allottee starts commercial production
             after completing construction to the extent of at least 25% of
             the permissible covered area of the plot as per the approved
B            Zoning Plan of the concerned estate within the aforesaid
             period failing that event, the plot shall liable to be resumed
             by the Corporation.
             However, the Corporation shall have the right to call for
             periodical reports every 6 months from the allottee about the
C            progress /implementation of the project and if, after hearing
             the allottee the Corporation is of the opinion that the progress
             is unsatisfactory it may order the plot to be resumed.
             In the event of reasons beyond the control of the allottee to
             set up the unit within the prescribed period/the Corporation
D            may grant the suitable extension depending upon the merits
             of the case. However, such extension shall be granted on
             payment of a fee in accordance with the rules/policy of the
             Corporation”.
             17. Besides this, there were other mandatory stipulations such as
E     that regular payment of maintenance charges, proportional conservation
      charges, proportionate external development charges as could be
      determined by HSIDC and importantly the condition that the allottee
      could not change its constitution and if it did so, it should in any event,
      hold not less than 51 % shareholding in its concern. Similarly, any request
      of the allottee for transfer of plot, could be considered where the final
F     allotment letter had been issued and the project had been completed and
      approved by the HSIDC. The embargo on transfer was subject to the
      condition that the HSIDC had the final say or approval, in this regard.
            18. The development of industrial areas, was part of the state’s
      overall project for promoting industries and growth of its economy, with
G     the objective of providing livelihood. The HSIDC therefore, correctly
      contends that the stipulation in the allotment letter, requiring allottees to
      construct their respective projects and start it, was essential. The appellant
      too had furnished a project report, proposing to set up an FM radio and
      audio component manufacturing unit. This project was appraised, he
      was interviewed and after satisfying itself about its feasibility, HSIDC
H
     AMAN SEMI- CONDUCTORS (PVT.) LTD v. HARYANA STATE                         139
   INDUSTRIAL DEVELOPMENT CORP. LTD. [S. RAVINDRA BHAT, J.]


allotted the plot. There is no denial of the fact that the allottee did not    A
take any step towards setting up the unit he proposed. His pleading,
before the District Consumer Forum, was that the infrastructural facilities,
such as road and external development had not come up. He claims to
have applied for electricity connection. On the other hand, there is nothing
on the record- even till date- pointing to any plan to construct a factory
                                                                               B
or industrial unit. He did not supply any plans for approval; nor did he
ever show inclination to procure the needed machinery and equipment
required for his proposed industrial unit. Other steps such as securing
tax registration, etc., too were not shown to have been done. In these
circumstances, the conclusion which this court is compelled to draw is
that the appellant was always insincere and perhaps never intended to          C
follow up and set up the industrial project, which he proposed to HSIDC,
as the basis for allotment of his plot.
       19. The judgment of this court in Indu Kakkar had concluded
that Clause 7 of the agreement, entered into between the parties (in that
case), was binding. That condition required construction of the building       D
for setting up the industry, in respect of which land was allotted to the
appellant, to start within a period of six months. Construction had to be
completed with two years from the date of issue of the allotment letter.
Since the appellant failed to commence construction within the stipulated
time, show-cause notice was issued as to why the plot be not resumed in
terms of the agreement; that was in challenge and relied on Section 11         E
of the Transfer of Property Act, 1882. This court negatived the plea in
the following manner:
      “16. However, the allottee has contended before the trial court
      that Clause 7 of the agreement is unenforceable in view of
      Section 11 of the TP Act. But that contention was repelled,              F
      according to us, rightly because the deed of conveyance had
      not created any absolute interest in favour of the allottee in
      respect of the plot conveyed. For a transferee to deal with
      interest in the property transferred “as if there were no such
      direction” regarding the particular manner of enjoyment of               G
      the property, the instrument of transfer should evidence that
      an absolute interest in favour of the transferee has been
      created. This is clearly discernible from Section 11 of the TP
      Act. The Section rests on a principle that any condition which
      is repugnant to the interest created is void and when property
      is transferred absolutely, it must be done with all its legal            H
140            SUPREME COURT REPORTS                           [2023] 3 S.C.R.


A            incidents. That apart, Section 31 of the TP Act is enough to
             meet the aforesaid contention. The Section provides that “on
             a transfer of property an interest therein may be created with
             the condition super-added that it shall cease to exist in case
             a specified uncertain event shall happen, or in case a
             specified uncertain event shall not happen.”
B
             Illustration (b) to the Section makes the position clear, and it
             reads:
             (b) A transfers a farm to B, provided that, if B shall not go to
             England within three years after the date of the transfer, his
             interest in the farm shall cease. B does not go to England
C            within the term prescribed. His interest in the farm ceases.
             17. All that Section 32 of the Transfer of Property Act provides
             is that “in order that a condition that an interest shall cease
             to exist may be valid, it is necessary, that the event to which it
             relates be one which could legally constitute the condition of
D            the creation of an interest”. If the condition is invalid, it cannot
             be set up as a condition precedent for crystallization of the
             interest created. The condition that the industrial unit shall
             be established within a specified period failing which the
             interest shall cease, is a valid condition. Clause 7 of the
             agreement between the parties is, therefore, valid and is
E            binding on the parties thereto.”
             20. The decision in Hari Om in this court’s opinion, does not in
      any manner assist the appellant. In that case, the court had dealt with
      several appeals. In the main appeal, the allotment was offered on
      20.12.2001; however actual possession was handed over on 08.12.2003.
F     The appellant applied for approval of building plan, thereafter, which
      was given by HSIDC on 20.03.2004. The construction of the industrial
      unit was completed in May 2005. In the meanwhile, alleging non
      compliance with the terms of allotment, the plot was resumed on
      03.03.2005. Having regard to these facts, the High Court had set aside
      the resumption order. This court repelled the HSIDC’s argument that
G     writ proceedings were not maintainable, and held in the facts and
      circumstances, that the setting aside of the resumption was justified.
             21. The idea behind development of industrial plots and allotting
      them to deserving applicants is to act as a catalyst to promote economic
      growth; this aspect was underlined in Hari Om in the following manner,
H     while describing the functions of HSIDC:
      AMAN SEMI- CONDUCTORS (PVT.) LTD v. HARYANA STATE                            141
    INDUSTRIAL DEVELOPMENT CORP. LTD. [S. RAVINDRA BHAT, J.]


        “4. […] Its principal function is allotment of industrial plots            A
        belonging to the State of Haryana. It was set up as a catalyst
        for promoting economic growth and accelerating the pace of
        industrialization. It not only provides financial assistance to
        the industrial concerns by way of term loans; it also develops
        infrastructure for setting up of industrial units. The
                                                                                   B
        Corporation also invests money in developing the industrial
        estates at strategic locations. In exercise of its functions, it
        also allots industrial plots to entrepreneurs for setting up their
        industries on “no profit no loss” basis. The entrepreneurs,
        according to the Corporation, must be the deserving ones.
        For the said purpose, it keeps in mind the principle that                  C
        allotment of land should not be made to speculators who invest
        in property for getting high returns on escalation of price.”
        22. In the present case, as discussed earlier, the facts are stark;
the appellant never made any genuine effort to start its unit. There is no
material to disclose that upon receipt of no less than three show cause            D
notices, the appellant showed any sense of urgency in taking steps to
live up to the bargain, (of setting up an industrial unit). The inference
which this court is left to draw, is that the allottee’s intention was perhaps
never to set up any industrial unit, despite its promise to the contrary, and
speculatively deal with the plot. Having regard to these facts and
circumstances, the court is of the opinion that the impugned order does            E
not call for interference.
        23. In view of the above conclusions, this court would have been
justified in holding that the appellant is only entitled to refund of the sum
of ` 1,66,425/- which was paid for the plot. However, there is no denial
of the fact that the cheque issued to him was returned and HSIDC had               F
the benefit of those monies all these years. In these circumstances,
HSIDC is directed to refund the sum of ` 1,66,425/- with interest at 6%
p.a. from 18.09.1998 till date. The amounts shall be paid to the appellant,
within six weeks from today.
        24. The appeals are dismissed, but subject to directions contained
                                                                                   G
in the previous paragraph; there shall be no order on costs.

Divya Pandey                                                  Appeals dismissed.
(Assisted by : Anirudh Agrawal and Rakhi, LCRAs)


                                                                                   H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "industrial plot allotment"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.

AMAN SEMI-CONDUCTORS (PVT.) LTD versus HARYANA STATE INDUSTRIAL DEVELOPMENT CORPORATION LTD. & ANR. — 2023 INSC 172 - Legal Desk AI