Created byFuzzy Cloud

Supreme Court of India

BHARAT SANCHAR NIGAM LTD. AND ANR.versusDHANURDHAR CHAMPATIRAY

Citation
2009 INSC 1300
Decided
11 December 2009
Disposal
Case Partly allowed

Holding

The Supreme Court held that the right to appoint an arbitrator under Section 11(6) is not forfeited after 30 days and that any appointment must comply with the qualifications and independence requirements of Section 11(8), rendering the High Court’s appointment invalid.

Summary

Bharat Sanchar Nigam Ltd. entered into a construction contract containing an arbitration clause that named the Chief Engineer or, in his absence, the Administrative Head as the sole arbitrator. The respondent repeatedly requested the Chief Engineer to appoint an arbitrator, but the appellant failed to respond, prompting the respondent to file a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996. The appellant claimed that the Chief Engineer had already appointed a Principal Chief Engineer as arbitrator on 9 March 2005. The High Court, ignoring the contractual qualifications and the requirements of Section 11(8), appointed a senior advocate as arbitrator, superseding the departmental nominee. On appeal, the Supreme Court held that the right to appoint an arbitrator under Section 11(6) does not automatically forfeit after the 30‑day period and that any appointment must satisfy the qualifications and independence criteria of Section 11(8). Consequently, the High Court’s appointment was set aside and the matter remanded for a fresh appointment in compliance with Section 11(8).

Issues considered

  • The effect of the 30‑day period on the right to appoint an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996.
  • Whether the High Court was required to consider the qualifications and independence of the arbitrator as mandated by Section 11(8).
  • The validity of the arbitrator appointed by the High Court in view of the contractual arbitration clause.

Legislation cited

Subjects

ArbitrationAppointment of arbitratorSection 11Arbitration and Conciliation Act 1996Independent and impartial arbitratorConstruction contractHigh Court appointment

Judgment

                   [2009] 16 (ADDL.) S.C.R. 398


A          BHARAT SANCHAR NIGAM LTD. AND ANR.
                                  v.
                  DHANURDHAR CHAMPATIRAY
                  (Civil Appeal No. 8230 of 2009)
                       DECEMBER 11, 2009
B
        [TARUN CHATIERJEE AND AFTAB ALAM, JJ.]

        Arbitration and Conciliation Act, 1996:
                                                                          •
c       s. 11 (6) - Appointment of arbitrator - Arbitrator not
  appointed within 30 days of demand - Right to make
  appointment of arbitrator would not be forfeited but would
  continue, but such right should be exercised before the other
  party files application under s. 11 before High Court - On facts,
0 High Court did not focus on the agreement or conditions
  necessary to secure appointment of independent and
  impartial arbitrator - Since requirement of sub-section (8) of          I   •

  s. 11 was not dealt with by High Court, appointment of arbitrator
  became vulnerable - Matter remanded to High Court for
E decision afresh.
      Parties entered into a contract for work construction.
  The contract contained arbitration clause in terms
  whereof the Chief Engineer in charge of work at the time
  of dispute and in absence of Chief Engineer,
F Administrative head of the department was to be
  appointed as a sole arbitrator. The said provision
                                                                      .
  envisaged that in terms thereof no person other than the
  one appointed by such Chief Engineer or Administrative
  Head should act as arbitrator to decide the disputes
G referred to him. Dispute arose between the parties.
  Respondent sent letters to the Chief Engineer of the
  appellant no.1 on different dates requesting for
  appointment of an arbitrator to adjudicate the disputes.
  The appellants did not give response to the letters of
H                                398
          BHARAT SANCHAR NIGAM LTD. v. DHANURDHAR 399
                       CHAMPATIRAY
         respondent. Thereaftar respondent filed petitions under A
         Section 11 (6) of the Arbitration and Conciliation Act, 1996.
         However, according to the case made out by the
         appellants appointment of Principal Chief Engineer as an
         arbitrator was already made on 9.3.2005. By impugned
         order, High Court allowed the application under Section 8
         11 (6) and appointed arbitrator in place of the
         departmental nominee who was appointed by the Chief
         Engineer of the appellants. Hence the appeals.
             Partly allowing the appeals and remitting the matter
         to High Court, the Court                                      C
              HELD: 1. A plain reading of Section 11(5) of the
         Arbitration and Conciliation Act, 1996 would show that if
         one party demands appointment of an arbitrator and the
         other party does not appoint any arbitrator within thirty 0
         days of such demand, the right to appointment at the
..   I   instance of one of the parties does not get automatically
         forfeited. If the appellant makes an appointment even after
         thirty days of demand but the first party has not moved
         the Court under Section 11, that action on the part of the E
         appellant would be sufficient. In the instant case, High
         Court did not focus on requirements required by the
         agreement or other conditions necessary to secure the
         appointment of independent and impartial arbitrator.
         Since the requirement of sub-section (8) of Section 11 F
         was not at all dealt with by High Court, appointment of
         arbitrator without dealing with the said sub-section
         became vulnerable. [Para 8 and 11] [403-E-G; 406-G-H;
         407-A-H]
             Northern Railway Administration, Ministry of Railway v.   G
         Patel Engineering Company Ltd. (2008) 10 SCC 240, relied
         on.
             Punj Lioyd Ltd. v. Petronet MHB Uc. (2006) 2 SCC 638;
         Datar Switchgears Ltd. v. Tata Finance Ltd. And Another       H
    400 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.

A (2000) 8SCC 151; Ace Pipeline Contracts Private Limited v.               +
  Bharat Petroleum Corporation Limited (2007) 5 SCC 304;
  Union of India v. Bharat Battery Manufacturing Co. Pvt. Ltd.
  (2007) 7 sec 684, referred to.

                          Case Law Refernce:
B
        (2006) 2 sec 638           referred to           Para 8
        (2000) 8SCC 151            referred to           Para 9
        (2001) s sec 304           referred to           Para 10
c       (2007) 1 sec 684           referred to           Para 10
        (2008) 10 sec 240          relied on             Para 10
        CIVIL APPELLATE JURISDICTION : Civii Appeal No.
    8230 of 2009.
D
        From the Judgment & Order dated 5.1.2007 of the High           I       •
    Court of Orissa at Cuttack Arbitration Petition No. 11 of 2005.
                                WITH
E C.A. Nos. 8231, 8232, 8233, 8234 of 2009.

        Debasish Moitra, Ajit Kumar Pande for the Appellants.
        Parmanand Gaur (N.P.) for the Respondent.
                                                                           >- •
F       The Judgment of the Court was deliverd by

        TARUN CHATTERJEE, J. 1. Leave granted.

       2. These appeals by special leave have been filed against                    -
                                                                                   ,.,
  the orders dated 5th of January 2005 in A.R.B.P. Nos. 11, 12,
G 17, 18 and 28 of 2005 passed by the High Court of Orissa
  whereby the High Court had appointed Sh. Bibhudhendra
  Mishra, a Senior Advocate of the Orissa High Court as the sole           t "'
  arbitrator on the application of the respondent filed under
  Section 11 (6) of the Arbitration and Conciliation Act 2006
H (hereinafter ,referred to as "the Act"). Since the parties and the
                     BHARAT SANCHAR NIGAM LTD. v. DHANURDHAR 401
                        CHAMPATIRAY [TARUN CHATTERJEE, J.]
.. ._              subject matter of the dispute are the same, we have clubbed           A
                   all these appeals and the same are being decided analogously
                   by this common judgment to avoid any confusion.

                       3. The relevant facts leading to the filing of these appeals
                   as emerging from the records may be briefly stated as follows:        B
                         The parties herein entered into a contract pursuant to
              ,,   distinct notices inviting tender by BSNL [in short 'the appellant']
,..'"'             for the work of construction of 4 Nos. of Type-II, 2 Nos. Type-Ill
                   and 1 No. of Type-IV Staff Quarters at Bhanjanagar of vertical
                   extension to combined building at Aska of 3 Nos. of Type Ill, 3       c
                   Nos. of Type II and 4 K type T.E. building at Jankia and of
                   vertical extension to 8 Nos. of Type II and 6 Nos. of Type IV
                   staff quarters at CTTC compound Vanivihar, Bhubaneshwar.

                        4. The said contract contained an arbitration clause in          D
         >    I    terms whereof the Chief Engineer, Telecommunication/ Postal
                   Department in charge of the work at the time of dispute, or if
                   there be no Chief Engineer, the Administrative Head of the said
                   Telecommunication/ Postal Department was to be appointed
                   as a sole arbitrator. The said provision envisaged that in terms      E
                   thereof no person other than the one appointed by such Chief
                   Engineer or Administrative Head of the Telecommunication/
                   Postal as aforesaid should act as arbitrator to decide the
                   disputes referred to him.
          ---i                       '
                         5. The Respondent by letters, requested the Chief               F




-
                   Engineer (Civil) for appointment of an arbitrator to adjudicate
                   the disputes between the parties in terms of clause 25 of the
                   respective agreements. According to the respondent, letters
                   were received by the Chief Engineer of the appellant no.1 on
                   different dates. The Appellants having failed to respond to the       G
                   letters of respondent requiring them to appoint an arbitrator and
         .,   y    to appoint an arbitrator in response to such letters within the
                   stipulated period in accordance with Clause 25 of the
                   respective Agreements, the respondent was constrained to file
                   petitions under Section 11 (6) of the Act for appointment of an       H
     402 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.

A Arbitrator. However, according to the case made out by the
                                                                            ~           ..
  appellants, on 9th of March, 2005, Chief Engineer (Civil), BSNL
  had already appointed Sri. Gurbaux Singh, Principal Chief
  Engineer (Arbitration) BSNL vide its office letter No. 69- 41 (05)/
  CE(c)/BBSR/205. By the impugned order, the High Court
B allowed application under S. 11 (6) of the Act, and appointed
                                                                                             r
  one Sri. Bibhudhendra Mishra in place of departmental nominee
  Sri. Gurbaux Singh who was appointed by Chief Engineer                               .,
  (Civil) BSNL of appellant No.1.
                                                                                            "
c        6. Feeling aggrieved by the said order of the High Court,
   the appellant has filed these special leave Opetitions which on
   grant of leave, were heard in the presence of learned counsel
 _ for the parties.

          7. Before we consider the arguments raised by the
D
     learned counsel for the parties before us, it would be necessary
     to refer to Section 11 of the Act, which reads as under:
                                                                            .   "


         "Section 11. Appointment of arbitrators. (1) A person of
         any nationality may be an arbitrator, unless otherwise
E        agreed by the parties.

         (2) Subject to sub-section (6), the parties are free to agree
         on a procedure for appointing the arbitrator or arbitrators.
         (3) & (4) .............. omitted because these are not necessary   I- -


F.       for our purpose

         (5) Failing any agreement referred to in sub- section (2),
         in an arbitration with a sole arbitrator, if the parties fail to
         agree on the arbitrator within thirty days from receipt of a
G        request by one party from the other party to so agree the
         appointment shall be made, upon request of a party, by
         the Chief Justice or any person or institution designated          y      '

         by him.

         (6) Where, under an appointment procedure agreed upon
H                                                                                      ~>
                   BHARAT SANCHAR NIGAM LTD. v. DHANURDHAR 403
                      CHAMPATIRAY [TARUN CHATIERJEE, J.]
 ~
           ..
                      by the parties,- (a) a party fails to act as required under A
                      that procedure; or (b) the parties, or the two appointed
                      arbitrators, fail to reach an agreement expected of them
                      under that procedure; or (c) a person, including an
                      institution, fails to perform any function entrusted to him or
                      it under that procedure, a party may request the Chief B
                      Justice or any person or institution designated by him to
 ,   .                take the necessary measure, unless the agreement on the
                      appointment procedure provides other means for securing
                      the appointment.

                      (7) A decision on a matter entrusted by sub- section (4)
                                                                                      c
                      or sub-section (5) or sub-section (6) to the Chief Justice
                      or the person or institution designated by him is final.

                      (8) The Chief Justice or the person or institution designated
                                                                                      D
          ,, I        by him, in appointing an arbitrator, shall have due regard
                      to- (a) any qualifications required of the arbitrator by the
                      agreement of the parties; and (b) other considerations as
                      are likely to secure the appointment of an independent and
                      impartial arbitrator... "
                                                                                    E
                       8. A plain reading of Section 11 [5) of the Act would show
                  that if one party demands appointment of an arbitrator and the
                 other party does not appoint any Arbitrator within thirty days of
                 such demand, the right to appointment at the instance of one
          -'     of the parties does not get a\Jtomatically forfeited. If the F
                 appellant makes an appointment even after thirty days of
                 demand but the first party has not moved the Court under
-----;<          Section 11, that action on the part of the appellant would be
                 sufficient. In other words, in cases arising under Section 11 [6],
                 if the respondent has not made an appointment within thirty
                                                                                    G
                 days of demand, right to make an appointment of an arbitrator
                 is not forfeited but continues, but such appointment shall be
         "' ~    made before the other party files the application under Section
                 11 seeking appointment of an arbitrator before the High Court.
                 It is only then the right of the respondent ceases. In this
                 connection, a three-Judge Bench decision of this Court in Punj H
    404    SUPREME COURT REPORTS (2009) 16 (ADDL.) S.C.R.


A Lloyd Ltd. v. Petronet MHB Ltd., (2006) 2 SCC 638, may be
                                                                           . ...
  referred to. In this case, this Court considered the applicability
  of Section 11 [6] of the Act and after considering the scope and
  object of the Act held that once notice period of thirty days has
  expired and the party has moved the Hon. Chief Justice of the
B High Court under Section 11 [6] of the Act, the other party loses
  his right to appoint an arbitrator on the basis of arbitral
  agreement. While taking this view, this Court in the Punj Lloyd's
  case [supra] had relied on the judgment referred in Datar
  Switchgears Ltd. v. Tata Finance Ltd. and Another, (2000) 8
  SCC    151, wherein in paragraph 19 at page 158 this Court
c observed   as follows:

          "So far as cases falling under Section 11 (6) are concerned
          such as the one before us no time limit has been
          prescribed under the Act, whereas a period of 30 days has
D         been prescribed under Section 11 (4) and Section 11 (5)
          of the Act. In our view, therefore, so far as Section 11 (6)     • •
          is concerned, if one party demands the opposite party to
          appoint an Arbitrator and the opposite party do not make
          an appointment within 30 days of the demand, the right to
E         appointment does not get automatically forfeited after
          expiry of 30 days. If the opposite party makes an
          appointment even after 30 days of the demand, but before
          the first party has moved the Court under Section 11, which
          would be sufficient. In other words, in cases arising under      ••
F         Section 11 (6), if the opposite party has not made an
          appointment within 30 days of demand, the right to make
          appointment is not forfeited but continues, but an
          appointment has to be made before the former files
          application under Section 11 seeking appointment of an
G         Arbitrator. Only then the right of the opposite party ceases."

        9. Similarly in the case of Ace Pipeline Contracts Private
    Limited v. Bharat Petroleum Corporation Limited, (2007) 5              ' "
    SCC 304, this Court went to observe that:
                                                                                 '[
H         "But in sub-section (6), where, the procedure has already
                     BHARAT SANCHAR NIGAM LTD. v. DHANURDHAR 405
                        CHAMPATIRAY [TARUN CHATTERJEE, J.]

                         been agreed upon by the parties, as in the present case,       A
                         and in that event, if a party fails to act as required under
                         that procedure or the parties, or the two appointed
                         arbitrators, fail to reach an agreement expected of them
                         under that procedure or a person, including an institution,
                        fails to perform ariy function entrusted to him or it under     B
                        that procedure, a party may in that event, request the Chief
                        Justice_ or a person or an institution designated by him to
_..
                         make necessary measures, unless the agreement on the
                        appointment procedure provides other means for
                        appointment of arbitrator. Therefore, so far as the period      c
                        of thirty days is concerned, it is not mentioned in Sub-
                        section (6). The period of limitation is only provided under
                        sub-sections (4) & (5) of Section 11. As such, as per the
                        statute, the period of limitation of thirty days cannot be
                        invoked under sub-section (6) of Section 11 of the Act."
                                                                                        D
      •        i
                          10. On a perusal of the above quoted observations of this
                    Court made in Ace Pipeline Contracts Private Limited (supra),
                    the reasons advanced in the orders passed by the High Court
                    must be found to be a correct interpretation of the aforesaid
                    provision and so far as the period of 30 days with regard to E
                    Section 11(6) is concerned, there is no doubt at all that thirty
                    days limitation cannot be invoked as mandatory period under
                    Section 11 [6] of the Act. But a somewhat different view was
      -~            expressed in a latter decision of this Court in the case of Union
                   of India vs. Bharat Battery Manufacturing Co. Pvt.Ltd. [2007 F
                   (7) SCC 684]. In view of the difference of opinion of the two
                   coordinate benches of this Court, the matter was referred to a
                   three-Judge Bench in the case of Northern Railway
                   Administration, Ministry of Railway vs. Patel Engineering
                   Company Ltd. [2008 (10) SCC 240] in which the decision in G
                   Ace Pipeline Contracts Pvt. Ltd. (supra) was also referred to.
          1'       Arijit Pasayat, J. (as His Lordship then was), heading the three-
                   Judge Bench of this Court, after considering the scope and
                   object of the Act particularly Section 11 of the Act, concluded
                   the following :                                                    H
    406 SUPREME COURT REPORTS [2009] 16 (ADDL.) S.C.R.

A       "A bare reading of the scheme of Section 11 shows that          ..
        the emphasis is on the terms of the agreement being
        adhered to and/or given effect as closely as possible. In
        other words, the Court may ask to do what has not been
        done. The court must first ensure that the remedies
B       provided for are exhausted. It is true as contended by Mr.
        Desai, that it is not mandatory for the Chief Justice or any
        person or institution designated by him to appoint the
        named arbitrator or arbitrators. But at the same time, due
        regard has to be given to the qualifications required by the
        agreement and other considerations.          •
                                                                                 -
c
        )()()()()()()()


               In all these cases at hand the High Court does not
        appear to have focused on the requirement to have due
0       regard to the qualifications required by the agreement or
        other considerations necessary to secure the appointment
        of an independent and impartial arbitrator. It needs no
        reiteration that appointment of the arbitrator or arbitrators
                                                                        •
                                                                             -
        named in the arbitration agreement is not a must, but while
E       making the appointment the twin requirements of Sub-
        section (8) of Section 11 have to be kept in view,
        considered and taken into account. If it is not done, ii":e
        appointment becomes vulnerable. In the circumstances, we
        set aside the appointment made in each case, remit the
F       matters to the High Court to make fresh appointments            ~    -
        keeping in view the parameters indicated above."

       11. In the aforesaid decision in the case of Northern
  Railway Administration (Supra), Arijit Pasayat: J. (as His
  Lordship then was}, found that the High Court in the said case
G did not appear to have focused on the requirement to have due
  regard to the qualifications required by the agreement or other
  conditions necessary to secure the appointment of an
  independent and impartial arbitrator. In the aforesaid decision,
  this Court also concluded that since the requirement of sub-
H section (8) of Section 11 was not at all dealt with by the High
        BHARAT SANCHAR NIGAM LTD. v. DHANURDHAR 407
           CHAMPATIRAY [TARUN CHATIERJEE, J.]
       Court in its order, the appointment of an arbitrator without A
       dealing with Sub-Section 8 of Section 11 of the Act became
       vulnerable and accordingly, such appointment was set aside.
       Similar is the position in this case. In this case also, before
       appointing an arbitrator under Section 11 (6) of the Act, the High
       Court had failed to take into consideration the effect of Section B
       11 (8) of the Act as was done in Northern Railway
       Administration (supra).
             12. In view of the discussions made hereinabove and
       particularly, in view of the principles laid down by this Court in C
       Northern Railway Administration (supra), we set aside the
       impugned order and remand the case back to the High Court
       for fresh decision of the application under Section 11 (6) of the
       Act and while considering the applicaticn afresh, the High Court
       is directed to take into consideration the aforesaid decision of
       this Court.                                                        D

           13, The appeals are allowed to the extent indicate above.
       There will be no order as to costs.
       D.G.                                   Appeals partly allowed.
                                                                         E




- -+


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.