BHARAT SANCHAR NIGAM LTD. & ANR.versusMOTOROLA INDIA PVT. LTD.
- Citation
- 2008 INSC 1038
- Decided
- 15 September 2008
- Disposal
- Dismissed
- Bench
- TARUN CHATTERJEE
Holding
Clause 16.2 is not an excepted matter; the appointing authority lost its right to appoint after the 30‑day period, and the provision making liquidated‑damages quantification final is void as it contravenes the Contract Act.
Summary
The appellant BSNL awarded a turnkey tender to Motorola and later imposed liquidated damages under clause 16.2 of the tender for alleged delay in delivery. Motorola contested the levy, invoking the arbitration clause, while BSNL claimed the matter was an "excepted matter" under clause 20.1 and therefore not arbitrable. The High Court held the liquidated‑damages clause was not excepted and ordered arbitration. On appeal, the Supreme Court examined whether the quantification of liquidated damages is an excepted matter, whether the appointing authority lost its right to appoint an arbitrator after a Section 11 petition, and whether the clause making the quantum final violated Sections 28 and 74 of the Contract Act. The Court held that clause 16.2 does not constitute an excepted matter, the appointing authority had lost its right to appoint after the 30‑day period, and the provision rendering the quantum unchallengeable is void as it restrains legal proceedings. Consequently, the High Court’s order was affirmed and the appeal dismissed.
Issues considered
- Whether the levy of liquidated damages under clause 16.2 is an "excepted matter" under clause 20.1 and thus outside the scope of arbitration.
- Whether the appointing authority retained the right to appoint an arbitrator after a petition under Section 11 of the Arbitration and Conciliation Act, 1996.
- Whether the clause making the quantification of liquidated damages final and unchallengeable violates Sections 28 and 74 of the Indian Contract Act, 1872.
- Whether clause 62 of the special conditions overrides clause 16.2.
- Whether the appellant’s failure to raise a timely objection under Section 4 of the Arbitration Act results in waiver of the right to object.
Legislation cited
- Arbitration and Conciliation Act, 1996s. 11, s. 12, s. 4
- Indian Contract Act, 1872s. 28, s. 74
Subjects
Judgment
[2008] 13 S.C.R. 445
BHARAT SANCHAR NIGAM LTD. & ANR. A
v.
MOTOROLA INDIA PVT. LTD.
(Civil Appeal No. 5645 of 2008)
SEPTEMBER 15, 2008
~' B
i [TARUN CHATTERJEE AND LOKESHWAR SINGH
PANTA, JJ.)
Arbitration and Conciliation Act, 1996:
s.11 - Excepted matter- Agreement speaking of /iabil- c
ity of supplier to pay liquidated damages to purchaser on ac-
count of delay in delivery - But not pmviding for any adjudi-
catory process for determining delay- Levy of liquidated dam-
ages - Held: Is not excepted matter and hence is arbitrable.
D
s.11 - Appointment of arbitrator - Limitation - lmposi-
tion of liquidated damages by supplier - Notice by purchaser
for appointment of arbitrator - Supplier/Appointing authority
failing to act within time prescribed under the Act - Petition
under s.11 by purchaser- Right of supplier to appoint arbitra-
tor - Held: Once minimum of 30 days had expired and peti- E
tion under s.11 is filed in the court, appointing authority loses
right to make appointment.
Contract Act, 1872: s.28 - Restraint of legal proceed-
ings - Provision in agreement that quantification of Liquidated F
~·
Damages by purchaser would be final and cannot be cha/-
/enged - Held: Such provision would be in violation of s. 28
and s. 74 of the Act.
The appellant awarded the tender for turnkey project
in favour of respondent and issued an Advance Purchase G
Order. The Purchase Order provided the terms for pay·
ment and the schedule for delivery of the goods. It also
provided for liquidated damages in the event of failure on
the part of respondent to meet with the delivery sched-
445 H
446 SUPREME COURT REPORTS [2008] 13 S.C.R.
A ule. Clause 16.2 of the general conditions of the tender
document provided for liquidated damages to the extent
of 0.5% of the value 'of the delayed quantity of the goods
and services for each week of delay or the part thereof
for a period of upto 10 weeks and thereafter charge 0.7%
B of the value of delayed quantity or part thereof, for a pe- • .
riod of upto 10 weeks thereafter. It was the case of appel-
lants that the respondent failed to complete phase I and
phase II of the project within the schedule as provided in
the tender document, and therefore, liquidated damages
c were imposed by the appellant under clause 16.2 of the
tender document. The respondents denied any such de-
lay and objected to the levy of liquidated damages. On
24th of March, 2006, the respondent invoked the arbitra-
tion clause by sending a letter to the appellants. The ap-
pellants in their reply did not concede and justified the
D
imposition of liquidated damages.
The respondent filed an arbitration application be-
fore the High Court for appointment of arbitrator under
section 11 of the Arbitration and Conciliation Act, 1996 in
E respect of the liquidated damages assessed by the ap-
pellant. The appellant alleged that the liquidated damages
assessed and quantified by the appellant under clause
16.2 of the tender document was an excepted matter as
per clause 20.1 of the said document and, therefore, not
F arbitrable. The High Court held that the imposition of liq- »
uidated damages by the appellant was not an "excepted
matter" and therefore, was subject to arbitration. Hence
the present appeal.
Dismissing the appeal, the Court
G
HELD: 1.1. From a bare reading of clause 16.2 of Sec-
tion Ill of the tender document, it is clear that if the ten-
derer fails to deliver the goods and services on turnkey
basis within the period prescribed, the purchaser shall
be entitled to recover liquidated damages and the quan-
H
BHARAT SANCHAR NIGAM LTD. &ANR. v. 447
MOTOROLA INDIA PVT. LTD.
tum of the liquidated damages assessed and levied by A
the purchaser would be final and not challengeable by
the supplier. The question to be decided is whether the
liability of the respondent to pay Liquidated Damages and
the ,~ntitlement of the appellant, to collect the same from
the respondent is an excepted matter for the purpose of B
clause 20.1 of the General Conditions of contract. The au-
thority of the purchaser to quantify the Liquidated Dam-
ages payable by the supplier arises once it is found that
the supplier is liable to pay the damages claimed. The
decision contemplated under clause 16.2 of the agree- c
ment is the decision regarding the quantification of the
Liquidated Damages and not any decision regarding the
fixing of the liability of the supplier. [Paras 9, 10] [458·E,F,
H; 459-A & B]
1.2. It is clear from the reading of clause 15.2 that the D
supplier is to be held liable for payment of liquidated dam-
ages to the purchaser under the said clause and not under
clause 16.2. It was not stated anywhere in clause 15 that the
question as to whether the supplier had caused any delay
in the matter of delivery will be decided either by the appel- E
lant or by anybody who has been authorized on the terms
of the agreement. Reading clause 15 and 16 together, it is
apparent that clause 16.2 will come into operation only after
a finding is entered in terms of clause 15 that the supplier is
liable for payment of liquidated damages on account of de· F
lay on his part in the matter of making delivery. Therefore,
clause 16.2 is attracted only after the supplier's liability is
fixed under clause 15.2. The question of holding a person
liable for Liquidated Damages and the question of quantify-
ing the amount to be paid by way of Liquidated Damages G
are entirely different. Fixing of liability is primary, while the
quantification, which is provided for under clause 16.2, is
secondary to it. [Para 10] [459-D,E,F & G]
1.3. There is no provision in the agreement, appar-
ent on the face of it, relating to a decision made by any H
448 SUPREME COURT REPORTS [2008] 13 S.C.R.
A specified authority on the issue of levy of Liquidated Dam-
ages, as is contemplated under clause 20.1 of the agree-
ment which is excepted from the purview of arbitration. It
is clear from Clause 20.1 that matters which will not fall
within the arbitration clause are questions, disputes or
B differences, the decision to which is specifically provided
under the agreement. Clause 16.2 is not a clause wherein
a.ny decision making power is specifically provided for
with regard to any question, dispute or difference between
tf'le parties relating to the existence of breach or the very
C lack of liability for damages, i.e. the levy of Liquidated
Damages. [Paras 10, 11J [459-G,H; 460-A,G,H; 461-A & BJ
Vishwanath Sood v. UOI (1989) 1 SCC 657; General
Manager, Northern Railway v. Sarvesh Chopra (2002) 4 SCC
45 - distinguished.
D Food Corporation of India v. Sreekanth Transport 1999(4)
' SCC 491; State of Kamataka v. Shree Rameshwara Rice Mills,
(1987) 2 sec 160- referred to.
1.4. Clause 16.2 cannot be treated as an excepted
E matter. Admittedly, it does not, provide for any adjudica-
tory process for decision on a question, dispute or differ-
ence, which is the condition precedent to lead to the stage
of quantification of damages nor is it a no claim or no li-
ability clause. The quantum of damages calculated by the
F appellant in respect of clause 16.2 of the tender document,
simply cannot have the effect of rendering all the above
disputes as not being arbitrable. The true essence of any
arbitration agreement is to arbitrate the matters in a cor-
dial way in respect of issues where there is a dispute be-
tween the parties. To construe such limited words in
G clause 16.2 as being so all encompassing would destroy
the very foundation of the bargain between the parties.
The appellant in the present case is acting in an unfair
way by seeking to exclude, from arbitration, what it has
agreed to arbitrate in the first place. [Paras 12, 13J [461-
H C,D; 462-A,B & CJ
BHARAT SANCHAR NIGAM LTD. & ANR. v. 449
)
MOTOROLA INDIA PVT. LTD.
2. The submission of appellants before this courtthat A
it was the appellant, which had the right to appoint the
arbitrator cannot be accepted. The respondent had in-
voked the arbitration clause on the ground that there was
no delay on its part by sending a letter to this effect to the
appellants on 24th of March, 2006. On 25th April, 2006, B
the appellants replied that they had rightly recovered the
Liquidated Damages and that the recovery of the dam-
ages was not arbitrable. The appointing authority in this
matter, i.e., CGM Kerala, did not respond to the notice re-
quiring the appointment of arbitrator and failed to act c
within the time prescribed under the Arbitration and Con-
ciliation Act 1996. Since the appointing authority ap-
pointed no arbitrator, the respondent filed a petition un- ·
der Section 11 of the said Act before the High Court. Once
a minimum of 30 days is expired and a petition is filed to
0
the court, the appointing authority loses the right to make
the appointment. Therefore, the appellant has now lost
its right to appoint any arbitrator for settling the disputes
under the agreement. Further, appellant had already taken
a decision as is evident from his letter dated 25th of April,
2006, that the appellant was right in imposing the liqui- E
dated damages and therefore, the question of such a per-
son becoming an arbitrator does not arise as it would not
satisfy the test of impartiality and independence as re-
quired under s.12 of the Arbitration and Conciliation Act,
1996. Moreover it would also defeat the notions laid down F
under the principles of natural justice wherein it has been
recognized that a party cannot be a judge in his own
cause. (Paras 15, 16] (462-F,G & H; 463•A,B,C,D & E]
Datar Switchgear v. Data Finance Lt. (2000) 8 SCC 151; G
Pun) Llyod Ltd. v. Petronet MHB Ltd. (2006) 2 SCC 638 -
relied on.
State of Karnataka v. Shree Rameshwara Rice Mills
(1987) 2 sec 160 - referred to.
H
450 SUPREME COURT REPORTS (2008] 13 S.C.R.
A__ 3. The provision under clause 16.2 that quantifica-
tion of the Liquidated Damages shall be final and cannot
be challenged by the supplier is clearly in restraint of le-
gal proceedings under s.28 of the Indian Contracts Act.
So the provision to this effect has to be held bad. [Para
B 17] [464-A]
4. Pursuant to s.4 of the Arbitration and Conciliation
Act, 1996, a party who knows that a requirement under
the arbitration agreement has not been complied with and
still proceeds with the arbitration without rais1ng an ob-
C . jection, as soon as possible, waives their right to object.
The High Court had appointed an arbitrator in response
to the petition filed by the appellant. At this point, the mat-
ter was closed unless further objections were to be raised.
If further objections were to be made after this order, they
D should have been made prior to the first arbitration hear- \_·
ing. But the appellant had not raised any such objections.
The appellant therefore had clearly failed to meet the
stated requirement to object to arbitration without d~lay.
As such their right to object is deemed to be waived. [Para
· E 18] [464-8,C & D]
5. The contention of the Respondent that Clause 62
referring to special clauses has an overriding effect on
Clause 16.2, cannot be accepted .. There is in fact no con-
flict between clause 62 and 16.2. Clause 62 has two parts
F in it. One part referring to the Liquidated damages and the
other part refers to incentives in case the respondent per-
forms its part of the contract within time. The part dealing
with Liquidated Damages under clause 62 in fact refers it
back to clause 16.2 dealing with the quantification of Liq-
G uidated Damages. So it is apparent that there is no dispute
between clause 62 and clause 16.2. [Para 19] [464-E & F]
Case Law Reference
1999(4) sec 491 referred to Para 7
H (1987) 2 sec 160 referred to Para 10
BHARAT SANCHAR NIGAM LTD. & ANR. v. 451
)
MOTOROLA INDIA PVT. LTD.
(1989) 1 sec 657 distinguished Para 12 A
(2002) 4 sec 45 distinguished Para 12
(2000) 8 sec 151 relied.on Para 15
(2006) 2 sec 638 relied on Para 15
(1987) 2 sec 160 referred to Para 16 B
CIVILAPPELLATE JURISDCTION: Civil Appeal No. 5645
of 2008
From the Judgment and Order dated 26.10.2006 of the
High Court of Kerala at Ernakulam in A.R. No. 18/2006 c
Gopal Subraminiam A.S.G., Mukul Rohtagi Maninder
Singh, Prathiba M. Singh, Sumeet Bhatia, Gaurav 5harma and
Yoginder Hondoo for the Appellants.
Dr. A.M. Singhvi, R.F. Nariman, Ciccu Mukhopadhya, Kirat D
Singh and Shadan Rarasat (for M/s. Suresh A.,Shroof & Co.)
for the Respondent
The Judgment of the Court was delivered by
TARUN CHATTERJEE, J. 1. Leave granted. E
2. This appeal is directed against the judgment and final
order dated 26th of October, 2006 of the High Court of Kera la at
Ernakulam in AR No 18 of 2006 whereby, the High Court had
allowed the prayer for appointment of the arbitrator at the in-
~
stance of the respondents and directed the parties to submit F
their disputes to arbitration.
3. The pivotal questions that need to be decided in this
appeal are:
i) Whether the levy of liquidated damages under clause G
16.2 of the tender document is an "excepted matter"
,.. in terms of clause 20.1 of the said document so that
the same cannot be referred to arbitration or looked
into by the arbitrator.
H
452 SUPREME COURT REPORTS [2008] 13 S.C.R.
A ii) Whether clause 62 of the special conditions of the
tender document will prevail over clause 16.2 of the
general conditions of the contract.
4. The relevant facts, which would assist us in appreciat-
ing the controversy involved are narrated in a nutshell, which ._
B are as follows:
The appellant had issued a notice inviting tender dated
4th of January, 2001, calling upon the eligible bidders for turn
key project on planning, engineering, supply, installation and
c commissioning of Indian Mobile Personal Communications Sys-
tem in the telecom circles of Kerala, Karnataka, Tamil Nadu
and Andhra Pradesh. The respondent submitted its bid in re-
sponse to the notice inviting tender and after the technical, com-
mercial and. fin,ancial bid evaluation, the respondent was
awarded th·e tender and an Advance Purchase Order (APO)
0
dated 5th of September, 2001 for phase I and Phase II was is-
sued to it by the appellant. The purchase order provided, inter
alia, the terms for payment and the schedule for delivery of the
goods. It also provided for liquidated damages in the event of
failure on the part of the respondent to meet with the delivery
E schedule. Clause 16.2 of the general conditions of the tender
document provided for liquidated damages to the extent of 0.5%
of the value of the delayed quantity of the goods and services
for each week of delay or the part thereof for a period of upto
10 weeks and thereafter charge 0. 7% of the value of delayed
F quantity or part thereof, for a period of upto 10 weeks thereaf-
ter. It is the case of the appellants that the respondent had failed
to complete phase I and phase II of the project within the sched-
ule as provided in the tender document, and therefore, liqui-
dated damages were imposed by the Tamil Nadu Circle of the
G appellant on 21•1 of May, 2004 under clause 16.2 of the tender
document, quantification of which was beyond the purview of
the arbitration agreement. There was an exchange of corre-
spondence between the Tamil Nadu Circle of the appellant al-
leging the delay in the purchase of goods and the respondents
H denying any such delay and objecting to the levy of liquidated
BHARAT SANCHAR NIGAM LTD. & ANR. v. 453
MOTOROLA INDIA PVT. LTD. [TARUN CHATIERJEE, J.]
damages. On 24th of March, 2006, the respondent invoked the A
arbitration clause by sending a letter through its counsel to the
appellants to which they did not concede and justified the im-
position of liquidated damages. The respondent filed an arbi-
tration application before the High Court of Kera la at Ernakulam
for the appointment of arbitrator under section 11 of the Arbitra- B
tion and Conciliation Act, 1996 in respect of the liquidated dam-
ages assessed by the appellant. In the counter affidavit filed in
the High Court, the appellant alleged that the liquidated dam-
ages assessed and quantified by the appellant under clause
16.2 of the tender document was an excepted matter as per c
clause 20.1 of the said document and, therefore, not arbitrable.
The High Court, as noted herein earlier, by the impugned judg-
ment allowed the arbitration request of the respondents hold-
ing that the imposition of liquidated damages by the appellant
was not an "excepted matter" and therefore, subject to arbitra-
0
tion. It is this judgment of the High Court, which is impugned in
this appeal, in respect of which leave has already been granted.
5. Before proceeding further, we deem it appropriate to
note the relevant clauses of the tender document and the pur-
chase order, which would assist us in determining whether the E
matters alleged are an excepted matt~r.
Clause 16.2 reads as under:-
"16.2. Should the tenderer fail to deliver the goods and
services on turn key basis within the period prescribed, F
"the purchaser shall be entitled to recover 0.5% of the
value of the delayed quantity of the goods & services, for
each week of delay or part thereof, for a period up to 10
weeks and thereafter at the rate of 0. 7% of the value of
the delayed quantity of the goods and services for each G
week of delay or part thereo(for another 10 weeks of
delay In the present case of turn key solution of supply,
installation and commissioning, where the delayed
portion of the delivery and provisioning of services
, materially hampers effective user of the systems, H
454 SUPREME COURT REPORTS [2008) 13 S.C.R.
A Liquidated Damages charged shall be levied as above
on the total value of the concerned package of the
purchase order. Quantum of liquidated damages
assessed and levied by the purchaser shall be final and
not challengeable by the supplier."
B Clause 20.1 which is the arbitration clause and provides
for excepted matters, i.e., those matters the decision to which
is specifically provided in the agreement itself reads as under:-
20. 1 In the event of any question, dispute or difference
c arising under this agreement or in connection there-with
(except as to the matters, the decision to which is
specifically provided under this agreement), the same
shall be referred to the sole arbitration of the CGM, Kera/a
Telecom Circle, BSNL or in case his designation is
changed or his office is abolished, then in such cases to
D
the sole arbitration of the officer for the time being
entrusted (whether in addition to his own duties or
otherwise) with the functions of the CGM, Kera/a Telecom
Circle, BSNL or by whatever designation such an officer
may be called (hereinafter referred to as the said officer),
E and if the CGM Kera/a Telecom Circle or the said officer
is unable or unwilling to act as such, then to the sole
arbitration of some other person appointed by the CGM,
Kera/a Telecom Circle or the said officer. The agreement
to appoint an arbitrator will be in accordance with the
F Arbitration and Conciliation Act, 1996.
There will be no objection to any such appointment on
the ground that the arbitrator is a Government Servant or
that he has to deal with the matter to which the agreement
relates or that in the course of his duties as a government
G
servant he has expressed his views on all or any of the
matters in dispute. The award of the arbitrator shall be
final and binding on both the parties to the agreement.
In the event of such an arbitrator to whom the matter is
originally referred, being transferred or vacating his office •
H
BHARAT SANCHAR NIGAM LTD. & ANR. v. 455
) MOTOROLA INDIA PVT. LTD. [TARUN CHATIERJEE, J.)
or being unable to act for any reason whatsoever, the A
CGM, Kera/a Telecom Circle, BSNL or the said officer
shall appoint another. person to act as an· arbitrator in
accordance with the terms of the agreement and the
person so appointed shall be entitled to proceed from
~ the stage at which it was left out by his B
pre decessors ... ...... . "
Clause 15.2 of Section 111 of the tender document, which deals
with the "delays in the supplier's performance" reads as under:
"Delay by the Supplier in the performance of its delivery c
obligations shall render the Supplier liable to any or all
. of the following sanctions, forfeiture of its performance
security, imposition of liquidated damages, and/or
termination of the contract for default".
Clause 62 of Section IV of the tender document which D
deals with liquidated damages and incentive reads as under:-
'The bidder shall be charged liquidated damages at the
rates as defined in the General conditions of contract as
contained in Section Ill for any delay in the turnkey job
entrusted to the bidder. However he shall be provided an · E
incentive @ 0. 5% of the cost of the network of each service
area (Telecom Circle), for each week of early commissioning
of the entire network in that service area, subject to a
maximum of 3% of the value of the contract of the circle".
F
6. Since this appeal arises out of an order, which appointed
an arbitrator, to decide the dispute referred to by the respon-
dent, we, in this appeal, need to decide that whether in view of
the arbitration clause in the tender document provided under
clause 20 of the said document, the breach specified in 16.2 is G
an "excepted matter".
7. Mr. Gopal Subramaniam, Additional Solicitor General
of India appearing on behalf of the appellant contended that in
view of the decision of this Court in Vishwa Nath Sood vs. UO/
[(1989) 1 sec 657], a conjoint reading of clause 16.2 and clause H
456 SUPREME COURT REPORTS (2008] 13 S.C.R.
A 20.1 would clearly show that clause 16.2 is covered under the
excepted matters as provided in clause 20.1 of the tender docu-
ment. He further contended that the High Court had erred in
holding that the quantification of the liquidated damages was
subsequent to the decision of liability of liquidated damages to
8 be payable to the appellant. Therefore, he contended that the
respondent had specifically subscribed to each and every clause
of the agreement without any objection at the tender stage and
accordingly, it was not open to them to claim immunity from the
contractual obligations. Thus, the matter in respect of which the
C respondent sought reference to arbitration was "excepted mat-
ter" in terms of clause 16.2 of the tender agreement.
In order to satisfy us in the aforesaid contentions, the learned
Additional Solicitor General, Mr. Gopal Subramanium placed
strong reliance in the case of Food Corporation of India Vs.
D Sreekanth Transport 1999 (4) SCC 491, which has given the
following principles relating to "Excepting matters" as under:- \..-
"1. These appeals by the grant of Special Leave pertains
to the effect of the usual 'excepted clause' vis-a-vis the
arbitration clause in a Government contract. While it is
E true and as has been contended, that the authorization
of the arbitrators to arbitrate, flows from the agreement
but the High Court in the judgment impugned thought it
fit to direct adjudication of 'excepted matters' in the
agreement itself by the arbitrators and hence these
F appeals before this Court.
2. At the outset, it is pertinent to note that in the usual
Government contracts, the reference to which would be
made immediately hereafter, there is exclusion of some
matters from the purview of arbitration and a senior officer
G of the Department usually is given the authority and power
to adjudicate the same. The clause itself records that
the decision of the senior officer, being the adjudicator,
shall be final and binding between the parties - this is
..
what popularly known as 'excepted matters' in a
H Government or Governmental agencies' contract.
)
BHARAT SANCHAR NIGAM LTD. & ANR. v. 457
MOTOROLA INDIA PVT. LTD. [TARUN CHATIERJEE, J.]
3. 'Excepted matters' obviously, as the parties agreed, A
do not require any further adjudication since the
agreement itself provides a named adjudicator -
concurrence to the same obviously is presumed by
.)
reason of the um~quivocal acceptance of the terms of
the contract by the parties and this is where the courts B
have found our lacking in its jurisdiction to entertain an
application for reference to arbitration as regards the
disputes arising therefrom and it has been the consistent
view that in the event the claims arising within the ambit
of excepted matters, 'question of assumption of c
;urisdiction of any arbitrator either with or without the
intervention of the court would not arise; the parties
themselves have decided to have the same adjudicated
by a particular officer in regard to these matters; what are
these exceptions however are questions of fact and
usually mentioned in the contract documents and forms
D
part of the agreement as such there is no ambiguity in
the matter of adjudication of these specialized matter;s
and termed in the agreement as the excepted matters ..... "
Keeping the aforesa.id principles in mind, let us proceed E
further.
We may keep on record that the appellants alleged that re-
spondents had not completed phase I and phase II of the project
within the schedule as provided in the tender document where-
upon the appellants had to impose liquidated damages and in- F
voke clause 16.2 of the tender document. But the respondents
refuted these allegations. The contention of the respondent in this
case was that the delay, if any, was caused due to the appellant's
, delay in supplying necessary inputs to the respondent. So the re-
spondent contends that it had performed its part of the contract in G
time and the blame for delay lies on the appellant. Thus it is to be
~· noted that there is a dispute between the parties on the question
whether any breach was committed in this case.
8. The appellant had contended before the High Court of
H
458 SUPREME COURT REPORTS [2008] 13 S.C.R.
A Kerala that the levy of the liquidated damages on the respon-
dent was a matter outside the purview of the scope of arbitra-
tion proceedings as it "squarely falls within the exception pro-
vided under Clause 20 of Section 111, being the matters for which
mode of decision is provided under the Agreement itself."
B The respondent on the other hand contended that the claim
of the petitioner that the dispute pertaining to levy of liquidated
damages falls outside the arbitration agreement being an ex-
cepted matter is fallacious.
c The High Court held that there was no reason why the ar-
bitration request on behalf of the respondent should not be al-
lowed. It held that clause 16.2 is not an excepted matter under
clause 20 of the tender document.
9. Having heard the learned counsel for the parties and
D after examining the judgment of the High Court and the other
materials on record, we are of the view that this appeal must be
dismissed. Clause 20 is the arbitration clause and provides that
any question, dispute or difference arising under this agreement
or in connection therewith would be referred to arbitration. To this,
E an exception is also provided which lays down that the matters,
the decision to which is specifically provided under this agree-
ment, would not be referred to arbitration. From a bare reading
of clause 16.2 of Section Ill of the tender document, it is clear that
if the tenderer fails to deliver the goods and services on turnkey
F basis within the period prescribed, the purchaser shall be en-
titled to recover liquidated damages and the quantum of the liq-
uidated damages assessed and levied by the purchaser shall
be final and not challengeable by the supplier.
10. We are in full agreement with the findings of the High
G Court that there was a dispute as to whether the respondent
had at all acted in breach of any terms and conditions of the
tender document.
The question to be decided in this case is whether the
H liability of the respondent to pay Liquidated Damages and the
BHARAT SANCHAR NIGAM LTD. &ANR. v. 459
MOTOROLA INDIA PVT. LTD. [TARUN CHATTERJEE, J.]
entitlement of the appellant, to collect the same from the re- A
spondent is an excepted matter for the purpose of clause 20.1
of the General Conditions of contract. The High Court has
pointed out correctly that the authority of the purchaser (BSNL)
to quantify the Liquidated Damages payable by the supplier
~ Motorolla arises once it is found that the supplier is liable to pay 8
the damages Claimed. The decision contemplated under clause
16.2 of the agreement is the decision regarding the quantifica-
tion of the Liquidated Damages and not any decision regard-
ing the fixing of the liability of the supplier. It is necessary as a
condition precedent to find that there has been a delay on the c
part of the supplier in discharging his obligation for delivery
under the agreement.
It is clear from the reading of clause 15.2 that the supplier
is to be held liable for payment of liquidated damages to the
purchaser under the said clause and not under clause 16.2. The D
~
High Court in this regard correctly observed that it was not stated
anywhere in clause 15 that the question as to whether the sup-
. plier had caused any delay in the matter of delivery will be de-
cided either by the appellant/BSNL or by anybody who has been
authorized on the terms of the agreement. Reading clause 15 E
and 16 together, it is apparent that clause 16.2 will come. into
operation only after a finding is entered in terms of clause 15 that
the supplier is liable for payment of liquidated damages on ac-
count of delay on his part in the matter of making delivery. There-
.:-, fore, clause 16.2 is attracted only after the supplier's liability is F
fixed under clause 15.2. It has been correctly pointed out by the
High Court that the question of holding a person liable for Liqui-
dated Damages and the question of quantifying the amount to
be paid by way of Liquidated Dmages are entirely different. Fix-
ing of liability is primary, while the quantification, which is pro-
G
vided for under clause 16.2, is secondary to it.
,. There is no provision in the agreement, apparent on the
face of it, relating to a decision made by any specified authority
on the issue of levy of Liquidated Damages, as is contemplated
under clause 20.1 of the agreement which is excepted from the H
460 SUPREME COURT REPORTS [2008] 13 S.C.R.
A purview of arbitration. No decision coming within the scope of
excepted matters under clause 20.1 is envisaged by any por-
tion of the agreement regarding the liability of the supplier to
liquidated damages.
Quantification of liquidated damages may be an excepted
8 matter as argued by the appellant, under clause 16.2, but for
the levy of liquidated damages, there has to be a delay in the
first place. In the present case, there is a clear dispute as to the
fact that whether there was any delay on the part of the respon-
dent. For this reason, it cannot be accepted that the appoint-
c ment of the arbitrator by the High Court was unwarranted in this
case. Even if the quantification was excepted as argued by the
appellant under clause 16.2, this will only have effect when th9
dispute as to the delay is ascertained.
D Clause 16.2 cannot be treated as an excepted matter because
of the fact that it does not provide for any adjudicatory process for ~'
decision on a question, dispute or difference, which is the condition
precedent to lead to the stage of quantification of damages.
The above stated position can be ascertained through the
E judgment of this Court in the case of State of Karnataka vs.
Shree·Rameshwara Rice Mills, (1987) 2 SCC 160. This Court
in the said case, made a clear distinction between adjudicat-
ing upon an issue relating to a breach of condition of contract
and the right to assess damages arising from a breach of con-
F dition. It was held that the right conferred to assess damages
arising from a breach of condition does not include a right to
,,
adjudicate upon a dispute relating to the very breach of condi-
tions and that the power to assess damages is a subsidiary
and consequential power and not the primary power.
G 11. Clause 20.1 regarding excepted matters reads "In the
event of any question, dispute or difference arising under this
agreement or in connection there-with (except as to the mat-
ters, the decision to which is specifically provided under this
agreement) ... ". Therefore it is clear from this provision, mat-
H ters which will not fall within the arbitration clause are questions,
BHARAT SANCHAR NIGAM LTD. & ANR. v. 461
MOTOROLA INDIA PVT. LTD. [TARUN CHATTERJEE, J.)
disputes or differences, the decision to which is specifically A
provided under the agreement. Clause 16.2 is riot a clause
where in any decision making power is specifically provided
for with regard to any question, dispute or difference between
the parties relating to the existence of breach or the very lack of
~ liability for damages, i.e. the levy of Liquidated Damages. B
12. The learned senior counsel for the appellant relied on
the decisions of this court in Vishwanath Sood vs. UOI [(1989)
1 SCC 657], and General Manager, Northern Railway vs.
Sarvesh Chopra [(2002) 4 sec
45]. These cases, we are
afraid, will not be of any help to the appellants being distinguish- c
able on facts and having different contractual clauses. We may
note that clause 16.2 cannot be treated as an excepted matter.
This is because admittedly, it does not, provide for any adjudi- .
catory process for decision on a question, dispute or difference,
which is the condition precedent to lead to the stage of quanti- D
.......
fication of damages nor is it a no claim or no liability clause.
In Vishwanath Sood's case (supra), it was held by this court
that a particular claim of the government was excluded because
the Superintendent Engineer acted as the revisional authority
to decide disputes between the two parties by an adjudicatory E
process, there being a complete machinery for settlement of
the disputes in the relevant clause and most importantly, the
Superintendent Engineer had the discretion on consideration
of the facts and circumstances including mitigating facts, held
no damages was payable. Again in the case of Sarvesh F
Chopra, this court had held that the claims covered by the no
claims clause, i.e., where the contractor had given up the right
to make a claim for breach on the part of the government was
not arbitrable in terms of the arbitration clause contained therein
and clause 63 of the general conditions of the contract which G
provided for exclusion because no claim clause was excepted
as such claims were simply not entertainable. In view of the dis-
·~
cussions made hereinabove, we hold that the disputes raised
by the respondents are arbitrable and not excepted from scope
of arbitration. H
462 SUPREME COURT REPORTS [2008] 13 S.C.R.
A 13. We feel that there are certain other issues that are to
be discussed while disposing of this appeal. The respondent
contended in its written submission filed before this court on
14th May, 2007 that the quantum of damages calculated by the
appellant in respect of clause 16.2 of the tender document, sim-
B ply cannot have the effect of rendering all the above disputes
as not being arbitrable. We find that there is considerable merit
in this argument. The true essence of any arbitration agreement
is to arbitrate the matters in a cordial way in respect of issues
where there is a dispute between the parties. To construe such
c limited words in clause 16.2 as being so all encompassing would
destroy the very foundation of the bargain between the parties.
The appellant in the present case is acting in an unfair way by
seeking to exclude, from arbitration, what it has agreed to arbi-
trate in the first place.
D 14. The appellant contended that it has the unilateral right
to determine the Liquidated damages under clause 16.2 and
that the quantum of Liquidated Damages decided by the ap-
pellant, even if it is exorbitant, would be final and cannot be
challenged. We find the contention of the respondent that if the
E said contention of the appellant is supported, it would mean
that a party would be held liable to damages of whatever amount
the other party demands without recourse to a remedy, to be
relevant and should be given due importance. Such a conten-
tion by the appellant would be in violation of Section 28 and
F Section 74 of the Indian Contract Act.
15. The learned counsel of the appellants had submitted
before this court that it was the appellant, which had the right to
appoint the arbitrator. This submission cannot be accepted. The
respondent had invoked the arbitration clause on the ground
G that there was no delay on its part by sending a letter to this
~ffect to the appellants on 24th of March, 2006. On 25th April,
2006, the appellants/BSNL replied stating that they had rightly
recovered the Liquidated Damages and that the recovery of
the damages was not arbitrable. The appointing authority in this
H matter, i.e., CGM Kerala, did not respond to the notice requir-
. ~'
BHARAT SANCHAR NIGAM LTD. & ANR. v. 463
MOTOROLA INDIA PVT. LTD. [TARUN CHATTERJEE, J.]
ing the appointment of arbitrator and failed to act within theJime A
prescribed under the Arbitration _and Conciliation Act 1996,.
Since the appointing authority appointed no arbitrator, the re-
spondenUMotorolla, on 25th. of May, 2006, filed a petition under
Section 11 of the said Act before the High Court at Kerala. In
the case of Oatar Switchgear vs. Data Finance Lt. [(2000) 8 B
SCC 151), which was affirmed in Punj Llyod Ltd. vs. Petronet
MHB Ltd. [(2006) 2 sec 638], it was held that once a minimum
of 30 days is expired and a petition is filed to the court, the
appointing authority loses the right to make the appointment.
Therefore, the appellanUBSNL has now lost its right to appoint c
any arbitrator for settling the disputes under the agreement.
16. Further, CGM Kerala Circle has already taken a deci-
sion as is evident from hisJetter dated 25th of April, 2006, that
the appellant was right in ifTll?OSing the liquidated damages and
therefore, the question of such a person becoming an arbitra- D
tor does not arise as it would not satisfy the test of impartiality
and independence as required under Section 12 of the Arbitra-
tion and Conciliation Act, 1996. Moreover it would also defeat.
the notions laid down under the principles of natural justice
wherein it has been recognized that a party cannot be a judge E
in his own cause. The judgment of this Court in State of
Karnataka vs. Shree Rameshwara Rice Mills, (1§HJ7) 2 SCC
160, is significant in this matter. The Court had stated:
"..... Even assuming that the terms of Clause 12 afford
scope for being construed as empowering the officer of F
the State to decide upon the question of breach as well
as assess the quantum of damages, adjudication by the
officer regarding the breach of the contract can not be
sustaine9 under law because a party to the agreement
cannot be an arbiter in his own cause. Interest of justice G
and equity require that where a party to a contract disputes
the committing of any breach of conditions the
adjudication should be by an independent person or
body and not by the other party to the contract".
H
464 SUPREME COURT REPORTS [2008] 13 S.C.R.
A 17. The provision under clause 16.2 that quantification of
the Liquidated Damages shall be final and cannot be challenged
by the supplier Motorolla is clearly in restraint of legal proceed-
ings under section 28 of the Indian Contracts Act. So the provi-
sion to this effect has to be held bad.
8 18. Pursuant to· section 4 of the Arbitration and Concilia-
tion Act, 1996, a party who knows that a requirement under the
arbitration agreement has not been complied with and still pro-
ceeds with the arbitration without raising an objection, as soon
as possible, waives their right to object. The High Court had
C appointed an arbitrator in response to the petition filed by the
appellant. At this point, the matter was closed unless further
objections were to be raised. If further objections were to be
made after this order, they should have been made prior to the
first arbitration hearing. But the appellant had not raised any
D such objections. The appellant therefore had clearly failed to
meet the stated requirement to object to arbitration without de-
lay. As such their right to object is deemed to be waived.
19. Finally we are of the opinion that the contention of the
Respondent that Clause 62 referring to special clauses has an
E overriding effect on Clause 16.2, cannot be accepted .. There
is in fact no conflict between clause 62 and 16.2. Clause 62
has two parts in it. One part referring to the Liquidated dam-
ages and the other part refers to incentives in case the respon-
dent/Motorolla performs its part of the contract within time. The
F part dealing with Liquidated Damages under clause 62 in fact
refers it back to clause 16.2 dealing with the quantification of
Liquidated Damages. So it is apparent that there is no dispute
between clause 62 and clause 16.2.
G 20. For the reasons aforesaid, we are of the view that the
High Court was justified in passing the impugned judgment and
there is no infirmity in the impugned order for which we can
.interfere with the order of the High Court. The appeal is there-
fore dismissed. There will be no order as to costs.
'- .
H D.G. Appeal dismissed.
Search Indian case law
Ask in plain English, not just keywords. 25,000 AI words free, no card.