Created byFuzzy Cloud

Supreme Court of India

CHATTERJEE PETROCHEM CO. & ANRversusHALDIA PETROCHEMICALS LTD. & ORS.

Citation
2013 INSC 817
Decided
10 December 2013
Disposal
Appeal(s) allowed

Holding

The arbitration clause in the principal agreement dated 12 January 2002 is valid and enforceable, and the injunction suit is unsustainable; the parties must resolve their dispute through ICC arbitration.

Summary

Chatterjee Petrochem (Mauritius) Co. invoked the arbitration clause in a restructuring agreement dated 12 January 2002, seeking ICC arbitration over a dispute with Haldia Petrochemicals Ltd. Haldia contended that a later agreement dated 8 March 2002, which granted exclusive jurisdiction to the Calcutta courts, nullified the earlier arbitration clause and sought a permanent injunction against arbitration. The Supreme Court examined whether the later agreements effected a novation of the original contract and whether Section 5 of the Arbitration and Conciliation Act, 1996 barred judicial interference. It held that the subsequent agreements were merely supplementary and did not extinguish the principal agreement or its arbitration clause, which remained valid and enforceable. Consequently, the suit for injunction was deemed unsustainable and dismissed, and the parties were directed to proceed with arbitration under the ICC Rules.

Issues considered

  • Whether the arbitration clause in Clause 15 of the January 12, 2002 agreement remains enforceable notwithstanding Clause 7.5 of the March 8, 2002 agreement granting exclusive jurisdiction to Calcutta courts.
  • Whether the suit filed by the respondent seeking a permanent injunction against arbitration is maintainable under the Arbitration and Conciliation Act, 1996.

Legislation cited

Subjects

Arbitration clause validityNovation of contractInjunction against arbitrationInternational Chamber of Commerce (ICC)Section 5 Arbitration and Conciliation ActJurisdiction of courtsSupplementary agreement

Judgment

                   [2013] 11 S.C.R. 1101


         CHATTERJEE PETROCHEM CO. & ANR                        A
                             v.
        HALDIA PETROCHEMICALS LTD~ & ORS.
            (Civil Appeal No. 10932 of 2013)
                  DECEMBER 10, 2013
                                                               B
     [G.S. SINGHVI AND V. GOPALA GOWDA, JJ.]

     Arbitration - Arbitration clause - Validity - Suit seeking
injunction against arbitration of disputes - Maintainability -
Appellant filed request for arbitration in the International C
Chamber of Commerce (ICC), Paris in relation to an
agreement of restructuring dated 12th January, 2002 by
invoking arbitration clause contained in Clause 15 of the
agreement dated 12th January, 2002 - Dispute as whether
Clause 7.5 of the subsequent Agreement dated 8th March, D
2002 invoking the exclusive jurisdiction of the courts of
Calcutta nullified the scope of arbitration as mentioned in the
agreement dated 12th January, 2002 - Suit filed by
respondents, seeking injunction against arbitration of disputes
between the parties - Maintainability - Held: In view of the E
clauses of the Principal Agreement dated 12th January 2002
and subsequent Agreements dated 8th March 2002 and 30th
July, 2004, read with section 5 of the A&C Act, it is clear that
the Arbitration clause in the Principal Agreement continued
to be valid in view of clause no. 6 of the Agreement dated 30th F
July, 2004 and also by virtue of its mention in different parts
of both the supplementary agreements dated 8th March, 2002
and 30th July, 2004 - Appellant thus entitled to invoke the
arbitration cfause. for settling their disputes - Since, the
arbitration clause was valid, suit filed by respondent no. 1 for
declaration and permanent injunction against arbitration of G
disputes between the parties unsustainable and liable to be
dismissed - Parties directed to resolve their disputes through
arbitration as mentioned in clause 15 of the letter of
                            1101                               H
    1102        SUPREME COURT REPORTS          [2013] 11 S.C.R.


A Agreement dated 12th January, 2002 in accordance with the
  Rules of ICC - Rules of Arbitration of the International
  Chamber of Commerce - Arbitration and Conciliation Act,
  1996 - ss. 5, 16 and 45.

      On 21st March, 2012, the appellant- CPMC filed a
8
  request for arbitration in the International Chamber of
  Commerce (ICC), Paris in relation to an agreement of
  restructuring entered into between CPMC, Government
  of West Bengal, West Bengal Industrial Development
  Corporation (WBIDC) and Haldia Petrochemical Limited
C (HPL) on 12th January, 2002. As per the agreement, the
  Government of West Bengal was to cause WBIDC to
  transfer existing shareholding to CPMC to ensure that
  CPMC holds 51% of the total paid up capital of HPL.

D      Clause 15 of the agreement dated 12th January, 2002
  provided for reference of all disputes, in any way relating
  to the said Agreement or to the business of or affair of
  HPL to the Rules of the ICC, Paris. The appellant sought
  to invoke the said arbitration clause contained in the
E agreement dated 12th January, 2002 and made a request
  for arbitration ..

       The respondent HPL, however, claimed that the
  Arbitration Agreement contained in clause 15 of the
  Agreement dated 12th January, 2002 was void and/ or
F unenforceable and/or had become inoperative and/or
  incapable of being performed; and filed a suit before the
  High Court of judicature at Calcutta praying that the
  arbitration clause in the agreement be declared as void.
G      The following issues arose for consideration of this
    Court in these proceedings:
           1.     Can the Arbitration clause under clause 15 of
                  the letter of Agreement dated 12th January,
                  2002 be invoked by the appellants and
H
     CHATIERJEE PETROCHEM CO. v. HALDIA               1103
            PETROCHEMICALS LTD.

           whether Clause 7.5 of the subsequent                A
           Agreement dated 8th March, 2002 invoking the
           exclusive jurisdiction of the courts of Calcutta
           nullify the scope of arbitration as mentioned in
           the previous agreement dated 12th January,
           2002?                                               B
     2.    Is the suit, filed by the respondents, seeking
           injunction against arbitration of disputes
           between the parties sought for by the
           appellants as per Clause 15 of the agreement        C
           dated 12th January, 2002 maintainable in law?

    Allowing the appeal, the Court
     HELD: 1.1. The submission made on behalf of the
respondents that the transfer of shares to CPIL (the           o
Indian counterpart of CPMC) instead of CPMC
substantially changed the legal rights and responsibilities
of the parties as per agreement, resulting in novation of
contract, is liable to be rejected. It is nowhere mentioned
in the letter dated 8th March, 2002 that transfer of shares    E
to CPIL instead of CPMC extinguished the old agreement
dated 12th January, 2002 to nullity. In fact, in the letter
dated 8th March, 2002, CPMC has been constantly
mentioned as a guarantor. It is only to this extent the
nature of agreement has changed. Clause 1 of the
supplementary agreeme·nt dated 30th July, 2004 goes to
                                                               F
show that CPIL Is an affiliate of CPMC. This is to say, that
by means of the letter dated 8th March,2002 CPMC
becomes a guarantor whereas CPIL becomes the
borrower. Therefore, the same does not change the rights
and responsibilities of the parties under the agreement        G
dated 12th January, 2002. Further, the contents of the
letter written by CPMC to WBIDC goes to show that the
agreement dated 12th January; 2002 remains the
principal agreement while agreement dated 8th March
2002 remains a supplementary agreement which was               H
    1104   SUPREME COURT REPORTS              [2013) 11 S.C.R.


A meant for restructuring of HPL on urgency. Further, and
  most importantly, an agreement was entered into
  between the parties dated 30th July, 2004. The
  subsequent Agreements dated 8th March, 2002 and 30th
  July, 2004 go to show that there was no alteration in the
B nature of rights and responsibilities of the parties
  involved in the contract. Consequently, there was no
  novation of the contract. [Paras 21, 22, 26, 27 and 28]
  [1115-F-G; 1116-A; 1117-C, E-F, H; 1118-A-B, E-F]

      1.2. It cannot be said that Section 5 of the Arbitration
C & Conciliation Act, 1996 which bars intervention by
  judicial authority in Arbitration Agreement will not be
  applicable to lnternatiol)al Agreements such as the
  present case. [Para 29) [111.8-F-G]

D      1.3. Further, it is pertinent to read Clause 7 .5 of the
  Agreement dated 8th March, 2002 carefully. The phrase
  'this agreement' in Clause 7.5 means that the Agreement
  dated 8th March, 2002 is essentially a supplementary
  Agreement and does not, by any means, make the
E Principal Agreement dated 12th January, 2002 subject to
  the jurisdiction of the Court. [Para 30) [1119-D, F]

       1.4. In view of the clauses of the Principal Agreement
  dated 12th January 2002 and subsequent Agreements
  dated 8th' March 2002 and 30th July, 2004, read with
F section 5 of the Arbitration & Conciliation Act, 1996, it is
  clear that the Arbitration clause in the Principal
  Agreement continued to be valid in view of clause no. 6
  of the Agreement dated 30th July, 2004 and also by virtue
  of its mention in different parts of both the supplementary
G agreements dated 8th March, 2002 and 30th July, 2004.
  Therefore, the arbitration clause mentioned in Clause 15
  of the Arbitration agreement dated January 12, 2002 is
  valid and the appellant is entitled to invoke the arbitration
  clause for settling their disputes. [Para 31) [1119-G-H;
H 1120-A-B]
    CHATTERJEE PETROCHEM CO. v. HALDIA                   1105
           PETROCHEMICALS LTD.

     Venture Global Engineering v. Satyam Computer               A
Services Ltd. and Anr. (2008) 4 SCC 190: 2008 (1) SCR 501
- relied on.
     Yograj Infrastructure Ltd. v. Ssang Yong Engineering and
Construction Co. Ltd. (2011) 9 SCC 735: 2011 (14) SCR            B
301; Bhatia International v. Bulk Trading S.A. and Anr. (2002)
4 SCC 105: 2002 (2) SCR 411; Bajaj Auto Ltd. v. TVS Motor
Company Ltd. (2009) 9 SCC 797: 2009 (14) SCR 548;
Shree Vardhman Rice & General Mills v. Amar Singh
Chawalwala (2009) 10 SCC 257;· Mi/met Oftho Industries &         C
Ors. v. Allergan Inc. (2004) 12 SCC 624: 2004 (2) Suppl.
SCR 586 and Dhariwal Industries Ltd. & Anr. v. M.S.S. Food
Products (2005) 3 SCC 63 - cited.

     2. It is the claim of the respondent no.3 that the suit
was filed by Respondent no. 1 under section 9 of CPC D
and not section 45 of the Arbitration & Conciliation .Act,
1996. Respondent no. 3 contended that the Calcutta High
Court (exercising its ordinary original jurisdiction) has the
jurisdiction (territorial as well as pecuniar}t) to entertain
the present suit under section 9 of CPC and grant of such E
interim injunctive relief as it deems fit under Order 39
Rules 1 and 2 of the CPC is permissible in law. This
contention is liable to be rejected. It is already held that
the Principal Agreement dated 12th January, 2002
continues to be in force with its arbitration clause in F
place. Also, section 5 of the A&C act will be applicable to
Part II of the Act as well. The Agreement dated 12th
January, 2002 remains valid and the arbitration clause,
with all fours, will be applicable to the parties concerned
to get their disputes arbitrated and resolved in the G
Arbitration as per the Rules of ICC. The fact that CPIL,
which initially was a non-signatory to the Agreement
does not jeopardize the arbitration clause in any manner.
Since, the arbitration clause is valid, suit filed by the
respondent no.1 for declaration and permanent
                                                              H
    1106   SUPREME COURT REPORTS                [2013] 11 S.C.R.


A injunction against arbitration of disputes between the
  parties is unsustainable in law and the suit is liable to be
  dismissed. [Paras 32, 33, 35, 36, 37) [1120-D, H; 1121-A-
  B, H; 1122-A-B, C; 1123-D)
       Chloro Controls India Pvt. Ltd. v. Severn Trent Water
B Purification Inc. and Ors. (2013) 1 SCC 641; Ganga Bai v.
  Vijay Kumar & Ors. (1974) 2 SCC 393: 1974 (3) SCR 882
  and SBP & Co. v. Pafel Engineering Ltd. & Anr. (2005) 8 SCC
  618: 2005 (4) Suppl. SCR 688 - referred to.
C      3. The parties are directed to resolve their disputes
  through arbitration as mentioned in clause 15 of the letter
  of Agreement dated 12th January, 2002 in accordance
  with the Rules of ICC. It is seen from the written
  submission of the appellants that they have already
o initiated an arbitration proceeding. In such case, the
  parties shall continue with the arbitration proceeding
  since the suit filed for permanent injunction against the
  arbitration proceeding is dismissed by setting aside the
  impugned judgment and final order passed by the High
E Court of judicature at Calcutta. [Para 38) [1123-E-G]
                       Case Law Reference:
       2011 (14) SCR 301          cited                Para 8
       2002 (2) SCR 411           cited                Para 10
F
       2008 (1) SCR 501           relied on            Para 11
       2009 (14) SCR 548          cited                Para 18
       (2009) 1o sec 251          cited                Para 18
       2004 (2) Suppl. SCR 586 cited                   Para 18
G
       (2005) 3 sec 63            cited                Para 18
       (2013) 1 sec 641           referred to          Para 19
       1974 (3) SCR 882           referred to          Para 32
H      2005 (4) Suppl. SCR 688 referred to             Para 34
      CHATTERJEE PETROCHEM CO. v. HALDIA                  1107
             PETROCHEMICALS LTD.
     CIVIL APPELLATE JURISDICTION : Civil Appeal No.               A
 10932 of 2013.

     From the Judgment & Order dated 04.06.2013 of the High
 Court of Calcutta in APO No. 13 of 2013.

      Dr. Abhishek Manu Singhvi, Sudipto Sarkar, Ashok Desai,      8
 R.S. Suri, K.K. Venugopal, C.A. Sundaram, Maushumi
 Bhattacharya, Amit Bhandari, Purnima Bhat Kak, Suruchi Suri,
 Pallavi Tayal, Anu Bindra, Amar Gupta, Ananya Kumar, Mayank
 Mishra, Sidharth Nair, Sidharth Sethi, Dheeraj Nair for the
 Appearing parties.                                        ·       C

      The Judgment of the Court was delivered by

        V. GOPALA GOWDA J. 1. On 21st March, 2012, the
  appellant Chatterjee Petrochem (Mauritius) Company               D
  (hereinafter referred to as 'CPMC') filed a request for
  arbitration in International Chamber of Commerce (ICC), Paris
  in relation to an agreement of restructuring which was entered
  into between CPMC, Government of West Bengal, West
  Bengal Industrial Development Corporation (in short 'WBIDC')
  and Haldia Petrochemical Limited (in short 'HPL') on 12th        E
  January, 2002. As per the Agreement, the Government of West
. Bengal was to cause WBIDC to transfer existing shareholding
  to CPMC to ensure that CPMC holds 51% of the total paid up
  capital of HPL. Clause 15 of the Agreement provides for
  reference of all disputes, in any way relating to the said       F
  Agreement or to the business of or affair of HPL to the Rules
  of the ICC, Paris.

      2. The respondent HPL on the other hand, claims that the
 Arbitration Agreement contained in clause 15 of the Agreement     G
 dated 12th January, 2002 is void and/ or unenforceable and/
 or has become inoperative and/or incapable of being
 performed.

      3. A dispute arose between the parties regarding the
 allotment of shares and the appellant filed Company i:>etition    H
    1108    SUPREME COURT REPORTS                 (2013] 11 S.C.R.


A No. 58 of 2009 before the Company Law Board (in short
  'CLB')on the grounds of oppression and mismanagement. The
  appellant also sought transfer of 155 million shares in favour
  of Chatterjee Petrochem (India) Pvt. Ltd. (in short "the CPIL"),
  the Indian counterpart of CPMC as was decided in the
B Agreement.

       4. The Company Petition was disposed of by the CLB by
  upholding the decision of the Company to allot 155 million
  shares by Indian Oil Corporation (in short 'IOC'). The transfer
C of 155 million shares to CPIL by WBIDC was also confirmed.
  The CLB further directed the Government of West Bengal and
  WBIDC to transfer 520 million shares held by thern in HPL to
  Chatterjee Groups.

        5. The Government of West Bengal preferred an appeal
0 against the said Order before the High Court of Judicature at
  Calcutta under the provisions of Section 1OF of the Company's
  Act, 1956. The High Court set aside the Order of the CLB on
  the ground that CPIL was not a member of HPL and the CLB
  could not have enforced its right under private contract entered
E into between CPIL and WBIDC for transfer of shares as the
  same could not be the subject matter of a petition under
  Section 397 of the Companies Act.

       6. Aggrieved by the same, the appellant preferred appeal
  Nos. 5416-5419, 5420, 5437 and 5440 of 2008 before this
F Court. Vide judgment dated 30.09.2011, this Court held that the
  claim of the appellant transferring shares to IOC has changed
  the private character of the Company and was not an act of
  oppression on the part of the Company. According to this Court,
  the transfer of shares to IOC was a result of failure on the part
G of the. appellant to infuse adequate funds into the Company by
  way of equity as promised and to participate in its rights issues.
  The Company was therefore, constraint to induct IOC as a
  member and the 155 million shares which was to be transferred
  to the appellant was instead transferred to the IOC. The relevant
H paragraph of the judgment reads as under:
   CHATTERJEE PETROCHEM CO. v. HALDIA     1109
PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]

  "103. The failure ofWBIDC and GoWB to register the 155          A
  million shares transferred to CP(l)PL could not, strictly
  speaking, be taken to be failure on the part of the
  Company, but it was the failure of one of the parties to a
  private arrangement to abide by its commitments. The
  remedy in such a case was not under Section 397 of the          B
  Companies Act. It has been submitted by both Mr.
  Nariman and Mr. Sarkar thateven if no acts of oppression
  had been made outagainst the Company, it would still be
  open to the learned Company Judge to grant suitable relief
  under Section 402 of the Act to iron out the differences that   c
  might appear from time to time in the running of the affairs
  of the Company. No doubt, in the Needle Industries case,
  this Court had observed that the behaviour and conduct
  complained of must be held to be harsh and wrongful and
  in arriving at such a finding, the Court ought not to confine   D
  itself to a narrow legalistic view and allow technical pleas
  to defeat the beneficial provisions of the Section, and that
  in certain situations the Court is not powerless to do
  substantial justice between the parties, the facts of this
  case do not merit such a course of action to be taken.
  Such an argument is not available to the Chatterjee Group,      E
  since the alleged breach of the agreements referred to
  hereinabove, was really in the nature of a breach between
  two members of the Company and not the Company itself.
   It is not on account of any act on the part of the Company
  that the shares transferred to CP(l)PL were not registered      F
  in the name of the Chatterjee Group. There was. therefore.
  no occasion for the CLB to· make any order either under
  Section 397 or 402 of the aforesaid Act. If. as was
  observed in M.S.D.C. Radharamanan's case (supra). the
  CLB had given a finding that the acts of oppression had         G
  not been established. it would still be in a position to pass
  appropriate orders under Section 402 of the Act. That.
  however. is not the case in the instant appeals."

                                (emphasis laid by this Court)     -H
    1110     SUPREME COURT REPORTS                 [2013] 11 S.C.R.


A      7. On this decision given by this Court, the appellant sought
  to invoke the arbitration clause contained in the agreement
  dated 12th January, 2002 and made a request for arbitration.
  The respondent no.1 on the other hand, filed a suit before the
  High Court of judicature at Calcutta praying that the arbitration
B clause in the agreement be declared as void.

          8. Learned senior counsel on behalf of the appe.llant Dr.
    Abhishek Manu Singhvi relied upon Clause 15 of the letter of
    agreement dated 12th January, 2002 to contend that any
C   dispute, difference or claims arising between the parties
    relating to this letter of agreement dated 12th January, 2002,
    or any construction or interpretation relating to the working of
    or the business of the respondent no.1, shall first make an
    endeavour to settle their disputes, differences etc. in
    accordance with the Rules of Arbitration of the International
D   Chamber of Commerce. Therefore, the learned senior counsel
    contended that the validity or existence of the arbitration
    agreement is to be decided by the Arbitration Tribunal in terms
    of Article 6 of the ICC Rules, 1998 which is pari-materia to
    Section 16 of the Arbitration and Conciliation Act, 1996 (in short
E   'A & C Act')and the Civil Court has no jurisdiction to decide
    on such issues. In support of this legal contention, the learned
    senior counsel relied upon the decision of this Court in Yograj
    Infrastructure Ltd. v. Ssang Yong Engineering and
    Construction Co. Ltd. 1 wherein it was held that the arbitration
F   shall be held as is mentioned in the agreement which in the
    present case, is at Paris.

        9. It is the further case of the appellant that the agreement
  dated 12th January, 2002 between the parties was not novated
G by the subsequent agreements. According to the appellant, the
  agreement dated 12th January, 2002 is the principal
  agreement, which was later followed by the supplemental
  agreements dated 8th March, 2002 and 30th July, 2004. The
  letter of agreement dated 8th March, 2002 did not create any
H 1. (2011)9SCC735.
     CHATIERJEE PETROCHEM CO. v. HALDIA     1111
  PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]

 independent legal right but was a mere direction from CPMC             A
 to transfer 155 million shares to its nominee CPIL to avoid
 delay. Therefore, according to the appellant, the letter of
 agreement dated 8th March 2002 provided that the terms and
 conditions of 12th January, 2002 agreement would continue to
 remain valid and subsisting between the parties. The relevant          B
 clauses will be mentioned in the reasoning portion of the
 judgment.

        10 .. The learned senior counsel relied upon Section 45 of
  the A & C ·Act to contend that the suit instituted. by the
  respon"dent No. 1 against the request of arbitration by the           C
  appellant is not maintainable in law. He further argued that the
  suit instituted by the respondent No. 1 to restrain a foreign
  arbitration for resolution of the disputes between the parties
  was in violation of Section 5 of the A & C Act which limits
  judicial authority's intervention in arbitration and therefore the    D
  impugned order of injunction passed by the High Court of
  Judicature at Calcutta was contrary to law and therefore, the
  same is liable to be set aside. In this regard, the learned senior
  counsel relied upon the three Judge Bench decision of this
  Court in Bhatia International v. Bulk Trading S.A. and Anr. 2         E
  to contend that section 5 of the A & C Act provides that no
. judicial authority shall intervene except where it is provided. The
   relevant paragraph will be extracted in the reasoning portion
  of the judgment.
                                                                        F
      11. Mr. Sudipto Sarkar, learned senior counsel also
 appearing on behalf of the appellant further contended that the
 maintainability of the arbitration of the disputes between the
 parties can be established by relying on the decision of this
 Court in Venture Global Engineering v. Satyam Computer
 Services Ltd. and Anr. 3 wherein it was held that Part I of the A      G
 & C Act will be applicable to international arbitrations as well.
 Therefore, Mr. Sarkar contended that the Arbitration clause will
 2.   c2002) 4 sec 105.
 3. (2008) 4 sec 190.                                                   H
    1112     SUPREME COURT REPORTS                   [2013] 11 S.C.R.


A   be a bar for judicial intervention in the present case in spite of
    the fact that it is an international arbitration as per the principal
    agreement which will be continued in force as per the terms of
    the supplemental agreements.

       12. On the other hand, it is the case of the respondent HPL ·
8
  that the arbitration agreement dated 12th January, 2002 is
  rendered void in respect of the claim for transfer of 155 million
  shares in favour of CPIL inasmuch as the parties had contracted
  out of their earlier agreement and the legal liability in respect
  thereof was redefined in the subsequent 8th March, 2002
C Agreement which provided for an exclusive jurisdiction to courts
  in Calcutta to decide dispute arising out of the said agreement.
  Therefore, it was pleaded by Mr. Ashok Desai, the learned
  senior counsel appearing on behalf of the respondent no. 1-
  HPL that once a party to an arbitration agreement seeks to
D adjudicate dispute before another forum and such forum arrives
  at a conclusive findings of fact in relation to the dispute then,
  the subsequent effort on the part of the same party to refer
  dispute for arbitration under ICC Rules would be vexatious and
  abuse of law and it shall be construed that the arbitration clause
E in the principal agreement has been rendered inoperative by
  the conduct of the party itself.

        13. The learned senior counsel for the respondent no. 1
  further claimed that Section 5 of the A & C Act can come into
F play only when existence of a valid arbitration agreement is
  established. Institution of such a suit by the respondent no.1
  would constitute an "action pending before the judicial authority"
  necessitating the invocation of Section 45 of the A & C Act, if
  one of the parties makes a request to refer the matter for
G arbitration. In such cases, the court must see whether the
  arbitration agreement is valid, operative and capable of being
  performed, before ·referring the parties to arbitration.

      14. It is the further case of respondent no.1 that the
  subsequent agreement through letter dated 8th March 2002, in
H respect of transfer of 155 million shares of HPL, new rights and
    CHATTERJEE PETROCHEM CO. v. HALDIA     1113
 PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]

liabilities were created by and between the non- parties to the           A
arbitration agreement. The new agreement also provided for
a different dispute resolution mechanism among the parties,
that is, the courts in Calcutta. The relevant clause will be
extracted in the reasoning portion of the judgment.
                                                                          B
     15. The learned senior counsel, Mr. K.K. Venugopal,
appearing on behalf of Respondent no. 2, Govt. of West
Bengal, contended that the Arbitration and Conciliation Act,
1996 does not apply to the present case. According to the
learned senior counsel, a party may purport to appoint an                 C
arbitrator who may enter upon the arbitration even when there
is serious dispute as to whether the arbitration clause exists.
In spite of the fact that no arbitration clause exists, if a party
resorts to arbitration, then neither section 8 nor section 45 of
the A & C Act in case of international arbitration would provide
for adjudication of the issue as to whether the arbitration clause        D
exists. It is only where a suit has first been filed, in point of time,
on the substantive agreement or the underlying agreement,
either by way of specific performance or for compensation for
breach of contract, that section 8 or section 45 of the A & C
Act would come into play. However, we are not inclin.ed to                E
comment on this contention since it is not pertinent to the case.

      16. The learned senior counsel for Respondent no. 2 also
contended that when no arbitration clause exists in the
agreement, the matter cannot be adjudicated either under Part             F
I or Part II of the A & C Act rather, the matter can be adjudicated
only by an independent suit seeking injunction against the party
who had initiated arbitration, from proceeding with the
arbitration.

      17. It is further the case of the learned senior counsel, Mr.       G
K.K. Venugopal that the facts of the present case are
extraordinary and that the matter has been extensively litigated
in the previous round both, before the Company Law Board and
the appellate proceedings thereof. At no point in time did the
Chatterjee Group or any of its constituent affiliate, saved or            H
     1114      SUPREME COURT REPORTS              [2013] 11 S.C.R.


A reserved their right to seek arbitration under the alleged
  Arbitration Agreement which they now seek to enforce. This
  Court has already declined the reliefs on merit as well as on
  the point of jurisdiction. Therefore, he submits that at this
  juncture, invoking the arbitration clause from the principal
B agreement by the Chatterjee Group disregarding the
  Agreement dated 8th March, 2002, is clearly vexatious and
  abuse of the process of law. Therefore, the suit filed by
  respondent no. 1 seeking injunction relief on arbitration is
  maintainable in law.
c       18. It is further the case of the learned senior counsel on
   behalf of Respondent no.2 that the matter has been elaborately
  argued before this Court on complicated issues of law which
  arise for determination in the case. It is therefore, submitted by
  him that in such an event this Court would not render findings
D on questions of law while disposing an appeal against the
  interlocutory order so as to give finality in such findings. This
  approach of the Court is adopted in many cases arising under
  the Intellectual Property law, namely Bajaj Auto Ltd. v. TVS
  Motor Company Ltd. 4 , Shree Vardhman Rice & General Mills
E v. Amar Singh Chawalwala 5, Mi/met Oftho Industries & Ors.
  v. Allergan Inc. 6 and Dhariwal Industries Ltd. & Anr. v. M. S.S.
  Food Products? We are inclined to mention at this stage that
  in this appeal we are confined to deciding upon the validity of
  the arbitration clause in the principal agreement dated 12th
F January, 2002 only. Hence, this contention does not require to
  be addressed in this appeal.

       19. The learned senior counsel for respondent No. 3 Mr.
  C.A. Sundaram contends that jurisdictional issue in the present
G case, shall be decided as the threshold issue in the present
  case. In relation to this, he placed reliance upon the three Judge
    4.   (2009) 9 sec (para 5).
    5.   (2009) 10 sec 257 (para 2)
    6.   (2004) 12 sec 624 (paras 9 to 11)
H   7.   (2005) 3 sec 63 (para 20).
    CHATTERJEE PETROCHEM CO. v. HALDIA     1115
 PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]

Bench decision of this Court in Chloro Controls India Pvt. Ltd.      A
v. Severn Trent Water Purification Inc. and Ors. 8

     20. In the light of the facts and circumstances presented
before us on the basis of admitted documents on record, and
also based on the legal contentions urged by the learned senior      8
tounsel on behalf of both the parties, the following issues would
arise for consideration of this Court in these proceedings:

      1. Can the Arbitration clause under clause 15 of the letter
      of Agreement dated 12th January, 2002 be invoked by the
      appellants and whether Clause 7.5 of the subsequent            C
      Agreement dated 8th March, 2002 invoking the exclusive
      jurisdiction of the courts of Calcutta nullify the scope of
      arbitration as mentioned in the previous agreement dated
      12th January, 2002?
                                                                     D
      2. Is the suit, filed by the respondents, seeking injunction
      against arbitration of disputes between the parties sought
      for by the appellants as per Clause 15 of the principal
      agreement referred to supra maintainable in law?

      3. What Order?                                                 E

Answer to Point no.1

     21. We are inclined to reject the submission made by the
learned senior counsel on behalf of the respondents that the
                                                                     F
transfer of shares to CPIL instead of CPMC substantially
changes the legal rights and responsibilities of the parties as
per agreement referred to supra thereby, resulting in novation
of contract.

      22. It is nowhere mentioned in the letter d;:ited 8th March,   G
2002 that transfer of shares to CPIL instead of CPMC
extinguishes the old agreement dated 12th January, 2002 to
nullity. In fact, in the letter dated 8th March, 2002, CPMC has

a.   (2013) 1 sec 641.                                               H
    1116      SUPREME COURT REPORTS                [2013] 11 S.C.R.


A   been constantly mentioned as a guarantor. It is only to this
    extent the nature of agreement has changed.

       23. It is argued by the learned senior counsel Mr. C.A.
  Sundaram, appearing on behalf of Respondent no.3 that the
B concurrent findings of facts on the prima facie case by the
  learned single Judge and the Division Bench of the High Court
  of Calcutta have held that there has been a novation of
  agreement between the parties to the principal agreement
  dated 12th January,2002 by the subsequent agreements dated
C 8th March, 2002 and 30th July, 2004.

        24. It has been held by the learned single Judge of the
    Calcutta High Court that:

         " ...... This is a case, where by express words the parties
D        have altered their obligations by a new agreement on 8th
         March, 2002 with a term that the Courts in Kolkata 'alone'
         would have jurisdictions. This was affirmed by the 30th July,
         2004 agreement. This put an end to the arbitration, once
         and for all. Therefore, the arbitration clause in the 12th
         January, 2002 agreement was abrogated by the 8th March
E
         agreement. Abrogation of an arbitration agreement could
         not be made in clearer terms ... ".

         25. Further, the Division Bench of Calcutta High Court vide
    impugned judgment dated 12th January 2012, made the
F   following observations:

           (a.)   Agreement of 12th January 2002 was substituted
                  by agreements of March 8, 2002 and July 30, 2004.

           (b.)   Such a subsequent agreement completely
G                 extinguished the rights existing under the January
                  12, 2002 agreement and also destroyed the
                  arbitration clause.

           (c.)   Remedy is under Agreement of March 8, 2002
H                 which does not provide for Arbitration but states
    CHATTERJEE PETROCHEM CO. v. HALDIA     1117
 PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]
             that courts at Calcutta alone shall have jurisdiction.   A

      (d.)   Agreement of March 8, 2002 is not an ancillary to
             agreement of January 12, 2002 but materially alters
             the same. The principle laid down in Chloro
             Controls Case (supra) does not apply. Real               8
             intention of the parties in the instant case was to
             substitute one agreement with another.

     26. Clause 1 of the supplementary agreement dated 30th
July, 2004 reads as under:
                                                                      c
    "Pursuant to the said Principal Agreement GoWB has
    caused WBIDC to transfer to Chatterjee Petrochem (India)
    Private Limited (CPIL), an affiliate of CPMC Rs. 155
    crores of shares from the shareholding of WBIDC existing
    on the date of principal agreement. .. "                          D
                                    (emphasis laid by this Court)

The abovementioned clause goes to show that CPIL is an
affiliate of CPMC. This is to say, that by means of the letter
dated 8th March,2002 CPMC becomes a guarantor whereas                 E
CPIL becomes the borrower. Therefore, the same does not
change the rights and responsibilities of the parties under the
agreement dated 12th January, 2002.

     27. Further, the letter written by CPMC to WBIDC along
                                                                      F
with the agreement dated 8th March, 2002 reads as follows:

    "... It is clarified that the aforesaid shall not prejudice any
    of our rights under the said Agreement dt. January
    12. 2002 and all terms and conditions thereof shall
    continue to remain valid, binding and subsisting                  G
    between the parties to be acted upon sequentially".

                                    (emphasis laid by this Court)

The content of this letter goes to show that the agreement dated      H
    1118     SUPREME COURT REPORTS                 [2013] 11 S.C.R.

A   12th January, 2002 remains the principal agreement while
    agreement dated 8th March 2002 remains a supplementary
    agreement which was meant for restructuring of HPL on
    urgency.

         28. Further, and most importantly, the agreement entered
8
    into between the parties dated 30th July, 2004 states as follows:

         "WHEREAS the Parties hereto had entered into an
         agreement dated January 12, 2002 (hereinafter referred
         to as the principal agreement. ... "
c
    Also, the Agreement dated 30th July, 2004 which is based on
    shareholding issues, also notes through clause 6 that:

         "6. The Parties hereby agree, record and confirm that all
         other terms and conditions as contained in the said
D        Principal Agreement shall remain binding.
         subsisting, effective. enforceable and in force between
         the parties."

                                       (emphasis laid by this Court)
E
  The abovementioned clauses of the subsequent Agreements
  dated 8th March, 2002 and 30th July, 2004 go to show that
  there has been no alteration in the nature of rights and
  responsibilities of the parties involved in the contract.
F Consequently, there has been no novation of the contract.

        29. It has been further argued by the learned senior counsel
  for the respondents that Section 5 of the A & C Act, which bars
  intervention by judicial authority in Arbitration Agreement will not
  be applicable to International Agreements such as the present
G case. We are inclined Jo'~reject this contention by placing
  reliance upon the legal principle laid down by this Court in
  Venture Global Engineering case (supra), the relevant
  paragraph of which reads as under:                 '

         "25 ....... In order to find out an answer to the first and
H
    CHATIERJEE PETROCHEM CO. v. HALDIA     1119
 PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]

    prime issue and whether the decision in Bhatia                    A
    lntemational (supra) is an answer to the same, let us go
    into the details regarding the suit filed by the appellant as
    well as the re!evant provisions of the Act. The appellant -
    VGE filed O.S. No. 80 of 2006 on the file of the 1st
    Additional District Court, Secunderabad, for a declaration        B
    that the Award dated 3.4.2006 is invalid, unenforceable
    and to set aside the same. Section 5 of the Act makes it
    clear that in matters governed by Part I, no judicial authority
    shall intervene except where so provided. Section 5 which
    falls in Part I, specifies that no judicial authority shall       c
    intervene except where so provided. The Scheme of the
    Act is such that the general provisions of Part I. including
    Section 5. will apply to all Chapters or Parts of the Act."

                                   (emphasis laid by this Court)
                                                                      D
      30. Further, it is pertinent to read Clause 7.5 of the
Agreement dated 8th March, 2002 carefully. Clause 7.5 reads
thus:

    "Jurisdiction: Courts at Calcutta alone shall have                E
    jurisdiction in all matters relating to this Agreement."

The phrase 'this agreement' means the Agreement dated 8th
March, 2002 which is essentially a supplementary Agreement
and does not, by any mean, make the Principal Agreement
dated 12th January, 2002 subject to the jurisdiction of the Court.    F
     31. Therefore, we are of the opinion that both the learned
single Judge and the Division Bench erred in arriving at the
conclusion mentioned above and their findings are liable to be
set aside. In the light of the case mentioned above and also          G
on the basis of the clauses of the Principal Agreement dated
 12th January 2002 and subsequent Agreements dated 8th
March 2002 and 30th July, 2004, read with section 5 of the A&C
Act, we are inclined to observe that the Arbitration clause in
the Principal Agreement continued to be valid in view of clause
                                                                      H
    1120     SUPREME COURT REPORTS                   [2013] 11 S.C.R.


A no. 6 of the Agreement dated 30th July, 2004 and also by virtue
  of its mention in different parts of both the supplementary
  agreements dated 8th March, 2002 and 30th July, 2004.
  Therefore, the arbitration clause mentioned in Clause 15 of the
  Arbitration agreement dated January 12, 2002 is valid and the
B appellant is entitled to invoke the arbitration clause for settling
  their disputes. We, therefore, answer the point no.1 in favour
  of the appellant.

    Answer to Point nos.2 and 3

C        32. We answer point nos. 2 and 3 together since they are
    interrelated.

        It is the claim of the respondent no.3 that the suit was filed
    by Respondent no. 1 under section 9 of CPC and not section
0   45 of the A&C Act. Respondent no.3 further placed reliance
    upon the decision of this Court in Ganga Bai v. Vijay Kumar
    & Ors9 • to hold that:

         "15 .... There is an inherent right in every person to bring
         suit of a civil nature and unless the suit is barred by statute
E        one may. at ones peril. bring a suit of one's choice. It is
         no answer to a suit, howsoever frivolous the claim, that the
         law confers no such right to sue. A suit for its maintainability
         requires no authority of law and it is enough that no statute
         bars the suit. But the position in regard to appeals is quite
F        the opposite. The right of appeal inheres in no one and
        'therefore an appeal for its maintainability must have the
         clear authority of law. That explains why the right of appeal
         is described as a creature of statute."

G                                 (emphasis supplied by this Court)

    Therefore, the learned senior counsel appearing on behalf of
    respondent no. 3 places reliance upon this decision to contend


H 9. (1974) 2 sec 393.
    CHATIERJEE PETROCHEM CO. v. HALDIA     1121
 PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]

that the Calcutta High Court (exercising its ordinary original          A
jurisdiction) has the jurisdiction (territorial as well as pecuniary)
to entertain the present suit under section 9 of CPC and grant
of such interim injunctive relief as it deems fit under Order 39
Rules 1 and 2 of the CPC is permissible in law.
                                                                        B
     33. We are inclined to reject this contention raised by the
learned senior counsel appearing on behalf of Respondent no.
3. A careful reading of the decision leaves no doubt in the mind
as has been held in Ganga Bai's case (supra) that:

     "15 .... There is an inherent right in every person to bring       C
     suit of a civil nature and unless the suit is barred by statute
     one may. at ones peril. bring a suit of one's choice ...... "

                                    (emphasis laid by this Court)

    34. The learned senior counsel for respondent no. 3 further         D
places reliance upon the Constitution Bench decision of seven
Judges in SBP & Co. v. Patel Engineering Ltd. & Anr10•
wherein it was held that:

     "19 ..... When the defendant to an action before a judicial        E
     authority raises the plea that there is an arbitration
     agreement and the subject matter of the claim is covered
     by the agreement and the plaintiff or the person who has
     approached the judicial authority for relief, disputes the
     same, the judicial authority, in the absence of any                F
     restriction in the Act, has necessarily to decide whether,
     in fact, there is in existence a valid arbitration agreement
     and whether the dispute that is sought to be raised before
     it, is covered by the arbitration clause .... "

                                    (emphasis laid by this Court)       G

    35. We have already held that the Principal Agreement
dated 12th January, 2002 continues ·to be in force with its

10. c2oos) a sec s1s.                                                   H
    1122       SUPREME COURT REPORTS               [2013) 11 S.C.R.


A   arbitration clause in place. We have also mentioned, while
    answering point no. 1, that section 5 of the A&C act will be
    applicable to Part II of the Act as well. The Agreement dated
    12th January, 2002 remains valid and the arbitration clause,
    with all fours, will be applicable to the parties concerned to get
9   their disputes arbitrated and resolved in the Arbitration as per
    the Rules of ICC. The contention raised by the learned senior
    counsel for Respondent no.2, Mr. K.K. Venugopal regarding
    the maintainability of the suit while examining the interlocutory
    order in the appeals, is therefore, untenable in law.
c          c

       36. Tnefact that CPIL, which initially was a non-signatory
  to the Agreement does not jeopardize the arbitration clause in
  any manner. In this connection, we are inclined to record an
  observation made in the three Judge Bench decision of this
  Court in Chloro Controls India Pvt. Ltd. (supra), wherein it was
D held as under:

        "107. If one analyses the above cases and the authors'
        views, it becomes abundantly clear that reference of even
        non-signatorv parties to arbitration agreement can be
E       made. It may be the result of implied or specific consent
        or judicial determination. Normally. the parties to
        the arbitration agreement calling for arbitral reference
        should be the same as those to the an action. But this
        general concept is subject to exceptions which are that
F       when a third partv. i.e. non-signatory party. is claiming or
        issued as being directly affected through a party to
        the arbitration agreement and there are principal and
        subsidiary agreements. and such third party is signatory
        to a subsidiary agreement and not to the mother_or
        principal agreement which contains the arbitration clause.
G
        then depending upon the facts and circumstances of the
        given case. it may be possible to say that even such third
        party can be referred to arbitration."

                                      (Emphasis laid by this Court)
H
    CHATTERJEE PETROCHEM CO. v. HALDIA     1123
 PETROCHEMICALS LTD. [V. GOPALA GOWDA, J.]

     37. The respondent no.1 has filed a suit seeking two             A
remedies against the appellants: firstly, that the Arbitration
Agreement contained in Clause 15 of the Agreement dated
January 12, 2002 isvoid and/or unenforceable and/or has
become inoperative and/or incapable of being performed, and
secondly, the respondent no.1 sought permanent injunction             B
restraining the appellant herein from initiating and/ or continuing
with the impugned Arbitration proceedings bearing case no.
18582/ARP pursuant to the Impugned Arbitration Agreement
contained in clause 15 of the Agreement dated January 12,
2002 and the Request for Arbitration dated March 21, 2012             c
and the communication dated April 02, 2012 issued by
defendant no. 8 in the Arbitration proceedings connected
therewith and incidental thereto.

      Since, we have already held that the arbitration clause is
valid, suit filed by the respondent no.1 for declaration and          D
permanent injunction is unsustainable in law and the suit is
liable to be dismissed.

     38. In view of the above, we direct the parties to resolve
their disputes through arbitration as mentioned in clause 15 of       E
the letter of Agreement dated 12th January, 2002 in accordance
with the Rules of ICC. We have also seen from the written
submission of the appellants counsel that the appellants have
already initiated an arbitration proceeding. In such case, the
parties shall continue with the arbitration proceeding since the      F
suit filed for permanent injunction agaLnst the arbitration
proceeding is dismissed by setting aside the impugned
judgment and final order in A.P.O. No. 13 of 2013 passed by
the High Court of judicature at Calcutta on 04.06.2013.
Accordingly, the appeal is allowed, but no costs.
                                                                      G
B.B.B.                                           Appeal allowed.


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration clause validity"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.