Created byFuzzy Cloud

Supreme Court of India

DELHI AIRPORT METRO EXPRESS PVT. LTD.versusDELHI METRO RAIL CORPORATION LTD.

Citation
2021 INSC 464
Decided
9 September 2021
Disposal
Disposed off

Holding

Courts may set aside an arbitral award only on the limited grounds enumerated in Section 34, and the High Court's finding of patent illegality and perversity was erroneous, so the arbitral award is restored.

Summary

The Delhi Airport Metro Express Pvt. Ltd. (DAMEPL) and Delhi Metro Rail Corporation Ltd. (DMRC) entered into a concession agreement for the Airport Metro Express Line. DMRC was served a termination notice for alleged defects in the civil structure, which DAMEPL claimed were not cured within the 90‑day period, leading to an arbitral tribunal awarding DAMEPL Rs.2782.33 crore as termination payment. DMRC challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996, alleging patent illegality, perversity, and conflict with public policy, and the Delhi High Court partially set aside the award. The Supreme Court held that courts may interfere only on the limited grounds in Section 34 and must not re‑appreciate facts or law; the High Court’s finding of patent illegality and perversity was erroneous. Consequently, the arbitral award was restored in full, the High Court’s decision set aside, and the appeal by DAMEPL allowed while the cross‑appeal by DMRC was dismissed.

Issues considered

  • The scope of judicial interference under Section 34(2‑A) of the Arbitration and Conciliation Act, 1996, particularly the meaning of 'patent illegality' and 'perversity'.
  • Whether the arbitral tribunal erred in interpreting Article 29.5.1 of the concession agreement regarding the 90‑day cure period and the validity of the termination notice.
  • The correctness of the tribunal's computation of 'Adjusted Equity' and the inclusion of Rs.611.95 crore as equity.
  • The binding effect of the CMRS safety certificate on the arbitral tribunal's findings.
  • Whether DAMEPL waived its right to terminate by participating in post‑notice meetings and operating the line.
  • The propriety of awarding interest on the termination payment and the claim of unjust enrichment.
  • Whether the award conflicted with the public policy of India.

Legislation cited

Subjects

ArbitrationSection 34Patent illegalityPublic policyArbitral awardTermination noticeAdjusted equityConcession agreementWaiverSpecific performanceInterest award

Judgment

984                       [2021]
               SUPREME COURT     5 S.C.R. 984
                              REPORTS                         [2021] 5 S.C.R.


A              DELHI AIRPORT METRO EXPRESS PVT. LTD.
                                         v.
                 DELHI METRO RAIL CORPORATION LTD.
                          (Civil Appeal No. 5627 of 2021)
B                             SEPTEMBER 09, 2021
         [L. NAGESWARA RAO AND S. RAVINDRA BHAT, JJ.]
             Arbitration and Conciliation Act, 1996: s. 34 – Interference
      with the arbitral award – Scope of – On facts, arbitration clause
      invoked on account of dispute pertaining to Metro Rail project
C
      between the parties – Arbitral tribunal held the termination notice
      issued by the appellant was valid and on basis of ‘Adjusted Equity’
      passed an award of Rs.2782.33 crore, along with interest, in favour
      of the appellant – Single Judge of the High Court dismissed the
      petition u/s. 34 for setting aside the award – However, the Division
D     Bench partly set aside the award – On appeal, held: While deciding
      applications u/s. 34, the courts are mandated to strictly act in
      accordance with and within the confines of s. 34, refraining from
      appreciation or re-appreciation of matters of fact as well as law –
      Courts do not sit in appeal against the arbitral award – Permissible
      grounds for interference with a domestic award u/s. 34(2-A) on the
E
      ground of patent illegality is when the arbitrator takes a view which
      is not a possible one, or interprets a clause in the contract which no
      fair-minded or reasonable person would, or commits an error of
      jurisdiction by wandering outside the contract and dealing with
      matters not allotted to them – Conclusions of the arbitrator which
F     are based on no evidence or have been arrived at by ignoring vital
      evidence are perverse and can be set aside on the ground of patent
      illegality – Also, consideration of documents which are not supplied
      to the other party is a facet of perversity falling within the expression
      ‘patent illegality’ – If a dispute which is not capable of settlement
      by arbitration is the subject-matter of the award or if the award is
G
      in conflict with public policy of India, the award is liable to be set
      aside – The conclusion of the Division Bench that the award of the
      arbitral tribunal suffers from patent illegality and shocks the
      conscience of the court is erroneous – Judgment of the Division
      Bench of the High Court set aside and the arbitral award in the
H     favour of the appellant is restored.
                                         984
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                  985
                RAIL CORPORATION LTD.

     Allowing Civil Appeal No.5627 of 2021 and dismissing Civil        A
Appeal No.5628 of 2021, the Court
      HELD: 1.1 A cumulative reading of the UNCITRAL Model
Law and Rules, the legislative intent with which the Arbitration
and Conciliation Act, 1996 is made, Section 5 and Section 34 of
the 1996 Act would make it clear that judicial interference with       B
the arbitral awards is limited to the grounds in Section 34. While
deciding applications filed under Section 34 of the Act, courts
are mandated to strictly act in accordance with and within the
confines of Section 34, refraining from appreciation or re-
appreciation of matters of fact as well as law. [Para 22][1004-E-F]
                                                                       C
      Uttarakhand Purv Sainik Kalyan Nigam Limited. v.
      Northern Coal Field Limited (2020) 2 SCC 455; Bhaven
      Construction Through Authorised Signatory Premjibhai
      K. Shah v. Executive Engineer Sardar Sarovar Narmada
      Nigam Ltd. and Another 2021 SCC OnLine SC 8;
      Rashtriya Ispat Nigam Limited v. Dewan Chand Ram                 D
      Saran (2012) 5 SCC 306 : [2012] 4 SCR 122 – relied
      on.
      Ssangyong Engineering and Construction Company
      Limited v. National Highways Authority of India (NHAI)
      (2019) 15 SCC 131 : [2019] 7 SCR 522 – referred to.              E

      1.2 The limited grounds available to courts for annulment
of arbitral awards are well known to legally trained minds.
However, the difficulty arises in applying the well-established
principles for interference to the facts of each case that come up
before the courts. There is a disturbing tendency of courts setting    F
aside arbitral awards, after dissecting and reassessing factual
aspects of the cases to come to a conclusion that the award needs
intervention and thereafter, dubbing the award to be vitiated by
either perversity or patent illegality, apart from the other grounds
available for annulment of the award. This approach would lead         G
to corrosion of the object of the 1996 Act and the endeavours
made to preserve this object, which is minimal judicial
interference with arbitral awards. That apart, several judicial
pronouncements of this Court would become a dead letter if

                                                                       H
986            SUPREME COURT REPORTS                      [2021] 5 S.C.R.


A     arbitral awards are set aside by categorising them as perverse or
      patently illegal without appreciating the contours of the said
      expressions. [Para 24][1007-H; 1008-A-D]
             1.3 Patent illegality should be illegality which goes to the
      root of the matter. In other words, every error of law committed
B     by the arbitral tribunal would not fall within the expression ‘patent
      illegality’. Likewise, erroneous application of law cannot be
      categorised as patent illegality. In addition, contravention of law
      not linked to public policy or public interest is beyond the scope
      of the expression ‘patent illegality’. What is prohibited is for
      courts to re-appreciate evidence to conclude that the award suffers
C     from patent illegality appearing on the face of the award, as courts
      do not sit in appeal against the arbitral award. The permissible
      grounds for interference with a domestic award under Section
      34(2-A) on the ground of patent illegality is when the arbitrator
      takes a view which is not even a possible one, or interprets a
D     clause in the contract in such a manner which no fair-minded or
      reasonable person would, or if the arbitrator commits an error of
      jurisdiction by wandering outside the contract and dealing with
      matters not allotted to them. An arbitral award stating no reasons
      for its findings would make itself susceptible to challenge on this
      account. The conclusions of the arbitrator which are based on no
E     evidence or have been arrived at by ignoring vital evidence are
      perverse and can be set aside on the ground of patent illegality.
      Also, consideration of documents which are not supplied to the
      other party is a facet of perversity falling within the expression
      ‘patent illegality’. [Para 25][1008-D-G]
F           1.4 Section 34 (2) (b) refers to the other grounds on which
      a court can set aside an arbitral award. If a dispute which is not
      capable of settlement by arbitration is the subject-matter of the
      award or if the award is in conflict with public policy of India, the
      award is liable to be set aside. Explanation (1), amended by the
G     2015 Amendment Act, clarified the expression ‘public policy of
      India’ and its connotations for the purposes of reviewing arbitral
      awards. It has been made clear that an award would be in conflict
      with public policy of India only when it is induced or affected by
      fraud or corruption or is in violation of Section 75 or Section 81

H
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                      987
                RAIL CORPORATION LTD.

of the 1996 Act, if it is in contravention with the fundamental            A
policy of Indian law or if it is in conflict with the most basic notions
of morality or justice. [Para 26][1008-H; 1009-A-B]
      Ssangyong Engineering and Construction Company
      Limited v. National Highways Authority of India
      (NHAI)(2019) 15 SCC 131 : [2019] 7 SCR 522;                          B
      Renusagar Power Co. Ltd. v. General Electric Co. 1994
      Supp (1) SCC 644 : [1993] 3 Suppl. SCR 22 – referred
      to.
       2.1 As there is no ambiguity in the findings of the arbitral
tribunal regarding the time given for curing the defects and the           C
effective date of termination of the Concession Agreement, the
findings of the Division Bench that there is an ambivalence in
the award concerning the date of termination, having a bearing
on the final outcome of the award is not accepted. The arbitral
tribunal in its award clearly held that DMRC failed to cure the
defects before the expiry of 90 days from the initial notice laying        D
down the non-exhaustive list of defects issued on 09.07.2012.
The said conclusion is the outcome of interpretation of Article
29.5.1 of the Concession Agreement by the tribunal. An attempt
was made by the Counsel for the Respondent to impress upon
this Court that as the termination notice would become effective           E
only after 90 days from the date of its issue, i.e., 08.10.2012,
DMRC could avail this period as well to address the defects and
if the defects stood cured or effective steps were taken within
this additional 90-day period, the termination notice became
defunct and should not be effectuated. Construction of a provision
of the Concession Agreement is within the domain of the arbitral           F
tribunal. The view taken by the arbitral tribunal that the defects
have to be cured within 90 days from the date of the cure notice,
failing which DAMEPL is entitled to terminate the Concession
Agreement, is a possible interpretation of Article 29.5.1. The
findings of the arbitral tribunal are not interfered with on this          G
point, even assuming a different view can be taken on a reading
of the said Article. [Para 31][1012-F-H; 1013-A-D]
      2.2 The arbitral tribunal was called upon by the parties to
decide whether there was a breach of the Concession Agreement
                                                                           H
988            SUPREME COURT REPORTS                      [2021] 5 S.C.R.


A     due to the fault of DMRC and whether the defects pointed out by
      DAMEPL were cured within the period specified in the notice
      dated 09.07.2012. Safety of the AMEL was not an issue that fell
      for determination by the arbitral tribunal, though DAMEPL had
      insisted on not continuing operations of the Line citing safety
      concerns arising from the defects in its structural integrity. It is
B
      no doubt true that the Commissioner is the competent authority
      to determine the safety of the AMEL. It is also beyond cavil that
      the Commissioner would not have granted permission to restart
      the AMEL unless it was of the opinion that restarting of
      commercial operations would not pose a danger to the public.
C     However, the certificate by itself cannot come to the rescue of
      DMRC to show that the defects pointed out by DAMEPL were
      cured within the expiry of 90 days from 09.07.2012. The finding
      of the arbitral tribunal that the defects were not cured is one of
      fact which cannot be interfered with by the court. [Para 33][1014-
      C-F]
D
             2.3 The CMRS certificate was relied upon by DMRC before
      the arbitral tribunal as a strong piece of evidence to support its
      case that the defects were cured. DMRC did not contend before
      the tribunal that the CMRS certificate is binding and is conclusive
      of the defects being cured/effective steps taken to cure the
E     defects. The conditions imposed by the Commissioner relating
      to speed restrictions and close monitoring of the Line, according
      to the tribunal, support the contention of DAMEPL that the
      defects were not fully cured. The issue before the tribunal was
      whether the defects were cured within 90 days from the notice
F     dated 09.07.2012 and the certificate dated 18.01.2013 is relevant
      for deciding the said issue. The High Court’s view that the issue
      of the CMRS certificate being dealt with separately has a bearing
      on the tribunal’s determination of the validity of the termination
      notice cannot be accepted. The members of the arbitral tribunal,
      nominated in accordance with the agreed procedure between the
G     parties, are engineers and their award is not meant to be
      scrutinised in the same manner as one prepared by legally trained
      minds. In any event, it cannot be said that the view of the tribunal
      is perverse. Therefore, the High Court’s opinion that the award

H
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                    989
                RAIL CORPORATION LTD.

of the tribunal on the legality of the termination notice is vitiated    A
due to the vice of perversity cannot be accepted. [Para 34][1014-
F-H; 1015-A-B]
      2.4 The Division Bench referred to various factors leading
to the termination notice, to conclude that the award shocks the
conscience of the court. The discussion in the impugned                  B
judgement amounts to appreciation or re- appreciation of the facts
which is not permissible under Section 34 of the 1996 Act. The
Division Bench further held that the fact of the AMEL being
operated without any adverse event for a period of more than
four years since the date of issuance of the CMRS certificate,
was not given due importance by the arbitral tribunal. As the            C
arbitrator is the sole judge of the quality as well as the quantity of
the evidence, the task of being a judge on the evidence before
the tribunal does not fall upon the court in exercise of its
jurisdiction under Section 34. On the basis of the issues submitted
by the parties, the arbitral tribunal framed issues for consideration    D
and answered the said issues. Subsequent events need not be
taken into account. [Para 35][1015-B-E]
      2.5 The conclusion of the Division Bench that the award of
the arbitral tribunal suffers from patent illegality and shocks the
conscience of the court is held to be erroneous. [Para 36][1015-         E
E-F]
      2.6 The tribunal focused on two components of Termination
Payment, which are ‘Debt Due’, and 130 % of the ‘Adjusted
Equity’. The tribunal was correct in holding that the amount of
Rs.611.95 crore advanced by DAMEPL’s promoter would qualify              F
for inclusion under the definition of ‘Equity’ on a plain reading of
the said definition. Construction of the contract is within the
jurisdiction of the tribunal and merely because another view is
possible, the court cannot interfere with such construction and
substitute its own view. [Para 39][1018-F-G; 1019-A-B]
                                                                         G
      2.7 The opinion of the tribunal is that the amount of
Rs.611.95 crore was an amount advanced by DAMEPL’s promoter
which was not disputed by DMRC. The submission advanced by
DMRC, that it was only the equity share capital as is understood
within the meaning of the Companies Act, 2013 which is liable to
be paid by DMRC under Article 29.5.2, was rejected by the                H
990           SUPREME COURT REPORTS                      [2021] 5 S.C.R.


A     Ttribunal. The view taken by the tribunal that the amount
      contributed by a member of the consortium or by shareholders
      to meet the ‘Concessionaire’s Capital Costs’ in any form,
      including where such funds are classified as subordinated debt,
      cannot be treated as ‘Subordinated Debt’ in terms of its definition
      in the Concession Agreement, is a reasonable and possible view.
B
      On the other hand, the Division Bench of the High Court relied
      upon the board resolution dated 16.03.2011 and held that the
      tribunal ought not to have treated the said amount as ‘Equity’
      after the share application money was converted into
      subordinated debt. After a detailed consideration of the relevant
C     clauses of the Concession Agreement, the High Court held that
      the tribunal had committed a serious error in its tabulation of
      ‘Adjusted Equity’ by completely ignoring the evidence on record.
      [Para 41][1019-G-H; 1020-A-C]
            2.8 Even assuming the view taken by the High Court is not
D     incorrect, a possible view expressed by the tribunal on
      construction of the terms of the Concession Agreement cannot
      be substituted by the High Court. This view is in line with the
      understanding of Section 28(3) of the 1996 Act as a ground for
      setting aside the arbitral award. No case has been made out by
      the High Court to establish violation of Section 28(3). Having
E     carefully examined the Concession Agreement, the findings
      recorded by the tribunal and the findings recorded by the Division
      Bench, it cannot be held that the opinion of the tribunal on
      inclusion of Rs.611.95 crore under ‘Equity’ is a perverse view. It
      cannot be said that the tribunal did not consider the evidence on
F     record, especially the resolution dated 16.03.2011 passed by
      DAMEPL’s board of directors. Also, there is no fault with the
      approach of the tribunal that the understanding of the term equity
      as per the Companies Act, 2013 is not relevant for the purposes
      of determining ‘Adjusted Equity’ in light of the express definition
      of the term in the Concession Agreement. The support placed
G     by the Division Bench on the interpretation of Section 28(1)(a) of
      the 1996 Act as adopted in Associate Builders’s case is, therefore,
      no longer good law. The findings of the High Court are set aside
      and the award by the tribunal in respect of the computation of
      Termination Payment under Clause 29.5.2 is upheld.
      [Para 42][1020-C-H]
H
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                   991
                RAIL CORPORATION LTD.

      Associate Builders v. Delhi Development Authority                 A
      (2015) 3 SCC 49 : [2014] 13 SCR 895 – held not good
      law.
      Ssangyong Engineering and Construction Company
      Limited v. National Highways Authority of India
      (NHAI)(2019) 15 SCC 131 : [2019] 7 SCR 522 –                      B
      referred to.
      2.9 As regards the ground of challenge in SLP(c) No. 8311
of 2019, as the participation of DAMEPL in several meetings
held after issuance of the termination notice dated 09.07.2012
and its decision to continue operating the AMEL was without             C
prejudice, the tribunal rejected the submission of DMRC that
the doctrine of waiver applied and that DAMEPL was estopped
from terminating the Concession Agreement after having actively
participated in the process of rectifying the defects pointed out.
The Division Bench of the High Court approved the said finding
on the ground that the decision of the tribunal could not be held       D
to be flawed within the limited scrutiny afforded to courts under
Section 34 of the 1996 Act. The Division Bench of the High Court
rightly refrained from interfering with the findings on waiver by
the tribunal. The prayer for a direction to DAMEPL for specific
performance of its obligations under the Concession Agreement           E
to operate the AMEL was refused by the tribunal. The Division
Bench of the High Court in its judgment observed that the said
findings had not been challenged before the High Court.
Therefore, there is no reason for this Court to adjudicate on the
point of specific performance of the Concession Agreement.
[Para 43, 44][1021-B-E]                                                 F

      2.10 The tribunal awarded interest in accordance with the
terms of the Concession Agreement on termination payment.
DMRC contended before the High Court that the award in respect
of interest had to be set aside on the ground that it would result
in unjust enrichment. After a thorough consideration of Article         G
29.8 and Article 36.2.6.1 of the Concession Agreement, the High
Court has rightly refused to interfere with the findings by the
tribunal relating to interest and there is no cause for interference.
The judgment of the Division Bench of the High Court is set
aside. [Para 45, 46][1021-E-G]                                          H
992            SUPREME COURT REPORTS                          [2021] 5 S.C.R.


A           State of Rajasthan v. Puri Construction Co. Ltd. and
            Another (1994) 6 SCC 485 : [1994] 3 Suppl. SCR 616
            – referred to.
                              Case Law Reference
      (2020) 2 SCC 455                  relied on                Para 23
B
      [2012] 4 SCR 122                  relied on                Para 23
      [2019] 7 SCR 522                  referred to              Para 23
      [1993] 3 Suppl. SCR 22            referred to              Para 26
      [1994] 3 Suppl. SCR 616           referred to              Para 35
C
      [2014] 13 SCR 895                 held not good law        Para 42
            CIVIL APPELLATE JURISDICTION : Civil Appeal No.5627
      of 2021.
            From the Judgment and Order dated 15.01.2019 of the High Court
D     of Delhi at New Delhi in FAO (OS) (COMM) No.58 of 2018.
            With
            Civil Appeal No.5628 of 2021.
            Tushar Mehta, SG, Harish N. Salve, J. J. Bhatt, P. S. Narsimha,
E     Parag Tripathi, Ajit Sinha, Sr. Advs., Ms. Anjali Chandurkar, Mahesh
      Agarwal, Ms. Megha Mehta, Nishant Rao, Biswabara Dash, E. C.
      Agrawala, Tarun Johri, Advs. for the appearing parties.
            The Judgment of the Court was delivered by
            L. NAGESWARA RAO, J.
F
            Leave granted.
             1. Whether in exercise of its power under Section 37 of the
      Arbitration and Conciliation Act, 1996 (hereinafter, ‘the 1996 Act’), the
      Division Bench of the Delhi High Court was right in interfering with the
G     award dated 11.05.2017 passed by the Arbitral Tribunal in favour of the
      Appellant -Delhi Airport Metro Express Pvt. Ltd. (hereinafter, ‘DAMEPL’
      or the ‘Concessionaire’), is the question that arises for consideration in
      these Appeals.
             2. Delhi Metro Rail Corporation Ltd. (hereinafter, ‘DMRC’), a
H     joint venture of the Government of India and the Government of National
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                            993
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

Capital Territory of Delhi, proposed implementation of the Airport Metro         A
Express Line project in New Delhi, from New Delhi Railway Station to
Dwarka Sector 21 via Indira Gandhi International Airport, New Delhi
(hereinafter, ‘AMEL’). The approximate length of the project was 22.7
kilometers. It was decided to develop the project by engaging a
concessionaire for financing, design, procurement, installation of all
                                                                                 B
systems (including but not limited to rolling stock, overhead electrification,
track, signaling and telecommunication, ventilation and air conditioning,
automatic fare collection, baggage check-in and handling, depot and other
facilities). DMRC had to undertake design and construction of basic
civil structure for the project, which was in the nature of a public private
partnership.                                                                     C
       3. The bid of a consortium comprising Reliance Energy Limited
(renamed as Reliance Infrastructure Limited) and M/s Construcciones
y Auxiliar de Ferrocarriles, S.A. was accepted by DMRC, by issuing a
letter of acceptance on 21.01.2008. Thereafter, on 25.08.2008, a
Concession Agreement was entered into between DMRC and DAMEPL                    D
for design, installation, commissioning, operation and maintenance of the
AMEL. It was agreed between the parties that all civil works as well as
appointment of consultants, land acquisition and other clearances from
the Government and other authorities have to be obtained by DMRC
and the design, supply, installation, testing and commissioning of various
systems like rolling stock, power supply, overhead equipment, signalling,        E
track system, platform, screen doors, ventilation, architectural finishing
etc. were to be provided by DAMEPL. As the work could not be
completed in time, extensions were granted and finally, safety clearances
were obtained from the Commissioner of Metro Railway Safety
(hereinafter, the ‘CMRS’ or ‘Commissioner’) on 10.01.2011. The date              F
of commercial operation was achieved on 23.02.2011.
       4. On 22.03.2012, DAMEPL requested DMRC for a joint
inspection of viaduct and its bearings before expiry of the defect liability
period of the civil contractors. Another letter was written by DAMEPL
on 23.05.2012, complaining of issues relating to the design and quality in       G
the installation of viaduct bearings. It was mentioned in the said letter
that there were signs of girders having sunk at some locations as a result
of deformations/cracks. DMRC responded to the said letter of DAMEPL
on 08.06.2012 by which DAMEPL was informed that inspections were
carried out at the locations pointed out by DAMEPL and no bearings
                                                                                 H
994             SUPREME COURT REPORTS                              [2021] 5 S.C.R.


A     were found damaged. However, DMRC admitted that grouting material
      filled above/below the bearings was damaged/loosened for which action
      would be taken to repair them on priority. Due to the said defects, DMRC
      advised DAMEPL to impose speed restrictions as deemed necessary in
      the interest of safety.
B             5. The Ministry of Urban Development, Government of India
      convened a meeting of all the stakeholders on 02.07.2012. The views of
      all the parties relating to the defects were obtained and a Joint Inspection
      Committee was formed. An interim report was submitted by the Joint
      Inspection Committee after inspection on 4 th & 5 th July, 2012.
      Subsequently, DAMEPL stopped operations of the Line on 08.07.2012.
C
             6. A notice was issued by DAMEPL on 09.07.2012, asking DMRC
      to cure the defects in DMRC’s works within a period of 90 days from
      the date of the notice, failing which it shall be treated as a breach having
      Material Adverse Effect on the Concessionaire under the Concession
      Agreement. In the said notice dated 09.07.2012, ‘a non-exhaustive list
D     of defects’ was set out by DAMEPL. Thereafter, a number of meetings
      were conducted between the parties which were attended by SYSTRA,
      the original design consultant for the viaduct sections. It appears from
      the record that DMRC had also engaged some other agencies for carrying
      out the repair work.
E            7. DAMEPL issued a notice dated 08.10.2012 terminating the
      Concession Agreement as, according to it, the defects that were pointed
      out in the notice dated 09.07.2012 were not cured within a period of 90
      days, resulting in an Event of Default under the Concession Agreement.
      DMRC invoked arbitration under Article 36.2 of the Concession
F     Agreement on 23.10.2012. On 22.01.2013, the Line was restarted with
      reduced speed after a certificate sanctioning resumption was issued by
      the Commissioner on 18.01.2013. According to DAMEPL, it agreed to
      operate the Line only as an agent in public interest and on instructions of
      DMRC, although DAMEPL’s stance was not accepted by DMRC.
      DAMEPL stopped its operations on 30.06.2013 and handed over the
G     Line to DMRC on the next day.
             8. At this stage, it is relevant to refer to Article 36 of the Concession
      Agreement which refers to dispute resolution. Article 36.2.2, read with
      Article 36.2.3, provides that all disputes, whatsoever arising between
      the parties, out of, touching upon or relating to construction, measuring,
H
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                           995
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

operation or effect of the Concession Agreement or the breach thereof,          A
shall be settled through arbitration by reference to a sole arbitrator, where
the total value of claims do not exceed Rs.1,500,000/-. Beyond this limit,
the dispute shall be referred to three arbitrators who will be selected
from a panel of engineers with requisite qualifications and professional
experience relevant in the field to which the Concession Agreement
                                                                                B
relates. The panel shall be from serving or retired engineers of government
departments or of public sector.
       9. The main issue that arose for determination before the Arbitral
Tribunal constituted under the Concession Agreement is the validity of
the termination notice dated 08.10.2012. DMRC claimed that the
termination notice issued by DAMEPL is illegal, as DMRC had taken               C
various steps honouring its obligations under the Concession Agreement.
A direction was sought from the Arbitral Tribunal to DAMEPL to take
over operations of the AMEL under the Concession Agreement, and in
the alternative, to grant compensation of Rs.3,173 crore with interest of
18% per annum. Further monetary reliefs were sought by DMRC. The                D
claim of compensation sought by DMRC was dependent on the
determination of the main issue, i.e., the validity of the termination notice
dated 08.10.2012.DMRC also raised an issue on the real motive of
DAMEPL to terminate the Concession Agreement. DAMEPL justified
the termination as being in conformity with the Concession Agreement
and consequently, filed a counter claim seeking an amount of Rs.3,470           E
crore as termination payment along with interest and further amounts as
detailed in the counter claim, on the ground that DMRC did not cure the
defects in the civil structure in terms of the cure notice dated 09.07.2012.
 As DMRC did not comply with its obligations under Article 29.5.1(i),
DAMEPL justified the termination notice dated 08.10.2012 and the                F
consequent claim of termination payment from DMRC under Article
29.5.2.
       10. The Arbitral Tribunal formulated the following primary issues
for consideration in relation to the termination notice dated 08.10.2012: -
      “i) Were there any defects in the civil structure of the airport          G
      metro line?
      (ii) If there were defects, did such defects have a material
      adverse effect on the performance of the obligation of
      DAMEPL under CA?
                                                                                H
996             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A           (iii) If there were defects in the civil structure, which had a
            material adverse effect on the performance of the obligations
            under the CA by DAMEPL, have such defects been cured by
            DMRC and / or have any effective steps been taken within a
            period of 90 days from the date of notice by DAMEPL to cure
            the defects by DMRC and thus were DMRC in breach of the
B
            CA as per 29.5.1 (i)?”
             11. In assessing whether the defects pointed out by DAMEPL
      were cured and/or effective steps to cure them were taken by DMRC
      within the time stipulated in the notice dated 09.07.2012, the Arbitral
      Tribunal undertook an in-depth analysis of the defects in the civil structure
C     and steps taken for their repair/rectification. Insofar as the existence of
      defects is concerned, the Arbitral Tribunal concluded that there were as
      many as 1551 cracks in 367 girders, i.e., 72 % of the girders were affected
      by such cracks. Reports of inspections conducted at the behest of DMRC,
      giving mapping data of the cracks, were relied upon by the Tribunal to
D     hold that such cracks were spread in a large number of girders. The
      Tribunal referred to the meeting dated 02.07.2012 conducted by the
      Ministry of Urban Development during which the Managing Director,
      DMRC expressed his views that the cracks occurred during “lowering”
      and not during operations. The evidence of Mr. Muls of Systra was
      considered by the Arbitral Tribunal to hold that they were not sure of the
E     cause of the cracks. On account of such large numbers of cracks in the
      base slab of the pre-stressed concrete girders in about a year of train
      operation, coupled with unreliable measurement of crack depth and non-
      serious inspection of the repairs by an agency appointed by DMRC, the
      Arbitral Tribunal was of the opinion that these defects adversely impacted
F     the integrity of the structure. As effective steps were not taken within
      the cure period of 90 days, the Tribunal held that DMRC was in breach
      of the Concession Agreement, resulting in Material Adverse Effect on
      the Concessionaire.
            12. As far as twist in the girders were concerned, the Arbitral
G     Tribunal found that there were about 80 girders with twists varying
      between 10 to 20 mm which had not been rectified and no effective
      steps were taken to cure the defects in such girders. The defects pointed
      out by DAMEPL regarding gaps between the shear key and the girder
      being more than 25 mm and between 10 mm to 25 mm were not addressed
      and only gaps below 10 mm were addressed by some grinding, detailed
H
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                          997
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

methodology for which was not brought out by DMRC in its evidence,             A
as per the findings of the Arbitral Tribunal. Therefore, the Tribunal
concluded that these defects were neither cured nor effective steps
taken by DMRC within the cure period up to 08.10.2012, constituting a
material breach on the part of DMRC. On the basis of the above findings
and findings in relation to other defects, deficiencies and constraints in
                                                                               B
the civil structure of the AMEL which are not referred to herein, the
Arbitral Tribunal concluded that the defects had not been cured within
the cure period of 90 days from 09.07.2012 nor had effective steps been
taken to cure such defects. Ergo, the termination notice issued by
DAMEPL on 08.10.2012 was valid.
       13. Having decided on the validity of the termination notice, the       C
Tribunal went on to consider certain legal issues so as to determine
questions around specific performance of the contract, or alternatively,
the award of damages and the outcome of the counter claim filed by
DAMEPL. One such issue considered by the Arbitral Tribunal was
whether the issue of certificate by the Commissioner on 18.01.2013,            D
giving clearance for resuming operations of the AMEL, showed that the
defects were duly cured. After examining the certificate issued by the
Commissioner, the Arbitral Tribunal held that while the Commissioner
had sanctioned resumption of services, certain conditions were imposed,
essentially relating to the restriction of speed up to 50 km per hour, which
had a material bearing on the prime purpose of the AMEL intended to            E
serve as a high-speed connectivity line. Moreover, the Commissioner
himself recognized that the operation of the Line had to be regularly
monitored. The subsequent operation of the Line by DMRC was found
to be not relevant for determining the validity of the termination notice
dated 09.07.2012. The Arbitral Tribunal answered this issue in favour          F
of DAMEPL. On consideration of the counter claim of DAMEPL, the
principal issue that came up before the Arbitral Tribunal was on
determination of the amount of Termination Payment payable by DMRC
under the Concession Agreement. In this regard, the Tribunal had to
determine the quantum payable under each component of Termination
Payment, one of which was ‘Adjusted Equity’. DAMEPL sought payment             G
of an amount of Rs.3,470 crore as Termination Payment. In this total, an
amount of Rs.685 crore, which had been infused by DAMEPL’s promoter,
was factored in by DAMEPL for the purposes of calculating ‘Adjusted
Equity’. Relying on the relevant clauses of the Concession Agreement,
the Tribunal first sought to determine the portion of funds that would         H
998             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


A     qualify as ‘Equity’ under the Concession Agreement, which would then
      be used for arriving at the figure of ‘Adjusted Equity’. Out of Rs.685
      crore which was sought to be slotted under the head ‘Equity’ by
      DAMEPL, an amount of Rs.611.95 crore was determined to be ‘Equity’
      by the Tribunal, on the basis of the evidence produced and the construction
      of the relevant provisions of the Concession Agreement. Thereafter, the
B
      Tribunal worked out ‘Adjusted Equity’ at Rs.983.02 crore and awarded
      a total amount of Rs.2782.33 crore, along with further interest, as
      Termination Payment to be made to DAMEPL.
             14. DMRC filed a petition under Section 34 of the 1996 Act for
      setting aside the award of the Arbitral Tribunal dated 11.05.2017 in the
C     Delhi High Court, which was dismissed by the learned Single Judge of
      the High Court by a judgement dated 06.03.2018 observing that grounds
      for interference had not been made out by DMRC. The learned Single
      Judge held that the findings recorded by the Arbitral Tribunal on facts,
      law and interpretation of the Concession Agreement were all within the
D     realm of the Arbitral Tribunal and they needed no intervention by the
      Court exercising its power under Section 34 of the 1996 Act. He was
      also of the view that the Court cannot substitute its view when there are
      two views possible and the view taken by the Arbitral Tribunal is a
      plausible one.
E            15. DMRC filed an appeal under Section 37 of the 1996 Act read
      with Section 13 of the Commercial Courts, Commercial Division and
      Commercial Appellate Division of High Courts Act, 2015 (the title since
      amended to Commercial Courts Act, 2015), challenging the correctness
      of the judgment passed by the learned Single Judge on 06.03.2018
      dismissing the objections filed by DMRC under Section 34 of the 1996
F     Act. The Division Bench reversed the judgement of the learned Single
      Judge and allowed the appeal filed by DMRC. The award passed by the
      Arbitral Tribunal was partly set aside. The parties were left to invoke
      the arbitration clause for adjudication of the issues that were not decided
      by the Division Bench. The judgement of the Division Bench dated
G     15.01.2019 is assailed in these Appeals.
             16. DMRC has also filed SLP (C) No.8311 of 2019 challenging
      the correctness of the aforesaid judgement of the Division Bench in
      relation to the issues of grant of interest, waiver of the termination notice
      due to DAMEPL’s conduct of operating the project for more than five
H     months from 22.01.2013, refusal by the Division Bench to grant relief of
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                          999
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

specific performance of the Concession Agreement and non-consideration         A
of the issue pertaining to the real reason for the termination of the
Concession Agreement by DAMEPL.
     Reasons given by the Division Bench for setting aside the
award
        17. The Division Bench of the High Court held that the award of        B
the Arbitral Tribunal had recorded two different termination dates. As
the Tribunal had based its reasoning on the validity of the termination
notice on two different dates leading to confusion and ambivalence as to
the termination notice and the date of termination, the award was found
to be suffering from the vices of perversity, irrationality and patent         C
illegality. The High Court observed that in deciding the question on defects
in the civil structure and whether effective steps were taken to cure the
defects, the Arbitral Tribunal had committed serious error by holding,
without ‘reason’, that the vital evidence of the sanction granted by the
CMRS for resumption of commercial operations of the AMEL and the
fact that DMRC had successfully operated the AMEL from 30.06.2013              D
till the date of the award without any adverse incident were
inconsequential. The High Court found fault with the Arbitral Tribunal in
virtually negating the certificate issued by the CMRS under the Delhi
Metro Railway (Operation and Maintenance) Act, 2002 (hereinafter,
‘the Delhi Metro Act’) and held that the cumulative effect of the findings     E
of the award on this issue ‘shocked the conscience of the court’.
       18. On the issue of Adjusted Equity, while considering the approach
taken by the Arbitral Tribunal for computation of the amounts payable
under Article 29.5.2, the High Court was of the opinion that the Tribunal’s
reasoning was completely flawed and perverse. The High Court ruled             F
that the reasoning adopted by the Tribunal was patently illegal and the
conclusion reached after doing so, was one which no reasonable person
would have come to. According to the High Court, the treatment of
Rs.611.95 crore as ‘Equity’ by the Tribunal, on the ground that such a
project could not have been executed with only Rs.1 lakh as equity funded
by DAMEPL’s promoter (in terms of share capital), was based on an              G
assumption that the debt-to-equity ratio is commonly 60:40 or 80:20,
contrary to the evidence on record. This was held to be an egregious
mistake committed by the Tribunal. The High Court also found fault
with the award which ignored the resolution passed by the board of
directors of DAMEPL on 16.03.2011, by which the amount of Rs. 611.95           H
1000                SUPREME COURT REPORTS                        [2021] 5 S.C.R.


 A     crore was converted to subordinated debt. The High Court held that
       ‘Adjusted Equity’ under the Concession Agreement does not contemplate
       funds recognized as subordinated debt to be treated as ‘Equity’. With
       respect to the interpretation of the various provisions of the Concession
       Agreement and the resultant conclusions on ‘Adjusted Equity’, the High
       Court held that the findings of the Tribunal on this issue were in violation
 B
       of Sections 28(1)(a) and 28(3) of the 1996 Act, as elaborated in Associate
       Builders v.Delhi Development Authority1, as contractual provisions
       had been interpreted in a way no fair-minded and reasonable person
       would.
             19. In light of the reasons mentioned, the High Court set aside the
 C     conclusions of the Arbitral Tribunal on the validity of the termination
       notice and that Rs.611.95 crore was ‘Equity’ for the purpose of Article
       29.5.2 of the Concession Agreement. Consequently, the award of
       Rs.2,782.33 crore to DAMEPL was set aside. In view of the above
       findings, the High Court considered the direction for payment of interest
 D     to have become infructuous. The High Court felt that it would be
       inappropriate to hear the parties on the issue of restitution at that stage
       and granted liberty to the parties to move appropriate applications under
       the 1996 Act to seek remedies available to them.
                Contours of the Court’s power to review arbitral awards
 E            20. The 1996 Act was enacted to consolidate and amend the law
       relating to domestic arbitration, international commercial arbitration and
       enforcement of foreign arbitral awards and also to define the law relating
       to conciliation and for matters connected therewith, by taking into account
       the United Nations Commission on International Trade Law
 F     (UNCITRAL) Model Law on International Commercial Arbitration and
       the UNCITRAL Conciliation Rules. One of the principal objectives of
       the 1996 Act is to minimize the supervisory role of courts in the arbitral
       process. With respect to Part I of the 1996 Act, Section 5 imposes a bar
       on intervention by a judicial authority except where provided for,
       notwithstanding anything contained in any other law for the time being in
 G     force. An application for setting aside an arbitral award can only be
       made in accordance with provisions of Section 34 of the 1996 Act.
       Relevant provisions of Section 34 (as they were prior to the Arbitration
       and Conciliation (Amendment) Act, 2015) read as under:-
       1
           (2015) 3 SCC 49
 H
DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                  1001
   RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

   “34. Application for setting aside arbitral award. — (1)           A
   Recourse to a Court against an arbitral award may be made
   only by an application for setting aside such award in
   accordance with sub-section (2) and sub-section (3).
   (2) An arbitral award may be set aside by the Court only if—
      (a) the party making the application furnishes proof that—      B

         (i) a party was under some incapacity, or
         (ii) the arbitration agreement is not valid under the law
         to which the parties have subjected it or, failing any
         indication thereon, under the law for the time being in      C
         force; or
         (iii) the party making the application was not given
         proper notice of the appointment of an arbitrator or of
         the arbitral proceedings or was otherwise unable to
         present his case; or                                         D
         (iv) the arbitral award deals with a dispute not
         contemplated by or not falling within the terms of the
         submission to arbitration, or it contains decisions on
         matters beyond the scope of the submission to
         arbitration:
                                                                      E
               Provided that, if the decisions on matters
         submitted to arbitration can be separated from those
         not so submitted, only that part of the arbitral award
         which contains decisions on matters not submitted to
         arbitration may be set aside; or
                                                                      F
         (v) the composition of the arbitral tribunal or the
         arbitral procedure was not in accordance with the
         agreement of the parties, unless such agreement was in
         conflict with a provision of this Part from which the
         parties cannot derogate, or, failing such agreement, was
         not in accordance with this Part; or                         G

      (b) the Court finds that—
         (i) the subject-matter of the dispute is not capable of
         settlement by arbitration under the law for the time being
         in force, or                                                 H
1002             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


 A                  (ii) the arbitral award is in conflict with the public policy
                    of India.
                    Explanation.—Without prejudice to the generality of
                    sub-clause (ii), it is hereby declared, for the avoidance
                    of any doubt, that an award is in conflict with the public
 B                  policy of India if the making of the award was induced
                    or affected by fraud or corruption or was in violation
                    of section 75 or section 81.
                    …”
              21. An amendment was made to Section 34 of the 1996 Act by
 C     the Arbitration and Conciliation (Amendment) Act, 2015 (hereinafter,
       ‘the 2015 Amendment Act’). A perusal of the statement of objects and
       reasons of the 2015 Amendment Act would disclose that the amendment
       to the 1996 Act became necessary in view of the interpretation of the
       provisions of the 1996 Act by courts in certain cases which had resulted
 D     in delay of disposal of arbitration proceedings and increase in interference
       by courts in arbitration matters, which had the tendency to defeat the
       object of the 1996 Act. Initially, the matter was referred to the Law
       Commission of India to review the shortcomings in the 1996 Act in detail.
       The Law Commission of India submitted its 176th Report, recommending
       various amendments to the 1996 Act. However, the Justice Saraf
 E     Committee on Arbitration constituted by the Government, was of the
       view that the proposed amendments gave room for substantial intervention
       by the court and were also contentious. Thereafter, on reference, the
       Law Commission undertook a comprehensive study of the amendments
       proposed by the Government, keeping in mind the views of the Justice
 F     Saraf Committee and other stakeholders. The 246th Report of the Law
       Commission was submitted on 05.08.2014. Acting on the
       recommendations made by the Law Commission in its 246th Report,
       amendments by way of the 2015 Amendment Act were made to several
       provisions of the 1996 Act, including Section 34. The amended Section
       34 reads as under: -
 G
             “34. Application for setting aside arbitral award. — (1)
             Recourse to a Court against an arbitral award may be made
             only by an application for setting aside such award in
             accordance with sub-section (2) and sub-section (3).
             (2) An arbitral award may be set aside by the Court only if—
 H
DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                     1003
   RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

      (a) the party making the application furnishes proof that—         A
         (i) a party was under some incapacity, or
         (ii) the arbitration agreement is not valid under the law
         to which the parties have subjected it or, failing any
         indication thereon, under the law for the time being in
         force; or                                                       B

         (iii) the party making the application was not given
         proper notice of the appointment of an arbitrator or of
         the arbitral proceedings or was otherwise unable to
         present his case; or
                                                                         C
         (iv) the arbitral award deals with a dispute not
         contemplated by or not falling within the terms of the
         submission to arbitration, or it contains decisions on
         matters beyond the scope of the submission to
         arbitration:
                                                                         D
               Provided that, if the decisions on matters
         submitted to arbitration can be separated from those
         not so submitted, only that part of the arbitral award
         which contains decisions on matters not submitted to
         arbitration may be set aside; or
                                                                         E
         (v) the composition of the arbitral tribunal or the
         arbitral procedure was not in accordance with the
         agreement of the parties, unless such agreement was in
         conflict with a provision of this Part from which the
         parties cannot derogate, or, failing such agreement, was
         not in accordance with this Part; or                            F
   (b) the Court finds that—
         (i) the subject-matter of the dispute is not capable of
         settlement by arbitration under the law for the time being
         in force, or
                                                                         G
         (ii) the arbitral award is in conflict with the public policy
         of India.
   Explanation 1. —For the avoidance of any doubt, it is clarified
   that an award is in conflict with the public policy of India,
   only if,—                                                             H
1004             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


 A                  (i) the making of the award was induced or affected by
                    fraud or corruption or was in violation of section 75 or
                    section 81; or
                    (ii) it is in contravention with the fundamental policy of
                    Indian law; or
 B                  (iii) it is in conflict with the most basic notions of morality
                    or justice.
              Explanation 2. —For the avoidance of doubt, the test as to
              whether there is a contravention with the fundamental policy
              of Indian law shall not entail a review on the merits of the
 C            dispute.
              (2-A) An arbitral award arising out of arbitrations other than
              international commercial arbitrations, may also be set aside
              by the Court, if the Court finds that the award is vitiated by
              patent illegality appearing on the face of the award:
                    Provided that an award shall not be set aside merely on
 D
              the ground of an erroneous application of the law or by re-
              appreciation of evidence.
              …”
              22. A cumulative reading of the UNCITRAL Model Law and
       Rules, the legislative intent with which the 1996 Act is made, Section 5
 E
       and Section 34 of the 1996 Act would make it clear that judicial
       interference with the arbitral awards is limited to the grounds in Section
       34. While deciding applications filed under Section 34 of the Act, courts
       are mandated to strictly act in accordance with and within the confines
       of Section 34, refraining from appreciation or re-appreciation of matters
 F     of fact as well as law. (See: Uttarakhand Purv Sainik Kalyan Nigam
       Limited. v. Northern Coal Field Limited. 2,Bhaven Construction
       Through Authorised Signatory Premjibhai K. Shah v. Executive
       Engineer Sardar Sarovar Narmada Nigam Ltd. and
       Another3andRashtriya Ispat Nigam Limited v. Dewan Chand Ram
       Saran4).
 G
              23. For a better understanding of the role ascribed to courts in
       reviewing arbitral awards while considering applications filed under
       2
         (2020) 2 SCC 455
       3
         2021 SCC OnLine SC 8
       4
         (2012) 5 SCC 306
 H
    DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                       1005
       RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

Section 34 of the 1996 Act, it would be relevant to refer to a judgment of     A
this Court in Ssangyong Engineering and Construction Company
Limited v. National Highways Authority of India (NHAI) 5 wherein
R.F. Nariman, J. has in clear terms delineated the limited area for judicial
interference, taking into account the amendments brought about by the
2015 Amendment Act. The relevant passages of the judgment in
                                                                               B
Ssangyong (supra) are noted as under: -
         “34. What is clear, therefore, is that the expression “public
         policy of India”, whether contained in Section 34 or in Section
         48, would now mean the “fundamental policy of Indian law”
         as explained in paras 18 and 27 of Associate
         Builders [Associate Builders v. DDA, (2015) 3 SCC 49: (2015)          C
         2 SCC (Civ) 204] i.e. the fundamental policy of Indian law
         would be relegated to “Renusagar” understanding of this
         expression. This would necessarily mean that Western
         Geco [ONGC v. Western Geco International Ltd., (2014) 9
         SCC 263 : (2014) 5 SCC (Civ) 12] expansion has been done              D
         away with. In short, Western Geco [ONGC v. Western Geco
         International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC (Civ)
         12] ,as explained in paras 28 and 29 of Associate
         Builders [Associate Builders v. DDA, (2015) 3 SCC 49 :
         (2015) 2 SCC (Civ) 204], would no longer obtain, as under
         the guise of interfering with an award on the ground that the         E
         arbitrator has not adopted a judicial approach, the Court’s
         intervention would be on the merits of the award, which cannot
         be permitted post amendment. However, insofar as principles
         of natural justice are concerned, as contained in Sections 18
         and 34(2)(a)(iii) of the 1996 Act, these continue to be grounds       F
         of challenge of an award, as is contained in para 30
         of Associate Builders [Associate Builders v. DDA, (2015) 3
         SCC 49 : (2015) 2 SCC (Civ) 204] .
         35. It is important to notice that the ground for interference
         insofar as it concerns “interest of India” has since been             G
         deleted, and therefore, no longer obtains. Equally, the ground
         for interference on the basis that the award is in conflict with
         justice or morality is now to be understood as a conflict with
         the “most basic notions of morality or justice”. This again
5
    (2019) 15 SCC 131                                                          H
1006     SUPREME COURT REPORTS                        [2021] 5 S.C.R.


 A     would be in line with paras 36 to 39 of Associate
       Builders [Associate Builders v. DDA, (2015) 3 SCC 49 :
       (2015) 2 SCC (Civ) 204] , as it is only such arbitral awards
       that shock the conscience of the court that can be set aside
       on this ground.
 B     36. Thus, it is clear that public policy of India is now
       constricted to mean firstly, that a domestic award is contrary
       to the fundamental policy of Indian law, as understood in
       paras 18 and 27 of Associate Builders [Associate
       Builders v. DDA, (2015) 3 SCC 49: (2015) 2 SCC (Civ) 204],
       or secondly, that such award is against basic notions of justice
 C     or morality as understood in paras 36 to 39 of Associate
       Builders [Associate Builders v. DDA, (2015) 3 SCC 49 :
       (2015) 2 SCC (Civ) 204] . Explanation 2 to Section 34(2)(b)(ii)
       and Explanation 2 to Section 48(2)(b)(ii) was added by the
       Amendment Act only so that Western Geco [ONGC v. Western
 D     Geco International Ltd., (2014) 9 SCC 263 : (2014) 5 SCC
       (Civ) 12] ,as understood in Associate Builders [Associate
       Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204],
       and paras 28 and 29 in particular, is now done away with.
       37. Insofar as domestic awards made in India are concerned,
 E     an additional ground is now available under sub-section (2-
       A), added by the Amendment Act, 2015, to Section 34. Here,
       there must be patent illegality appearing on the face of the
       award, which refers to such illegality as goes to the root of
       the matter but which does not amount to mere erroneous
       application of the law. In short, what is not subsumed within
 F     “the fundamental policy of Indian law”, namely, the
       contravention of a statute not linked to public policy or public
       interest, cannot be brought in by the backdoor when it comes
       to setting aside an award on the ground of patent illegality.
       38. Secondly, it is also made clear that reappreciation of
 G     evidence, which is what an appellate court is permitted to do,
       cannot be permitted under the ground of patent illegality
       appearing on the face of the award.
       39. To elucidate, para 42.1 of Associate Builders [Associate
       Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204],
 H
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                          1007
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

      namely, a mere contravention of the substantive law of India,            A
      by itself, is no longer a ground available to set aside an
      arbitral award. Para 42.2 of Associate Builders [Associate
      Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204],
      however, would remain, for if an arbitrator gives no reasons
      for an award and contravenes Section 31(3) of the 1996 Act,
                                                                               B
      that would certainly amount to a patent illegality on the face
      of the award.
      40. The change made in Section 28(3) by the Amendment Act
      really follows what is stated in paras 42.3 to 45 in Associate
      Builders [Associate Builders v. DDA, (2015) 3 SCC 49 :
      (2015) 2 SCC (Civ) 204] , namely, that the construction of               C
      the terms of a contract is primarily for an arbitrator to decide,
      unless the arbitrator construes the contract in a manner that
      no fair-minded or reasonable person would; in short, that
      the arbitrator’s view is not even a possible view to take. Also,
      if the arbitrator wanders outside the contract and deals with            D
      matters not allotted to him, he commits an error of jurisdiction.
      This ground of challenge will now fall within the new ground
      added under Section 34(2-A).
      41. What is important to note is that a decision which is
      perverse, as understood in paras 31 and 32 of Associate                  E
      Builders [Associate Builders v. DDA, (2015) 3 SCC 49 :
      (2015) 2 SCC (Civ) 204] , while no longer being a ground
      for challenge under “public policy of India”, would certainly
      amount to a patent illegality appearing on the face of the
      award. Thus, a finding based on no evidence at all or an
      award which ignores vital evidence in arriving at its decision           F
      would be perverse and liable to be set aside on the ground of
      patent illegality. Additionally, a finding based on documents
      taken behind the back of the parties by the arbitrator would
      also qualify as a decision based on no evidence inasmuch as
      such decision is not based on evidence led by the parties,               G
      and therefore, would also have to be characterised as
      perverse.”
       24. This Court has in several other judgments interpreted Section
34 of the 1996 Act to stress on the restraint to be shown by courts while
examining the validity of the arbitral awards. The limited grounds available   H
1008             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


 A     to courts for annulment of arbitral awards are well known to legally
       trained minds. However, the difficulty arises in applying the well-
       established principles for interference to the facts of each case that
       come up before the courts. There is a disturbing tendency of courts
       setting aside arbitral awards, after dissecting and reassessing factual
       aspects of the cases to come to a conclusion that the award needs
 B
       intervention and thereafter, dubbing the award to be vitiated by either
       perversity or patent illegality, apart from the other grounds available for
       annulment of the award. This approach would lead to corrosion of the
       object of the 1996 Act and the endeavours made to preserve this object,
       which is minimal judicial interference with arbitral awards. That apart,
 C     several judicial pronouncements of this Court would become a dead
       letter if arbitral awards are set aside by categorising them as perverse
       or patently illegal without appreciating the contours of the said
       expressions.
              25. Patent illegality should be illegality which goes to the root of
 D     the matter. In other words, every error of law committed by the Arbitral
       Tribunal would not fall within the expression ‘patent illegality’. Likewise,
       erroneous application of law cannot be categorised as patent illegality.
       In addition, contravention of law not linked to public policy or public
       interest is beyond the scope of the expression ‘patent illegality’. What is
       prohibited is for courts to re-appreciate evidence to conclude that the
 E     award suffers from patent illegality appearing on the face of the award,
       as courts do not sit in appeal against the arbitral award. The permissible
       grounds for interference with a domestic award under Section 34(2-A)
       on the ground of patent illegality is when the arbitrator takes a view
       which is not even a possible one, or interprets a clause in the contract in
 F     such a manner which no fair-minded or reasonable person would, or if
       the arbitrator commits an error of jurisdiction by wandering outside the
       contract and dealing with matters not allotted to them. An arbitral award
       stating no reasons for its findings would make itself susceptible to
       challenge on this account. The conclusions of the arbitrator which are
       based on no evidence or have been arrived at by ignoring vital evidence
 G     are perverse and can be set aside on the ground of patent illegality. Also,
       consideration of documents which are not supplied to the other party is
       a facet of perversity falling within the expression ‘patent illegality’.
              26. Section 34 (2) (b) refers to the other grounds on which a court
       can set aside an arbitral award. If a dispute which is not capable of
 H     settlement by arbitration is the subject-matter of the award or if the
    DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                        1009
       RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

award is in conflict with public policy of India, the award is liable to be     A
set aside. Explanation (1), amended by the 2015 Amendment Act,
clarified the expression ‘public policy of India’ and its connotations for
the purposes of reviewing arbitral awards. It has been made clear that
an award would be in conflict with public policy of India only when it is
induced or affected by fraud or corruption or is in violation of Section 75
                                                                                B
or Section 81 of the 1996 Act, if it is in contravention with the fundamental
policy of Indian law or if it is in conflict with the most basic notions of
morality or justice. In Ssangyong (supra), this Court held that the meaning
of the expression ‘fundamental policy of Indian law’ would be in
accordance with the understanding of this Court in Renusagar Power
Co. Ltd. v. General Electric Co.6 In Renusagar (supra), this Court              C
observed that violation of the Foreign Exchange Regulation Act, 1973, a
statute enacted for the ‘national economic interest’, and disregarding
the superior courts in India would be antithetical to the fundamental
policy of Indian law. Contravention of a statute not linked to public policy
or public interest cannot be a ground to set at naught an arbitral award
                                                                                D
as being discordant with the fundamental policy of Indian law and neither
can it be brought within the confines of ‘patent illegality’ as discussed
above. In other words, contravention of a statute only if it is linked to
public policy or public interest is cause for setting aside the award as
being at odds with the fundamental policy of Indian law. If an arbitral
award shocks the conscience of the court, it can be set aside as being in       E
conflict with the most basic notions of justice. The ground of morality in
this context has been interpreted by this Court to encompass awards
involving elements of sexual morality, such as prostitution, or awards
seeking to validate agreements which are not illegal but would not be
enforced given the prevailing mores of the day.7
                                                                                F
       27. In light of the principles elucidated herein for interference
with an arbitral award by a court in exercise of its jurisdiction under
Section 34 of the 1996 Act, we proceed to consider the questions that
arise in these Appeals as to whether the Division Bench of the High
Court was right in setting aside the award of the Arbitral Tribunal dated
11.05.2017.                                                                     G
   Validity of the termination notice and consequences of the
CMRS sanction

6
    1994 Supp (1) SCC 644
7
    Ssangyong (supra)                                                           H
1010            SUPREME COURT REPORTS                           [2021] 5 S.C.R.


 A             28. Mr. Harish Salve, learned Senior Counsel appearing for the
       Appellant (DAMEPL), submitted that the High Court committed an error
       in setting aside the award of the Arbitral Tribunal by deviating from the
       well-settled principles for interference under Sections 34 and 37 of the
       1996 Act. The findings recorded by the Arbitral Tribunal in relation to
       the existence of defects in the civil structure and failure on the part of
 B
       DMRC in curing those defects/not taking effective steps to cure the
       defects are findings of fact which cannot be made subject to review by
       the court exercising its jurisdiction under Section 34. He asserted that
       interpretation of the provisions of the Concession Agreement is within
       the domain of the Arbitral Tribunal and even if such interpretation is not
 C     the most accurate interpretation in the opinion of the court, the award
       cannot be set aside if the Arbitral Tribunal has taken a possible view. He
       contended that the certificate issued by the CMRS, which was relied
       upon by DMRC, was considered by the Tribunal to rightly conclude that
       the conditions imposed for restarting the AMEL showed that the defects
       were not cured. He further submitted that the cure notice was issued on
 D
       09.07.2012 demanding the rectification of defects within a period of 90
       days from the date of the notice, as per the Concession Agreement.
       After the expiry of 90 days, the termination notice dated 08.10.2012 had
       been issued. He stated that there cannot be any doubt that the defects
       had to be cured within 90 days from the date of the cure notice. He
 E     emphasized that the observations of the High Court as regards confusion
       in the mind of the Arbitral Tribunal regarding the date of the termination
       notice are unfounded. The relevant portions of the award were shown
       to the Court to argue that the Arbitral Tribunal was clear in its mind that
       the defects had to be cured within 90 days from the date of cure notice
       dated 09.07.2012. On the defects not being cured within the 90-day
 F
       period, the termination notice was issued on 08.10.2012, with the effective
       date of termination as 07.01.2013. The further submission made on behalf
       of DAMEPL is that the subsequent successful operation of the AMEL
       for nearly four years is not relevant for adjudication of the disputes
       between the parties by the Arbitral Tribunal. Finally, according to Mr.
 G     Salve, the High Court committed a palpable error in setting aside the
       award.
              29. Mr. P.S. Narasimha and Mr. Parag Tripathi, learned Senior
       Counsel appearing for DMRC, on the other hand, supported the judgment
       of the Division Bench of the High Court by arguing that the award is
 H     contrary to public policy. Mr. Narasimha relied upon the Delhi Metro
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                        1011
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

Act and the Rules made thereunder to submit that the CMRS is the sole        A
authority to determine the safety of the Metro Railway and the certificate
issued by the Commissioner on 18.01.2013 is conclusive proof of the
fact that the defects pointed out by DAMEPL had been rectified. It was
contended on behalf of DMRC that the period for curing the defects did
not lapse on expiry of 90 days from the initial notice dated 09.07.2012
                                                                             B
but extended for another 90 days from the termination notice dated
08.10.2012. According to the Respondent, a serious error was committed
by the Arbitral Tribunal in its interpretation of Article 29.5.1 of the
Concession Agreement. Abundant material placed by DMRC to show
effective steps were taken to cure the defects was not considered by
the Arbitral Tribunal. The Commissioner in exercise of his powers            C
conferred by the Delhi Metro Act permitted the opening of the AMEL
on 18.01.2013 after considering all safety aspects and the AMEL has
been in operation since then without any adverse event. The subsequent
smooth functioning of the AMEL is a relevant consideration which was
ignored by the Arbitral Tribunal. DAMEPL’s participation in several
                                                                             D
meetings that were conducted which led to inspections and steps taken
to address the defects as well as the AMEL being run by DAMEPL
from 22.01.2013 to 30.06.2013 would show that even DAMEPL was
aware that effective steps had been taken to cure the defects.
       30. Termination by DAMEPL for DMRC Event of Default is
dealt with in Article 29.5.1 which reads as under: -                         E

      “29.5 Termination for DMRC Event of Default
      29.5.1 The Concessionaire may after giving 90 (ninety) days
      notice in writing to DMRC terminate this Agreement upon the
      occurrence and continuation of any of the following events             F
      (each a “DMRC Event of Default”), unless any such DMRC
      Event of Default has occurred as a result of Concessionaire
      Event of Default or due to a Force Majeure Event.
      (i)    DMRC is in breach of this Agreement and such breach
             has a Material Adverse Effect on the Concessionaire             G
             and DMRC has failed to cure such breach or take
             effective steps for curing such breach within 90 (ninety)
             days of receipt of notice in this behalf from the
             Concessionaire;

                                                                             H
1012             SUPREME COURT REPORTS                            [2021] 5 S.C.R.


 A           (ii)    DMRC repudiates this Agreement or otherwise evidences
                     an irrevocable intention not to be bound by this
                     Agreement;
             (iii)   GoI or GNCTD or any Governmental Agency have by
                     an act of commission or omission created circumstances
 B                   that have a Material Adverse Effect on the performance
                     of its obligations by the Concessionaire and have failed
                     to cure the same within 90 (ninety) days of receipt of
                     notice by DMRC in this behalf from the Concessionaire;
             (iv)    DMRC has delayed any payment that has fallen due
 C                   under this Agreement if such delay exceeds 90 (ninety)
                     days.”
              31. By referring to certain paragraphs of the award, the Division
       Bench of the High Court held that there was confusion in the mind of
       the Arbitral Tribunal relating to the actual date of termination, which
 D     would have a material bearing on the exegesis of Article 29.5.1. The
       confusion around the date of termination is highlighted by the High Court
       by referring to the award of the Arbitral Tribunal in which it was held
       that the defects were not cured within the 90-day period from the date
       of the cure notice dated 09.07.2012. However, in paragraphs 128, 130
       and 131, the Arbitral Tribunal, while considering the counter claim, referred
 E     to 07.01.2013 as the date of termination of the Concession Agreement.
       It is clear from a careful examination of the award that the Arbitral
       Tribunal had in precise terms held that the defects had to be cured within
       90 days from the date of the cure notice dated 09.07.2012. Further, the
       Arbitral Tribunal held that the termination notice dated 08.10.2012 was
 F     issued as defects were not cured. The Tribunal expressed its view that
       consequently, the effective date of termination was 07.01.2013, which is
       90 days from the termination notice. As there is no ambiguity in the
       findings of the Arbitral Tribunal regarding the time given for curing the
       defects and the effective date of termination of the Concession
       Agreement, we are not in agreement with the findings of the Division
 G     Bench that there is an ambivalence in the award concerning the date of
       termination, having a bearing on the final outcome of the award. The
       ancillary issue that arises for consideration is whether the period for
       curing the defects is 180 days or 90 days under Article 29.5.1 of the
       Concession Agreement. The Arbitral Tribunal in its award has clearly
 H     held that DMRC failed to cure the defects before the expiry of 90 days
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                         1013
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

from the initial notice laying down the non-exhaustive list of defects        A
issued on 09.07.2012. The said conclusion is the outcome of interpretation
of Article 29.5.1 of the Concession Agreement by the Tribunal. An
attempt was made by the learned Senior Counsel appearing for the
Respondent to impress upon this Court that as the termination notice
would become effective only after 90 days from the date of its issue,
                                                                              B
i.e., 08.10.2012, DMRC could avail this period as well to address the
defects and if the defects stood cured or effective steps were taken
within this additional 90-day period, the termination notice became defunct
and should not be effectuated. Construction of a provision of the
Concession Agreement is within the domain of the Arbitral Tribunal.
The view taken by the Arbitral Tribunal that the defects have to be           C
cured within 90 days from the date of the cure notice, failing which
DAMEPL is entitled to terminate the Concession Agreement, is a possible
interpretation of Article 29.5.1. We refuse to interfere with the findings
of the Arbitral Tribunal on this point, even assuming a different view can
be taken on a reading of the said Article.
                                                                              D
       32. The High Court was of the view that the Tribunal committed
a grave error in ignoring the CMRS certificate, as the Tribunal lost sight
of the binding nature of the certificate. According to the Division Bench,
the Arbitral Tribunal went wrong in considering the issue of the CMRS
certificate as a separate issue, distinct from the questions pertaining to
the termination of the Concession Agreement. The Delhi Metro Act              E
was promulgated for the operation, maintenance and regulation of the
working of the metro railway in the National Capital Region, metropolitan
city and metropolitan area. The Commissioner of Metro Railway Safety,
appointed under Section 7 of the said Act, has the duty to inspect the
metro railway with a view to determine whether it is fit to be opened for     F
the public carriage of passengers and report thereon to the Central
Government as required thereunder. Section 15 of the Delhi Metro Act
provides that before granting sanction to the opening of the metro railway
by the Central Government under Section 14, a report has to be obtained
from the Commissioner certifying fitness of the metro railway so as not
to be of any danger to the public. Rule 11 of the Opening of Delhi Metro      G
Railway for Public Carriage of Passengers Rules, 2002 imposes a duty
on the Commissioner to inquire into all relevant matters concerning safety
before coming to a conclusion that the metro railway should be opened.
Sanction to open the metro railway line for public carriage of passengers
is granted by the Central Government after considering the report of the      H
1014             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


 A     Commissioner on the fitness and safety aspects. The contention on behalf
       of DMRC is that the certificate issued by the Commissioner is binding
       on the Arbitral Tribunal and the Tribunal could not have taken a different
       view. In addition thereto, the certificate is conclusive of the fact that
       there were no defects in the civil structure, as otherwise, the Commissioner
       would not have permitted the AMEL to be opened. On the basis of the
 B
       certificate issued by the Commissioner, the Respondent has argued that
       all defects pointed out by DAMEPL had been cured. In any event,
       effective steps had been taken to cure the defects by periodical meetings
       and inspections being held.
              33. The Arbitral Tribunal was called upon by the parties to decide
 C     whether there was a breach of the Concession Agreement due to the
       fault of DMRC and whether the defects pointed out by DAMEPL were
       cured within the period specified in the notice dated 09.07.2012. Safety
       of the AMEL was not an issue that fell for determination by the Arbitral
       Tribunal, though DAMEPL had insisted on not continuing operations of
 D     the Line citing safety concerns arising from the defects in its structural
       integrity. It is no doubt true that the Commissioner is the competent
       authority to determine the safety of the AMEL. It is also beyond cavil
       that the Commissioner would not have granted permission to restart the
       AMEL unless it was of the opinion that restarting of commercial operations
       would not pose a danger to the public. However, the certificate by itself
 E     cannot come to the rescue of DMRC to show that the defects pointed
       out by DAMEPL were cured within the expiry of 90 days from 09.07.2012.
       The finding of the Arbitral Tribunal that the defects were not cured is
       one of fact which cannot be interfered with by the court.
             34. The CMRS certificate dated 18.01.2013 was relied upon by
 F     DMRC before the Arbitral Tribunal as a strong piece of evidence to
       support its case that the defects were cured. DMRC did not contend
       before the Tribunal that the CMRS certificate is binding and is conclusive
       of the defects being cured/effective steps taken to cure the defects.
       The conditions imposed by the Commissioner relating to speed restrictions
 G     and close monitoring of the Line, according to the Tribunal, support the
       contention of DAMEPL that the defects were not fully cured. The issue
       before the Tribunal was whether the defects were cured within 90 days
       from the notice dated 09.07.2012 and the certificate dated 18.01.2013 is
       relevant for deciding the said issue. We are not in agreement with the
       High Court’s view that the issue of the CMRS certificate being dealt
 H
    DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                            1015
       RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

with separately has a bearing on the Tribunal’s determination of the                A
validity of the termination notice. The members of the Arbitral Tribunal,
nominated in accordance with the agreed procedure between the parties,
are engineers and their award is not meant to be scrutinised in the same
manner as one prepared by legally trained minds. In any event, it cannot
be said that the view of the Tribunal is perverse. Therefore, we do not
                                                                                    B
concur with the High Court’s opinion that the award of the Tribunal on
the legality of the termination notice is vitiated due to the vice of perversity.
       35. The Division Bench referred to various factors leading to the
termination notice, to conclude that the award shocks the conscience of
the court. The discussion in paragraph 97 of the impugned judgement
amounts to appreciation or re-appreciation of the facts which is not                C
permissible under Section 34 of the 1996 Act. The Division Bench further
held that the fact of the AMEL being operated without any adverse
event for a period of more than four years since the date of issuance of
the CMRS certificate, was not given due importance by the Arbitral
Tribunal. As the arbitrator is the sole judge of the quality as well as the         D
quantity of the evidence, the task of being a judge on the evidence before
the Tribunal does not fall upon the court in exercise of its jurisdiction
under Section 34.8 On the basis of the issues submitted by the parties,
the Arbitral Tribunal framed issues for consideration and answered the
said issues. Subsequent events need not be taken into account.
                                                                                    E
      36. For the aforementioned reasons, the conclusion of the Division
Bench that the award of the Arbitral Tribunal suffers from patent illegality
and shocks the conscience of the court is held to be erroneous.
          Adjusted Equity
     37. Article 29.5.2 of the Concession Agreement which deals with                F
Termination Payment is as follows:-
          “29.5.2 Upon termination by the Concessionaire on account
          of DMRC Event of Default, DMRC shall pay to the
          Concessionaire, by way of Termination Payment, an amount
          equal to                                                                  G
          a) Debt Due;
          b) 130 % of the Adjusted Equity;

8
    State of Rajasthan v. Puri Construction Co. Ltd. and Another (1994) 6 SCC 485
                                                                                    H
1016              SUPREME COURT REPORTS                       [2021] 5 S.C.R.


 A           c) Depreciated Value of the Project Assets, if any, acquired
             and installed on the Project after the 10th anniversary of the
             COD.”
              38. It is relevant to note the definitions of ‘Adjusted Equity’,
       ‘Concessionaire’s Capital Costs’, ‘Debt Due’, ‘Equity’, and ‘Subordinate
 B     debt’ as provided in the Concession Agreement, which read as follows:-
             “Adjusted Equity” means the Equity funded in Indian Rupees
             and adjusted on the first day of the current month (the
             “Reference Date”), in the manner set forth below, to reflect
             the change in its value on account of depreciation and
 C           variations in WPI, and for any Reference Date occurring:
             a)     on or before COD, the Adjusted Equity shall be a sum
                    equal to the Equity funded in Indian Rupees and
                    expended on the Project, revised to the extent of one
                    half of the variation in WPI occurring between the first
 D                  day of the month of Appointed Date and the Reference
                    Date;
             b)     from COD and until the 4th (fourth) anniversary thereof,
                    an amount equal to the Adjusted Equity as on COD
                    shall be deemed to be the base (the “Base Adjusted
 E                  Equity”) and the Adjusted Equity hereunder shall be a
                    sum equal to the Base Adjusted Equity, revised at the
                    commencement of each month following COD to the
                    extent of variation in WPI occurring between COD and
                    the Reference Date;
             c)     after the 4th (fourth) anniversary of COD, the Adjusted
 F
                    Equity hereunder shall be a sum equal to the Base
                    Adjusted Equity, reduced by 0.42% (zero point four two
                    per cent) (This number shall be substituted in each case
                    by the product of 100 divided by the number of months
                    comprising the Concession Period. For example, the
 G                  figure for a 20 year Concession Period shall be 100/
                    240 = 0.416 rounded off to decimal points i.e. 0.42)
                    thereof at the commencement of each month following
                    the 4th (fourth) anniversary of the Project Completion
                    Date and the amount so arrived at shall be revised to
                    the extent of variation in WPI occurring between COD
 H
DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                 1017
   RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

         and the Reference Date; and the aforesaid shall apply,      A
         mutatis mutandis, to the Equity funded in Indian Rupees.
         For the avoidance of doubt, the Adjusted Equity shall,
         in the event of Termination, be computed as on the
         Reference Date immediately preceding the Termination
         Date; provided that no reduction in the Base Adjusted
                                                                     B
         Equity shall be made for a period equal to the duration,
         if any, for which the Concession Period is extended,
         but the revision on account of WPI shall continue to be
         made.”
   “Concessionaire’s Capital Costs” means following:
      •Prior to COD, the cost of the Concessionaire’s Works as       C
      set forth in the Financing Documents plus any further
      additional capital cost for any Change of Scope instructed
      since the finalisation of the Financing Documents; and
      • After COD, the actual capital cost of the Concessionaire’s
      Works upon Project Completion as certified by the Statutory    D
      Auditors.”
   “Debt Due” means the aggregate of the following sums
   expressed in Indian Rupees outstanding on the Transfer Date:
   a)    the principal amount of the debt provided by the Senior
         Lenders under the Financing Agreements for financing        E
         the Total Project Cost (the “principal”) but excluding
         any part of the principal that had fallen due for
         repayment two years prior to the Termination Date;
   b)    all accrued interest, financing fees and charges payable
         under the Financing Agreements on, or in respect of,        F
         the debt referred to in Sub-clause (a) above until the
         Transfer Date but excluding (i) any interest, fees or
         charges that had fallen due one year prior to the
         Transfer Date, (ii) any penal interest or charges payable
         under the Financing Agreements to any Senior Lender,
         and (iii) any pre-payment chares in relation to             G
         accelerated repayment of debt except where such
         charges have arisen due to Authority Default; and
   c)    any Subordinated Debt which is included in the
         Financial Package and disbursed by lenders for
         financing the Total Project Cost.”                          H
1018            SUPREME COURT REPORTS                           [2021] 5 S.C.R.


 A             “Equity” means the sum expressed in Indian Rupees
               representing the equity share capital of the Concessionaire
               and shall include the funds advanced by any Member of the
               Consortium or by any of its shareholders to the Concessionaire
               for meeting the equity component of the Concessionaire’s
               Capital Costs.”
 B
               “Subordinated Debt” means the aggregate of the following
               sums expressed in Indian Rupees or in the currency of debt,
               as the case may be, outstanding as on the date of termination:
               a)    the principal amount of debt provided by lenders or the
                     Concessionaire for meeting the Concessionaire’s Capital
 C                   Cost and subordinated to the financial assistance
                     provided by the Senior Lenders; and
               b)    all accrued interest on the debt referred to in Sub-clause
                     (a) above but restricted to the lesser of actual interest
                     rate and a rate equal to 5% (five per cent) above the
 D                   Bank Rate in case of loans expressed in Indian Rupees
                     and lesser of the actual interest rate and six-month
                     LIBOR (London Inter Bank Offer Rate) plus 2% (two
                     per cent) in case of loans expressed in foreign currency,
                     but does not include any interest that had fallen due
                     one year prior to the Termination Date;
 E
                     sprovided that if all or any part of the Subordinated
                     Debt is convertible into Equity at the option of the
                     lenders and/ or the Concessionaire, it shall for the
                     purposes of this Agreement be deemed to be
                     Subordinated Debt even after such conversion and the
 F                   principal thereof shall be dealt with as if such
                     conversion had not been undertaken.”
               39. The Tribunal focused on two components of Termination
       Payment, which are (i) ‘Debt Due’, and (ii) 130 % of the ‘Adjusted
       Equity’. According to the Appellant, the Division Bench committed an
       error in concluding that the expression ‘Adjusted Equity’ in the Concession
 G
       Agreement should be calculated by taking into account only the share
       capital of DAMEPL. The Appellant contended that the Tribunal had
       rightly held that the expression ‘Adjusted Equity’ should include the
       money brought in by DAMEPL’s promoter and had fairly concluded
       that the amount of Rs.611.95 crore was used as expenses, thereby
 H     qualifying as ‘Concessionaire’s Capital Costs’ under the Concession
 DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                        1019
    RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

Agreement. The Tribunal was correct in holding that the amount of            A
Rs.611.95 crore advanced by DAMEPL’s promoter would qualify for
inclusion under the definition of ‘Equity’ on a plain reading of the said
definition. Construction of the contract is within the jurisdiction of the
Tribunal and merely because another view is possible, the court cannot
interfere with such construction and substitute its own view.
                                                                             B
       40. On the other hand, it was contended by DMRC that the amount
of Rs.611.95 crore was recorded as ‘share application money’ in the
balance sheet of DAMEPL as on 31.03.2010. However, the said amount
was shown as subordinated debt in the balance sheet as on 31.03.2011.
The Respondent referred to the resolution passed by the board of directors
of DAMEPL on 16.03.2011, in which a decision was taken to convert            C
the share application money into subordinated debt. DMRC urged that
the conversion of the share application money as subordinated debt was
a calculated move on the part of DAMEPL. If the share application
money had been allowed to retain the nature of equity, DAMEPL would
have lost the entire amount in the event of termination of the Concession
Agreement by DMRC for Concessionaire Event of Default in terms of            D
Article 29.1.1. After electing to convert the share application money
into subordinated debt, DAMEPL should not be permitted to claim that
for the purposes of computation of ‘Adjusted Equity’, the said amount
be treated as ‘Equity’. It was further argued on behalf of the Respondent
that no material was produced by DAMEPL to show that the amount of           E
Rs. 611.95 crore was actually used for ‘Concessionaire’s Capital Costs’.
Reference was also made to the testimony of one of the witnesses
produced by DAMEPL to contend that the amount of Rs.611.95 crore
cannot be treated as equity in accordance with the provisions of the
Companies Act, 2013. DMRC contended that the High Court aptly set
aside the findings recorded by the Tribunal in respect of computation of     F
‘Adjusted Equity’.
       41. We do not intend to re-examine the entire material on record
for the purpose of deciding whether the High Court was right in reversing
the conclusion of the Tribunal in relation to computation of the amount
under Article 29.5.2 of the Concession Agreement. The opinion of the         G
Tribunal is that the amount of Rs.611.95 crore was an amount advanced
by DAMEPL’s promoter which was not disputed by DMRC. The
contention advanced by DMRC, that it was only the equity share capital
as is understood within the meaning of the Companies Act, 2013 which
is liable to be paid by DMRC under Article 29.5.2, was rejected by the
                                                                             H
1020             SUPREME COURT REPORTS                           [2021] 5 S.C.R.


 A     Tribunal. The view taken by the Tribunal that the amount contributed by
       a member of the consortium or by shareholders to meet the
       ‘Concessionaire’s Capital Costs’ in any form, including where such funds
       are classified as subordinated debt, cannot be treated as ‘Subordinated
       Debt’ in terms of its definition in the Concession Agreement, is a
       reasonable and possible view. On the other hand, the Division Bench of
 B     the High Court relied upon the board resolution dated 16.03.2011 and
       held that the Tribunal ought not to have treated the said amount as ‘Equity’
       after the share application money was converted into subordinated debt.
       After a detailed consideration of the relevant clauses of the Concession
       Agreement, the High Court held that the Tribunal had committed a serious
 C     error in its tabulation of ‘Adjusted Equity’ by completely ignoring the
       evidence on record.
               42. Even assuming the view taken by the High Court is not
       incorrect, we are afraid that a possible view expressed by the Tribunal
       on construction of the terms of the Concession Agreement cannot be
       substituted by the High Court. This view is in line with the understanding
 D     of Section 28(3) of the 1996 Act as a ground for setting aside the arbitral
       award, as held in Associate Builders (supra) and thereafter upheld in
       Ssangyong (supra). No case has been made out by the High Court to
       establish violation of Section 28(3). Having carefully examined the
       Concession Agreement, the findings recorded by the Tribunal and the
 E     findings recorded by the Division Bench, we are not in a position to hold
       that the opinion of the Tribunal on inclusion of Rs.611.95 crore under
       ‘Equity’ is a perverse view. It cannot be said that the Tribunal did not
       consider the evidence on record, especially the resolution dated 16.03.2011
       passed by DAMEPL’s board of directors. We also do not find fault with
       the approach of the Tribunal that the understanding of the term equity as
 F     per the Companies Act, 2013 is not relevant for the purposes of
       determining ‘Adjusted Equity’ in light of the express definition of the
       term in the Concession Agreement. As has been held in Ssangyong
       (supra), mere contravention of substantive law as elucidated in Associate
       Builders (supra) is no longer a ground available to set aside an arbitral
 G     award. The support placed by the Division Bench on the interpretation
       of Section 28(1)(a) of the 1996 Act as adopted in Associate Builders
       (supra) is, therefore, no longer good law. In view of the foregoing, we
       set aside the findings of the High Court and uphold the award by the
       Tribunal in respect of the computation of Termination Payment under
       Clause 29.5.2.
 H
  DELHI AIRPORT METRO EXPRESS PVT. LTD. v. DELHI METRO                           1021
     RAIL CORPORATION LTD. [L. NAGESWARA RAO, J.]

       Grounds of challenge in SLP (C) No. 8311 of 2019 filed by                 A
DMRC
       43. One of the legal issues considered by the Tribunal is whether
DAMEPL waived their rights to terminate after participating in the
reconciliation process and after operating the AMEL for more than five
months from 22.01.2013 to 30.06.2013. As the participation of DAMEPL             B
in several meetings held after issuance of the termination notice dated
09.07.2012 and its decision to continue operating the AMEL was without
prejudice, the Tribunal rejected the submission of DMRC that the doctrine
of waiver applied and that DAMEPL was estopped from terminating
the Concession Agreement after having actively participated in the
process of rectifying the defects pointed out. The Division Bench of the         C
High Court approved the said finding on the ground that the decision of
the Tribunal could not be held to be flawed within the limited scrutiny
afforded to courts under Section 34 of the 1996 Act. In our view, the
Division Bench of the High Court rightly refrained from interfering with
the findings on waiver by the Tribunal.
                                                                                 D
       44. The prayer for a direction to DAMEPL for specific
performance of its obligations under the Concession Agreement to operate
the AMEL was refused by the Tribunal. The Division Bench of the High
Court in its judgment observed that the said findings had not been
challenged before the High Court. Therefore, there is no reason for this
Court to adjudicate on the point of specific performance of the Concession       E
Agreement.
       45. The Tribunal awarded interest in accordance with the terms
of the Concession Agreement on termination payment. DMRC
contended before the High Court that the award in respect of interest
had to be set aside on the ground that it would result in unjust enrichment.     F
After a thorough consideration of Article 29.8 and Article 36.2.6.1 of
the Concession Agreement, the High Court has rightly refused to interfere
with the findings by the Tribunal relating to interest and we see no cause
for interference.
       46. For the aforementioned reasons, the Appeal filed by DAMEPL
is allowed and the judgment of the Division Bench of the High Court is           G
set aside. The Appeal arising out of SLP(C) No. 8311 of 2019 filed by
DMRC is dismissed.


Nidhi Jain                                                Appeals disposed of.   H


Search Indian case law

Ask in plain English, not just keywords. 25,000 AI words free, no card.

Try "Arbitration"Sign in to search

For a digitally signed copy suitable for filing, refer to the court's own website. Only the court can issue one.